Project updates
Pavement Management Program (PMP)
The updates listed below refer to the Pavement Management Program
(PMP). To find updates regarding other projects, go to major road construction
projects.
September 2010
September 3, 2010
PMP Street Improvement Project
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Seed and sod has been installed at the storm water energy dissipation basin. The
draintile in the bottom of the basin still needs to be installed.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The contractor will be fine grading the road in anticipation of placing pavement. Some
flat concrete sidewalk work remains to be done. The pavement will be placed towards the
end of the week of Labor Day, weather permitting and traffic is anticipated to be
switched to the east side of the road the week of September 13.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue is closed to facilitate the
installation of the large, deep trunk storm sewer. It is anticipated that the new
structures will be completed and shipped to the site by September 10. The week of
September 13 the placement of the structures and pipe work will be underway. Two of the
drainage structures will require a few days of dry weather in order to be placed given
that the 48” and 66” storm lines can carry a lot of water even days after a
rain. The temporary water need is complete and the contractor will start on Tuesday,
September 7 to remove the temporary system.
-
Beard Avenue (from 109th Street to 110th Street)
The final paving is scheduled for Wednesday, September 8, weather permitting.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
Storm sewer installation is complete. The contractor will be rough grading the road
and installing class 5 rock on the road beds.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
Striping of the road is being coordinated with seal coat for W. 86th Street. Striping
of the road between Penn Avenue all the way to Old Shakopee Road is scheduled to begin
on Tuesday, September 7.
-
E. 94th Street (from west of Columbus Avenue to 12th Avenue)
The first lift of pavement is scheduled for Wednesday, September 8, weather
permitting.
-
Oakland Avenue ( from Bishoff Lane to 90th Street)
Curb and gutter installation is scheduled for Tuesday, September 7, weather
permitting.
-
17th Avenue (from 82nd Street to the north)
Centerpoint is working in the area installing new gas main.
-
Clinton Ave Area (from E 79 ½ Street to E 82nd Street and from E 84th Street to
E 86th Street)
Centerpoint continues to work in the area and anticipates being complete with their
work in three weeks.
PMP Street Maintenance Project
-
E. 90th Street (between Stevens Avenue and Portland Avenue)
Staff and the contractor are coordinating the replacement of the trees for the trees
that had to be removed for the project. These trees will be installed sometime during
September if the replacements are coniferous trees and sometime in October if they are
deciduous trees based on the ideal time to plant trees in Minnesota for each species.
-
W. 90th Street (between France Avenue and Penn Avenue)
The signal work is winding down with the pedestrian pushbutton installation being one
of the last remaining items that still needs to occur.
-
89th Area (includes W. 89th Street and Kell Avenue)
This area is paved but still needs sod to be planted which is tentatively planned for
the week of September 7.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe parallel to American Blvd will
continue the next two weeks. Milling and paving of Sheridan, Russell, Queen and W.
81st Street will not occur until after the storm sewer work is completed in the
area.
Washburn, Vincent, Upton and Thomas have been paved. Sod still needs to be planted
in these areas which is tentatively planned for the week of September 7.
Centerpoint Energy also has topsoil and sod restoration that will need to occur in
the area. They anticipate beginning this work sometime after Labor Day. With the
restoration occurring by two different entities it may appear to some residents
that areas have been missed, when actually that is not the case.
August 2010
August 30, 2010
PMP Street Improvement Project
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Seed and sod has been installed at the storm water energy dissipation basin. The
draintile in the bottom of the basin still needs to be installed.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The contractor has obtained a noise variance to allow construction work to begin at 7
am on Saturday, August 28. Concrete work has begun and will continue on Saturday. Once
all the concrete is in place on the east side of Lyndale, the contractor will need to
wait until the concrete develops sufficient strength to work next to it. Likely around
September 2 or 3, weather dependant, the contractor will begin fine grading the road
for the pavement. The pavement will be placed the week of Labor Day and traffic is
anticipated to be switched to the east side of the road on Monday, September 13,
weather permitting.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue is closed to facilitate the
installation of the large, deep trunk storm sewer. Storm sewer is installed up to a
point approximately 200 feet away from the intersection of Penn Avenue and 82nd Street.
Issues with existing utility information not being correctly shown on the as-builts is
causing delays as we must redesign, work with private utilities and reorder materials.
The work at 81st Street and Russell cannot be completed until this connection at Penn
Avenue and 82nd Street is made because otherwise the storm pipe will have no place for
the water to flow. As soon as the Penn Avenue and 82nd Street work is complete we will
be able to connect the upstream storm sewer and complete the construction of Russell
Avenue. There is approximately three weeks of work that includes the rocking of the
road, curb and gutter installation and paving after to storm sewer work is completed.
We anticipate having the storm sewer redesign completed by September 3. A schedule for
the storm sewer work will be developed and shared in an upcoming update either on
September 3 or 10.
-
Beard Avenue (from 109th Street to 110th Street)
The final paving of this road still needs to occur and is scheduled to occur sometime
the week of Labor Day.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
Removals have begun in this area and will continue. Storm sewer construction will
begin Monday, August 30.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
Striping of the road is being coordinated with seal coat for W. 86th Street. The
existing stripes along 86th Street between Humboldt Avenue to Old Shakopee Road have
been ground off with the sealcoat operation to occur the week of August 30th.
-
E. 94th Street (from west of Columbus Avenue to 12th Avenue)
The contractor has obtained a noise variance to allow construction work to begin at 7
am on Saturday, August 28. Concrete work has begun and will continue on Saturday. Once
all the concrete is in place, the contractor will need to wait until the concrete
develops sufficient strength to work next to it. Likely around September 2 or 3,
weather dependant, the contractor will begin fine grading the road for the pavement.
The pavement will be placed the week of Labor Day.
-
Oakland Avenue ( from Bishoff Lane to 90th Street)
Removals have occurred and grading of the road is underway. Grading and installation
of class 5 rock will continue through the week of August 30. Curb and gutter is
expected to be installed towards the end of the week, around September 2 or 3, weather
permitting.
-
17th Avenue (from 82nd Street to the north)
Centerpoint plans on installing new gas main in this area and anticipates having a
crew out at the beginning of September.
-
Clinton Ave Area (from E 79 ½ Street to E 82nd Street and from E 84th Street to
E 86th Street)
Centerpoint plans on moving into this neighborhood the week of August 30 and being
complete with the work by the end of September.
PMP Street Maintenance Project
-
E. 90th Street (between Stevens Avenue and Portland Avenue)
Staff and the contractor are coordinating the replacement of the trees for the trees
that had to be removed for the project. These trees will be installed sometime during
September.
-
W. 90th Street (between France Avenue and Penn Avenue)
The signal work is winding down with the pedestrian pushbutton installation being one
of the last remaining items that still needs to occur.
-
89th Area (includes W. 89th Street and Kell Avenue)
This area is paved but still needs sod to be planted.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
The work of the boring pit is complete for the jacking of the large diameter storm
sewer pipe parallel to American Blvd. Rails will be installed and the jacking will
take approximately three weeks. The slide shoring at the south boring pit at
Russell is being removed. The open cut storm sewer installation south of the boring
pit will also occur during the next three weeks. Milling and paving of Sheridan,
Russell, Queen and W. 81st Street will not occur until after the storm sewer work
is completed in the area.
Milling of Washburn, Vincent, Upton and Thomas is scheduled for Monday, August 30
with paving scheduled for Wednesday, September 1. Topsoil of the boulevards that
were displaced for the work on the City project will be placed on Monday and
Tuesday. Centerpoint Energy also has topsoil and sod restoration that will need to
occur in the area. They anticipate beginning this work sometime after Labor Day.
With the restoration occurring by two different entities it may appear to some
residents that areas have been missed, when actually that is not the case.
August 20, 2010
PMP Street Improvement Project
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
Lyndale Circle
Punch list items remain.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Seed and sod restoration of the storm water energy dissipation basin has begun. The
draintile in the bottom of the basin still needs to be installed.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Storm sewer installation on the east side of the road is complete. The contractor
will continue to grade and subcut and place Class 5 aggregate base. The
intersection of 95th and Lyndale Avenue will be closed on Monday, August 23 so that
the grading and Class 5 rock placement can occur. Concrete work is anticipated to
begin the week of August 23.
Major upcoming milestones for Lyndale Avenue include switching the traffic from the
east side to the west side sometime around Labor Day. The project will reopen to
all lanes of traffic sometime in November. The new signal poles for the
intersection of 95th and Lyndale will be installed sometime in the winter once the
poles arrive. The landscaping and streetscaping work will occur in the spring of
2011. The entire project is on schedule to be completed by June 30, 2011.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue is closed to facilitate the
installation of the large, deep trunk storm sewer. Finishing the inside of the
structures and pouring inverts is scheduled for the week of August 23.
-
Beard Avenue (from 109th Street to 110th Street)
The final paving of this road still needs to occur.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
The gas main has been installed in the area. Centerpoint has a few issues to finish up
before they are complete with the area. The city contractor plans on moving into the
area sometime the week of August 23rd to begin removals.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
The final layer of wear has been placed and the road has been reopened to traffic.
Striping of the road is being coordinated with seal coat for W. 86th Street. The
existing stripes along 86th Street between Humboldt Avenue to Old Shakopee Road will be
ground off during the week of August 23rd with the sealcoat operation to occur the week
of August 30th.
-
E. 94th Street (from west of Columbus Avenue to 12th Avenue)
Storm sewer installation is complete. The contractor has begun to grade the road and
place Class 5 aggregate base. This will continue during the week of August 23rd.
Concrete curb and gutter is also scheduled to be installed for that week.
-
Oakland Avenue ( from Bishoff Lane to 90th Street)
Centerpoint continues to work on installing gas services in the area. Tree removals
have begun in the area. The City’s contractor is going to begin removals on
Oakland the begin later in the week.
-
17th Avenue (from 82nd Street to the north)
Centerpoint plans on installing new gas main in this area sometime during the month of
August, but no specific timeframes have been provided to the City yet.
-
Clinton Ave Area (from E 79 ½ Street to E 82nd Street and from E 84th Street to
E 86th Street)
Centerpoint plans on moving into this neighborhood the week of August 30 and being
complete with the work by the end of September.
PMP Street Maintenance Project
-
E. 90th Street (between Stevens Avenue and Portland Avenue)
With the heavy rain that occurred on Tuesday, August 10 some of the seeded areas have
washed away and will need to be reseeded.
-
W. 90th Street (between France Avenue and Penn Avenue)
The striping of the road is complete. It is a change from the previous existing
condition and will be one lane in each direction with a two way continuous left turn
lane in the middle and bike lanes between France Avenue and Xerxes Avenue. Signal
system modifications at the intersection of 90th Street and France Avenue continue and
will include painting the poles. The signal will be placed on flash between the hours
of 9 am and 3 pm at various times to complete the work.
-
89th Area (includes W. 89th Street and Kell Avenue)
Paving this area occurred on Monday, August 16.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Work for the jacking of the large diameter storm sewer pipe parallel to American
Blvd was temporarily stopped given the vibrations that were occurring. The
contractor was looking at ways to modify the operation before beginning again and
will use a system similar to the one that was used for the pipe installation along
Russell Avenue for the American Blvd installation.
Storm sewer repairs are scheduled to begin the week of August 23 throughout the
area. Curb will be placed sometime between August 25-27.
August 13, 2010
PMP Street Improvement Project
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
The final lift of paving was placed on Thursday, August 12.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road. The
final lift of paving was placed on Thursday, August 12 for all of the areas listed.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Storm sewer installation is winding down on the east side of the road. The contractor
will continue to grade and subcut Lyndale Avenue.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue is closed to facilitate the
installation of the large, deep trunk storm sewer. Retaining wall installation will
begin on Tuesday, August 17.
-
Beard Avenue (from 109th Street to 110th Street)
Sod restoration is scheduled to begin on Tuesday, August 17. Once the restoration is
complete the final paving will be scheduled.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
The gas main has been installed in the area. Centerpoint expects to be complete in the
area around August 20.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
The detour route is Lyndale Avenue, W. 90th Street and Penn Avenue. The final lift of
paving is scheduled for Monday, August 16, weather dependant. Hennepin County will be
out at the intersection of W. 86th Street and Penn Avenue working on the signal in
advance of the road reopening.
-
Lyndale Circle
The final lift of paving was placed on Thursday, August 12.
-
E. 94th Street (from west of Columbus Avenue to 12th Avenue)
The contractor has begun removals and will begin installing storm sewer on Tuesday,
August 17.
-
Oakland Avenue ( from Bishoff Lane to 90th Street)
Centerpoint is complete with the gas main installation. Centerpoint needs to verify
cross bores by camera and then install services. Centerpoint anticipates moving into
the area to complete this work the week of August 23 and be complete by the following
Monday, August 30.
-
17th Avenue (from 82nd Street to the north)
Centerpoint plans on installing new gas main in this area sometime during the month of
August, but no specific time frames have been provided to the City yet.
-
Clinton Ave Area (from E 79 ½ Street to E 82nd Street and from E 84th Street to
E 86th Street)
Centerpoint plans on moving into this neighborhood the week of August 30 and being
complete with the work by the end of September.
PMP Street Maintenance Project
-
E. 90th Street (between Stevens Avenue and Portland Avenue)
With the heavy rain that occurred on Tuesday, August 10 some of the seeded areas have
washed away and will need to be reseeded.
-
W. 90th Street (between France Avenue and Penn Avenue)
The section of road between France Avenue and Penn Avenue was paved on Thursday,
August 12 and reopened to traffic. Paving west of France Avenue still needs to occur
and is scheduled for Monday, August 16, weather dependant. Striping of the road will
occur the week of August 16 after the paving is complete. The striping will be a change
from the previous existing condition and will be one lane in each direction with a two
way continuous left turn lane in the middle and bike lanes between France Avenue and
Xerxes Avenue. Signal system modifications at the intersection of 90th Street and
France Avenue are also scheduled to begin the week of August 16 and will continue into
the following week. The signal will be placed on flash between the hours of 9 am and 3
pm at various times to complete the work.
-
89th Area (includes W. 89th Street and Kell Avenue)
Paving has been rescheduled to Monday, August 16, weather dependant.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe on Russell will continue for the
approximately the next two weeks and has begun for the pipe that runs parallel to
American Blvd. Curb removal for the entire area will begin on Monday, August 16 with
replacement beginning on Thursday, August 19. Storm sewer repairs are scheduled to
begin the week of August 23.
August 6, 2010
PMP Street Improvement Project
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
The final lift of paving has been rescheduled for Tuesday, August 10, weather
dependant.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road. The
final lift of paving has been rescheduled for Tuesday, August 10.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint completed their work on Monday, August 2. The City contractor has begun
installing storm sewer pipes which will continue into next week. Grading of the segment
between 98th Street and 99th Street has begun. Grading and road subcuts will occur
during the week of August 9.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue is closed to facilitate the
installation of the large, deep trunk storm sewer. Storm sewer installation is almost
complete on Russell Avenue. Watermain pipe installation will begin on Monday, August 9
along Russell Avenue. The contractor plans to continue the storm sewer installation
east of Queen Avenue along 82nd Street after the watermain is installed probably
towards the end of next week.
-
Beard Avenue (from 109th Street to 110th Street)
The base pavement has been placed along the entire road. The contractor will be
working on filling areas behind the curb and raising the iron during the week of August
9.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
The gas main has been installed in the area. Centerpoint is about complete with the
gas services on Thomas Avenue and will be moving to other streets in the area.
Centerpoint needs to verify cross bores by camera and then install services as each
street is cleared in the neighborhood. Centerpoint now expects to be complete in the
area around August 20.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
The detour route is Lyndale Avenue, W. 90th Street and Penn Avenue. The first lift of
bituminous was placed on Thursday, August 5. During the week of August 9, the
contractor will be working on filling areas behind the curb and sidewalk and raising
the iron.
-
Lyndale Circle
Paving is anticipated for Tuesday, August 10, weather dependant.
-
E. 94th Street (from west of Columbus Avenue to 12th Avenue)
Centerpoint Energy will begin installing new gas services on August 9 and anticipate
being complete with the work on August 10. The City contractor will begin work in the
area most likely sometime the week of August 16.
-
Clinton Ave Area (from E 79 ½ Street to E 82nd Street and from E 84th Street to
E 86th Street)
Centerpoint plans on moving into this neighborhood the week of August 23.
PMP Street Maintenance Project
-
E. 90th Street (between Stevens Avenue and Portland Avenue)
East 90th Street has been paved and is reopened to traffic. Striping is likely to
occur sometime before Tuesday, August 10.
-
W. 90th Street (between France Avenue and Penn Avenue)
The contractor is installing topsoil and raising iron in advance of paving the
road. Paving west of France will occur on Wednesday, August 11. W. 90th Street
between France and Penn will be closed on Thursday, August 12 for paving (rain date
Friday, August 13.) The road closure will only be for one day.
Striping of the road would occur the week of August 16. Signal system modifications
at the intersection of 90th Street and France Avenue are also scheduled for the
week of August 16 once the parts arrive. This work will continue into the following
week. The signal will be placed on flash between the hours of 9 am and 3 pm.
-
89th Area (includes W. 89th Street and Kell Avenue)
Paving is scheduled for Wednesday, August 11, weather dependant.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe on Russell will continue for the
approximately the next three weeks. Digging for the jacking pit for the pipe that runs
parallel to American Blvd has been started. Jacking pipe from this pit is scheduled to
begin sometime next week.
July 2010
July 30, 2010
PMP Street Improvement Project
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
The final lift of paving has been rescheduled for sometime the week of August 2.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road. The
final lift of paving has been rescheduled for sometime the week of August 2.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint will be switching from the existing pipe to the new system on either
Friday, July 30 or Monday, August 2. The City’s contractor will begin
installing storm sewer pipe on Lyndale starting Tuesday, August 3.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue is closed to facilitate the
installation of the large, deep trunk storm sewer. Storm sewer installation will
continue next week along W. 82nd Street and Russell Avenue.
-
Beard Avenue (from 109th Street to 110th Street)
Approximately the first 100 feet of the road was paved. The remainder of the base
pavement is scheduled to be placed sometime during the week of August 2.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
The gas main has been installed in the area. Centerpoint has verification that there
are no cross bores on Thomas Avenue and has begun to install gas services on Thomas
Avenue. They will continue to verify cross bores by camera and then install services as
each street is cleared in the neighborhood. Centerpoint now expects to be complete in
the area around August 13.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
The detour route is Lyndale Avenue, W. 90th Street and Penn Avenue. Fine grading of
the road is almost. The first lift of bituminous is planned for the end of the week of
August 2 or by August 9 at the latest.
-
Lyndale Circle
The first lift of bituminous has been installed. The disturbed areas will be repaired
with topsoil and sod likely during the week of August 2.
-
E. 94th Street (from west of Columbus Avenue to 12th Avenue)
Centerpoint Energy is still verifying that there are no cross bores within the system.
Once that is complete they can begin installing gas services. The City contractor can
move into the area to begin work once Centerpoint is finished with the gas services.
PMP Street Maintenance Project
-
E. 90th Street (between Stevens and Portland)
East 90th Street (3rd Avenue to Portland) is closed to allow for repair of a sanitary
sewer line. Local residents within the construction area are able to access their
homes, however, through traffic is prohibited. The Valley View Playfield/Aquatic Center
parking lots will remain open to traffic during the E. 90th Street closure. A marked
detour will use Nicollet Avenue, 86th Street and Portland Avenue. The disturbed areas
are being repaired with a topsoil and either sod or hydroseed depending on the location
of the disturbed area. The road is scheduled to be paved on Tuesday, August 3, weather
permitting. The road will be reopened Tuesday evening.
-
W. 90th Street (between France and Penn)
Milling of the road is scheduled for August 2 and 3. Once the milling is complete, the
contractor will be raising the manhole covers to the proper elevation for installation
of pavement. Paving is planned for Thursday, August 12 which would allow Friday, August
13 to serve as the rain date in case the weather does not cooperate.
-
89th Area (includes W. 89th Street and Kell Avenue)
Milling of the road is scheduled for August 4. Once the milling is complete, the
contractor will be raising the manhole covers to the proper elevation for installation
of pavement. Paving would occur either at the end of the following week or at the
beginning of the week of August 16.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe on Russell will continue for the next
few weeks.
-
82nd Street (between Stevens and Portland, includes 1st Avenue between 81st
Street and American Blvd)
Metro Drive Area (includes both Metro Drive and Metro Parkway)
12th Avenue (from I-494 to American Blvd)
Sodding is complete on 12th Avenue but some areas remain on 1st & 82nd. Four small
areas on Metro Drive that were accidentally forgotten will also be sodded.
July 23, 2010
PMP Street Improvement Project
-
West Bush Lake area (from W. 95th Street to Veness Road)
Stripes have been placed on the road. This segment is complete except for punch list
work.
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
The final lift of paving is scheduled for Wednesday July 28 or Thursday July 29.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road. The
final lift of paving is scheduled for Wednesday July 28 or Thursday July 29 on Izaak
Walton Road, Colorado Road, Colorado Circle and W. 93rd Street.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint still anticipates being complete with their gas main work by the end
of July which will allow the City’s contractor to move into the area and
begin storm sewer pipe installation the first week in August.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd
Street from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue is closed to facilitate the
installation of the large, deep trunk storm sewer. Storm sewer installation will
continue next week along W. 82nd Street and Russell Avenue. Work at the
intersection of Penn Avenue and 82nd Street has been delayed due to inaccurate
as-built information.
Given the deep storm sewer installation and the road closure, staff has received a
few phone calls regarding traffic on local roads in addition to construction
vehicles. Staff has looked at the issues and is making some minor modifications to
the traffic control set up in the area that should relieve some of the concerns,
but residents should continue to expect increased traffic including construction
vehicles in the area.
-
Beard Avenue (from 109th Street to 110th Street)
Concrete curb work is almost complete. Fine grading of the road will occur towards the
end of the week of July 26. The first lift of bituminous is planned for sometime the
first week of August.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
The gas main has been installed in the area. Centerpoint now is two-thirds complete
with the verification that there are no cross bores with the system to meet the
Minnesota Office of Pipeline Safety requirements. It appears likely that Centerpoint
will remain in the neighborhood through July before the City’s contractor can
begin work in the area.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
The road is closed to thru traffic and will be for approximately four weeks. The
detour route is Lyndale Avenue, W. 90th Street and Penn Avenue. Concrete curb work is
almost complete. Fine grading of the road will occur towards the end of the week of
July 26. The first lift of bituminous is planned for sometime the first week of August.
-
Lyndale Circle
Fine grading of the road is scheduled for Tuesday, July 27 with paving of the first
lift of bituminous at the end of the week.
-
E. 94th Street (from west of Columbus Avenue to 12th Avenue)
Centerpoint has installed the gas main. During the week of July 26 Centerpoint will be
verifying that there are no cross bores within the system and then begin installing gas
services. Once this work is complete, the City contractor can move into the area to
begin work.
PMP Street Maintenance Project
-
E. 90th Street (between Stevens and Portland)
East 90th Street (3rd Avenue to Portland) will close at 7 a.m. Wednesday, July 28.
This section of 90th Street will remain closed for approximately 1 week to allow for
repair of a sanitary sewer line. Local residents within the construction area will be
able to access their homes, however, through traffic will be prohibited. The Valley
View Playfield/Aquatic Center parking lots will remain open to traffic during the E.
90th Street closure. A marked detour will use Nicollet Avenue, 86th Street and Portland
Avenue.
-
W. 90th Street (between France and Penn)
Traffic will be moved to the outside lanes of W. 90th Street next week. This will
facilitate the concrete removal and replacement of the various medians in the road.
Milling of the road is scheduled for August 2 and 3. Paving would occur at the end of
the following week.
-
89th Area (includes W. 89th Street and Kell Avenue)
Milling of the road is scheduled for either August 2 and 3. Paving would occur at the
end of the following week.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe on Russell will continue for the next
few weeks.
-
82nd Street (between Stevens and Portland, includes 1st Avenue between 81st
Street and American Blvd)
Metro Drive Area (includes both Metro Drive and Metro Parkway)
12th Avenue (from I-494 to American Blvd)
Topsoil has been placed and is ready for sod.
July 16, 2010
PMP Street Improvement Project
-
West Bush Lake area (from W. 95th Street to Veness Road)
Sod and the final layer of pavement have been placed and the road has been reopened to
traffic. Stripes will be placed on Monday, July 19, weather dependant.
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
Restoration of the boulevards will continue along with other cleanup next week.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road.
The contractor has been granted a noise exception to begin work at 7 am on
Saturday, July 17 to work on the grading of the new storm water facilities.
Restoration of the boulevards will continue along with other cleanup next week for
Colorado and 93rd.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint anticipates being complete with their gas main work by the end of July
which will allow the City's contractor to move into the area and begin storm sewer
pipe installation.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd
Street from Russell Avenue to Penn Avenue)
82nd Street between Penn Avenue and Russell Avenue will be closed starting Monday,
July 19 to facilitate the installation of the large, deep trunk storm sewer.
Pavement removal will begin on Monday with the storm pipe installation beginning on
Tuesday and continuing throughout the week. Work at the intersection of Penn Avenue
and 82nd Street is anticipated to begin the end of the week of July 19 but may get
delayed to the following week depending on the weather.
The contractor has applied for a noise variance exception to begin work at 5:30 am
on either Tuesday, July 20 or Wednesday, July 21 weather dependant. This exception
is requested to limit the impacts due to the installation of a new watermain valve.
The installation of the new valve will require a watermain shutdown, one residence
and one business will be affected by the shut down. The business is a dentist
office and is the reason why the shutdown is being done early in the morning
necessitating the noise variance.
The City's Contractor continues to set up the temporary water system that will be
necessary to complete the construction work. These temporary water lines will
extend into the neighborhood and include areas from Xerxes Avenue east to Penn
Avenue and 84th Street north to 82nd Street.
-
Beard Avenue (from 109th Street to 110th Street)
Centerpoint Energy is complete with the gas service installation. The contractor will
be removing the pavement either on Friday, July 16 or Monday, July 19. Storm pipe
installation will begin the week of July 19.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between
Old Shakopee Road and Baliff Place)
The gas main has been installed in the area. Centerpoint now needs to verify that
there are no cross bores with the system to meet the Minnesota Office of Pipeline
Safety requirements before any gas services can be installed. A second crew has not
yet been brought into the area to help clear the main before beginning the
services. It appears likely that Centerpoint will remain in the neighborhood
through July before the City's contractor can begin work in the area.
Engineering staff began meeting individually with residents participating in the
2010 Rainwater Garden Project. Of the approximately 100 residents in the
neighborhood, 26 chose to incorporate rainwater gardens into their boulevard areas.
The recent meetings included discussions on plant varieties, garden location, and
anticipated planting timing among other questions. After the individual meetings,
residents will be asked to decide on their plant varieties and staff will assist
with planting designs. Residents will be given a chance for final planting plan
approval in late September. Engineering staff will assist the residents in planting
the gardens following the street reconstruction. The Nine Mile Creek Watershed
District has again partnered with the City's Rainwater Garden Project with a
$25,000 cost-share, the remainder will be from the Storm Water Drainage Utility.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
The road is closed to thru traffic and will be for approximately four weeks. The
detour route is Lyndale Avenue, W. 90th Street and Penn Avenue. Some concrete curb
replacement at the intersection of Penn and W. 86th Street has been completed, but
there is more replacement yet to occur. Grading including a subcut to deal with the
frost heave problem will continue through the week of July 19.
-
Lyndale Circle
Concrete curb has been replaced in the area. Tolerancing the area for placement of the
Class 5 aggregate base will occur during the week of July 19.
PMP Street Maintenance Project
-
Wellswood Area (includes Towerview Circle)
Lakeview Area (includes Lakeview Circle, Texas Avenue, W. 87th Street, Walton
Oaks Drive)
Collegeview Road (between 98th Street to north of Little Road)
Maryland area (includes Maryland Circle and Oregon Avenue)
Sod was placed this week. The areas are complete except for punch list work.
-
E. 90th Street (between Stevens and Portland)
The milling of the street is scheduled for July 19. A sink hole developed on Thursday,
July 15 at the intersection of E. 90th and 3rd Avenue due to sanitary sewer manhole and
pipe material failures. The area has been temporarily repaired while alternatives to
fix the sanitary sewer are explored. The sewer is deep and will likely require the
closure of the intersection to fix the pipe. Further updates will be provided once a
repair scenario is known. In the mean time the paving of the street has been postponed
to accommodate the repair.
-
W. 90th Street (between France and Penn)
Concrete removal and replacement will continue during the week of July 19.
The signals for both France Avenue and Penn Avenue have had some issues with short
green times for various movements or not responding to pedestrian push button
calls. Hennepin County has been contacted since they own both signals and staff was
out looking at the issue on Friday, July 16.
-
89th Area (includes W. 89th Street and Kell Avenue)
Concrete removal and replacement will begin during the week of July 19.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe on Russell will continue for the next
few weeks.
-
82nd Street (between Stevens and Portland, includes 1st Avenue between 81st
Street and American Blvd)
Metro Drive Area (includes both Metro Drive and Metro Parkway)
12th Avenue (from I-494 to American Blvd)
Topsoil has been placed and is ready for sod. Sod cannot be planted on days were the
expected high is over 90 degrees since the sod will dry out if left on the truck to
long.
-
Pleasant Area (between W. 100th Street and Old Shakopee Road and includes 3rd
Avenue between Portland Place and Old Shakopee Road)
Garfield Area (includes Grand Avenue & 97 ½ Street between 95th Street and 98th
Street)
Portland Avenue (Between E. 102nd Street and E. 99th Street)
Sod has been planted on Portland but still needs to be replaced in some of the
Pleasant and Garfield areas where it has not successfully completed its 30 day warranty
period. Sod cannot be planted on days were the expected high is over 90 degrees since
the sod will dry out if left on the truck to long. Staff has also agreed to allow some
slit seeding in areas where the sod did not take. This seeding method has successfully
been used on other projects in the past and hopefully will perform as well this time.
The same 30 day requirement will be enforced so that the areas are growing with green
grass at the end of the time period.
July 9, 2010
PMP Street Improvement Project
-
West Bush Lake area (from W. 95th Street to Veness Road)
West Bush Lake Road will continue to be closed. The detour route is West Bush Lake
Road to East Bush Lake Road to W. 86th Street. There will also be detour signs
posted on Bloomington Ferry Road and Lindstrom. Motorists should plan for addition
time while traveling round the area.
The final lift of pavement is scheduled for Thursday, July 15 weather dependant.
The road should be reopened on Friday, July 16 if the paving occurs as scheduled.
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
Restoration of the boulevards will continue along with other cleanup next week.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road.
Restoration of the disturbed area is ongoing but the recent rains have slowed
progress in constructing the storm water facility.
Bituminous pavement was placed this past week. Driveway restoration continues and
work to restore the boulevards will begin next week.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint continues to work along Lyndale and is slightly behind due to the
asbestos pipe wrap that was found on their old main. Their crew will continue to
work Saturdays to catch up.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The City’s Contractor continues to set up the temporary water system that will
be necessary to complete the construction work. These temporary water lines will extend
into the neighborhood and include areas from Xerxes Avenue east to Penn Avenue and 84th
Street north to 82nd Street. Work at the intersection of Penn Avenue and 82nd Street is
anticipated to begin the end of the week of July 19.
-
Beard Avenue (from 109th Street to 110th Street)
Centerpoint Energy will work on installing services in the area.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
The gas main has been installed in the area. Centerpoint now needs to verify that
there are no cross bores with the system to meet the Minnesota Office of Pipeline
Safety requirements before any gas services can be installed. Centerpoint has been
televising the sewer services to confirm that there are no cross bores at each service.
Centerpoint is trying to find a second camera crew to bring to this neighborhood to
speed up the process. The City has provided sanitary sewer system information for
Centerpoint to use in exploring the use of other equipment, like a vactor truck, in
clearing the sewer services.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
Storm sewer installation will begin on July 12 with concrete curb work beginning
towards the end of the week. Water service abandonment's and sewer manhole reconstructs
will also occur next week. The road is closed to thru traffic and will be for
approximately four weeks. The detour route is Lyndale Avenue, W. 90th Street and Penn
Avenue.
-
Lyndale Circle
Storm sewer installation will begin on July 12 with concrete curb work beginning
towards the end of the week.
PMP Street Maintenance Project
-
Wellswood Area (includes Towerview Circle)
Boulevard restoration is planned to occur sometime during the week of July 12, weather
permitting. Sod cannot be planted on days were the expected high is over 90 degrees
since the sod will dry out if left on the truck to long.
-
Lakeview Area (includes Lakeview Circle, Texas Avenue, W. 87th Street, Walton
Oaks Drive)
Collegeview Road (between 98th Street to north of Little Road)
Maryland area (includes Maryland Circle and Oregon Avenue)
Boulevard restoration is planned to occur sometime during the week of July 12, weather
permitting. Sod cannot be planted on days were the expected high is over 90 degrees
since the sod will dry out if left on the truck to long.
-
E. 90th Street (between Stevens and Portland)
The concrete work at various Valley View parking lots is complete and the temporary
entrances are being removed. Paving of the path is scheduled for Wednesday, July 14
weather permitting. The contractor will also begin lowering iron (manholes, gate
valves, etc) in advance of milling the road. The milling of the street is scheduled for
July 19.
-
W. 90th Street (between France and Penn)
The contractor plans on beginning work on this segment during the week of July 12.
Storm sewer construction and manhole reconstruction will be the first activities on
this road. Curb removals and replacements will also begin next week.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe on Russell will continue for the next
few weeks..
-
82nd Street (between Stevens and Portland, includes 1st Avenue between 81st
Street and American Blvd)
The road has been paved. Preparation of the boulevards for restoration will begin.
-
Metro Drive Area (includes both Metro Drive and Metro Parkway)
The road has been paved. Preparation of the boulevards for restoration will begin.
-
12th Avenue (from I-494 to American Blvd)
The road has been paved. Preparation of the boulevards for restoration will begin.
-
Pleasant Area (between W. 100th Street and Old Shakopee Road and includes 3rd
Avenue between Portland Place and Old Shakopee Road)
Garfield Area (includes Grand Avenue & 97 ½ Street between 95th Street and 98th
Street)
Portland Avenue (Between E. 102nd Street and E. 99th Street)
Sod that has not successfully completed its 30 day warranty period will be replaced
towards the end of the week of July 5 and will carry over to the following week. Sod
cannot be planted on days were the expected high is over 90 degrees since the sod will
dry out if left on the truck to long. Staff has also agreed to allow some slit seeding
in areas where the sod did not take. This seeding method has successfully been used on
other projects in the past and hopefully will perform as well this time. The same 30
day requirement will be enforced so that the areas are growing with green grass at the
end of the time period.
July 2, 2010
PMP Street Improvement Project
-
West Bush Lake area (from W. 95th Street to Veness Road)
West Bush Lake Road will continue to be closed. The detour route is West Bush Lake
Road to East Bush Lake Road to W. 86th Street. There will also be detour signs
posted on Bloomington Ferry Road and Lindstrom. Motorists should plan for addition
time while traveling round the area.
The first layer of bituminous was placed on July 1. Restoration of the boulevards
will begin next week. The contractor will being raising the iron (manholes, gate
valves etc.) in anticipation of the final lift of bituminous which is expected to
be placed on July 8. The road will reopen to traffic the following week, weather
dependant, once the stripes have been placed.
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
The first layer of bituminous was placed on July 1. Restoration of the boulevards will
begin next week.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road.
The first layer of bituminous was placed in the cul de sac on July 1. Restoration
of the disturbed area is ongoing.
Concrete work occurred on Colorado Circle and W. 93rd Street this past week. The
first lift of bituminous pavement is anticipated to occur on Thursday, July 8.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint continues to work along Lyndale and is slightly behind due to the
asbestos pipe wrap that was found on their old main. Their crew will continue to
work Saturdays to catch up. Centerpoint anticipates about three more weeks of work
on Lyndale before they are complete. The City's Contractor cannot begin their storm
pipe installation work until some of the gas main work is complete and likely will
not begin on this segment until mid July.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
Both gas main and services in the Russell Area will be complete on Tuesday, July 6.
The City's Contractor continues to set up the temporary water system that will be
necessary to complete the construction work. These temporary water lines will extend
into the neighborhood and include areas from Xerxes Avenue east to Penn Avenue and 84th
Street north to 82nd Street. Several meetings have been held with the Fire Department
to ensure that adequate coverage for fire protection will be provided during this time
and emergency responders have a strategy in place to combat a potential incident. The
Contractor plans on starting removals and pipe installation after the July Fourth
holiday.
-
Beard Avenue (from 109th Street to 110th Street)
Centerpoint Energy anticipates installing services towards the end of the week of July
5.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
Most of the gas main has been installed in the neighborhood. Centerpoint now needs to
televise the sanitary sewer services to be in compliance with the Minnesota Office of
Pipeline Safety requirements before any gas services can be installed. The current
production rate of the camera crew is about 5 houses a day. With nearly a 100 homes in
this area, it will take the entire month of July for Centerpoint to clear the area
before they can start installing services. Centerpoint is trying to find a second
camera crew to bring to this neighborhood to speed things up. Centerpoint will also try
to see if they can clear an entire street so that it can be worked on by other crews
while the camera crew is still in the neighborhood on other streets. They have run into
difficulty with this where an entire street is cleared except for one house where
someone is on vacation. After the main has been cleared the gas service crew can begin
installation at the beginning of August. The City's contractor is likely not to be in
the area until mid to late August if Centerpoint's schedule cannot be accelerated.
-
W. 86th Street (from Humboldt Avenue to Penn Avenue)
The Contractor plans on removing the pavement starting on Thursday, July 8. Storm
sewer installation would begin on July 12. Like all PMP reconstruction streets, the
road will be closed to thru traffic. The detour route will be on Lyndale Avenue, W.
90th Street and Penn Avenue. The information will also be posted on the City website.
PMP Street Maintenance Project
-
Wellswood Area (includes Towerview Circle)
This area has been paved. Boulevard restoration is planned to occur sometime during
the week of July 5, weather permitting. Sod cannot be planted on days when the expected
high is over 90 degrees since the sod will dry out if left on the truck to long.
-
Lakeview Area (includes Lakeview Circle, Texas Avenue, W. 87th Street, Walton
Oaks Drive)
Collegeview Road (between 98th Street to north of Little Road)
Maryland area (includes Maryland Circle and Oregon Avenue)
Boulevard restoration is planned to occur sometime during the week of July 5, weather
permitting. Sod cannot be planted on days when the expected high is over 90 degrees
since the sod will dry out if left on the truck to long.
-
E. 90th Street (between Stevens and Portland)
Temporary entrances with signs directing traffic have been installed at various Valley
View parking lots to facilitate the concrete removal and installation at the park
driveways. Storm sewer pipe work will begin on Tuesday, July 6 in this area. On July 7,
the contractor will finish grading the path in advance of paving the path the beginning
of the following week. The contractor will also begin lowering iron (manholes, gate
valves, etc) in advance of milling the road. The milling of the street will not occur
until July 19 or later so it does not interfere with the Fireman's Softball Tournament
which will occur at Valley View the weekend of July 16-18.
-
W. 90th Street (between France and Penn)
The contractor plans on beginning work on this segment during the week of July 12.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Jacking of the large diameter storm sewer pipe on Russell will begin on Tuesday, July
6. This pipe installation will take a number of weeks.
-
82nd Street (between Stevens and Portland, includes 1st Avenue between 81st
Street and American Blvd)
Milling for the road is scheduled for July 6 with paving planned for July 8, weather
dependant.
-
Metro Drive Area (includes both Metro Drive and Metro Parkway)
Milling for the road is scheduled for July 7 with paving planned for July 9, weather
dependant.
-
12th Avenue (from I-494 to American Blvd)
Milling for the road is scheduled for July 7 with paving planned for July 9, weather
dependant. The contractor also plans on submitting for a noise variance to begin work
at 5 am on this segment. The contractor would phase their work to mill the segment near
I-494 and the frontage road at this early hour and then move south to try and better
accommodate the busy traffic in this area. Staff has watched the traffic on this
segment and determined that there is less traffic in the AM rush than at either lunch
or the PM rush and an earlier morning start, while inconvenient is probably the least
disruptive.
-
Pleasant Area (between W. 100th Street and Old Shakopee Road and includes 3rd
Avenue between Portland Place and Old Shakopee Road)
Garfield Area (includes Grand Avenue & 97 ½ Street between 95th Street and 98th
Street)
Portland Avenue (Between E. 102nd Street and E. 99th Street)
Sod that has not successfully completed its 30 day warranty period will be replaced
towards the end of the week of July 5 and will likely carry over to the following week.
Sod cannot be planted on days were the expected high is over 90 degrees since the sod
will dry out if left on the truck to long.
June 2010
June 25, 2010
PMP Street Improvement Project
-
West Bush Lake area (from W. 95th Street to Veness Road)
West Bush Lake Road will continue to be closed. The detour route is West Bush Lake
Road to East Bush Lake Road to W. 86th Street. There will also be detour signs
posted on Bloomington Ferry Road and Lindstrom. Motorists should plan for addition
time while traveling round the area.
Significant progress was made this past week. The subcut of the soft soil material
is complete, the curb and gutter has been removed and replaced. Tolerancing of the
class 5 rock base will occur next Monday, June 28 with paving of the first lift of
bituminous projected for later in the week, weather dependant.
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
Class 5 rock has been placed on the road. Curb and gutter installation has begun. The
entrance to Pennsylvania from Old Shakopee Road will be closed over the weekend and
reopened Monday morning at 7 am to allow the concrete to develop enough strength to be
driven over. Hennepin County approved the closure of the left turn lane and the
notification of the closure was sent out to the appropriate emergency services. Paving
of the road is planned for next Friday, July 2, weather dependant.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road.
The cul de sac has been toleranced in advance of curb and gutter installation.
Paving is anticipated for Izaak Walton cul de sac on July 2, weather dependant.
Removals are underway on Colorado Circle and W. 93rd Street. Pipe installation is
scheduled for Monday, June 28 in this area.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint continues to work along Lyndale and originally planned on being
complete with their work gas main work by the end of June. One of the existing gas
mains was discovered to contain asbestos. Proper removal of this material takes
more time and Centerpoint's work may extend into the beginning of July. Centerpoint
also plans on working the next few Saturdays so that they can hold to the original
schedule as much as possible even with this extra work. The Signal Contractor will
continue working at the signal system at the intersection of 95th Street and
Lyndale. The Contractor will begin their storm pipe installation work on Lyndale
the week of July 5.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The gas main in the area has been installed and inspected based on the new Minnesota
Office of Pipeline Safety requirements. Now that the inspection is complete,
Centerpoint Energy can proceed with service installation during the week of June 28.
The City's Contractor will be beginning to set up the temporary water system that will
be necessary to complete the construction work. These temporary water lines will extend
into the neighborhood and include areas from Xerxes Avenue east to Penn Avenue and 84th
Street north to 82nd Street. The Contractor plans on starting removals and pipe
installation after the July Fourth holiday.
-
Beard Avenue (from 109th Street to 110th Street)
The gas main in the area has been installed and inspected based on the new Minnesota
Office of Pipeline Safety requirements. Now that the inspection is complete,
Centerpoint Energy can proceed with service installation during the week of June 28.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
Centerpoint will continue gas main installation in this area during the week of June
28.
PMP Street Maintenance Project
-
Wellswood Area (includes Towerview Circle)
Paving is scheduled for Monday, June 28. It had been delayed because a soft spot was
found and had to be corrected before the area could be paved.
-
Maryland area (includes Maryland Circle and Oregon Avenue)
This area was paved on June 17.
-
E. 90th Street (between Stevens and Portland)
The contractor will be grading and placing rock in the area for the trail along Valley
View Park on the south side of the road during the week of June 28.
-
W. 90th Street (between France and Penn)
The loop detector work on W. 90th Street at the intersection of Penn and W. 90th
Street is complete.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Construction of the jacking pit for storm sewer pipe installation along Russell is
underway. Jacking of the large diameter storm sewer pipe will begin soon and continue
for the next few weeks.
-
82nd Street (between Stevens and Portland, includes 1st Avenue between 81st
Street and American Blvd)
The disturbed areas will be prepped with topsoil. Work on various manholes will be
taking place. Milling for the road is scheduled for either July 6 or 7.
-
Collegeview Road (between 98th Street to north of Little Road)
The road has been paved and striped.
-
Metro Drive Area (includes both Metro Drive and Metro Parkway)
The disturbed areas will be prepped with topsoil. Work on various manholes will be
taking place. Milling for the road is scheduled for either July 6 or 7.
-
12th Avenue (from I-494 to American Blvd)
The disturbed areas will be prepped with topsoil. Work on various manholes will be
taking place. Milling for the road is scheduled for either July 6 or 7.
June 18, 2010
PMP Street Improvement Project
-
West Bush Lake area (from W. 95th Street to Veness Road)
West Bush Lake Road will continue to be closed. The detour route is West Bush Lake
Road to East Bush Lake Road to W. 86th Street. There will also be detour signs
posted on Bloomington Ferry Road and Lindstrom. Motorists should plan for addition
time while traveling round the area.
Class 5 rock has been placed on approximately half of the road. The rain delayed
the subcut work where soft soils need to be removed. The subcut work and the
placement of class 5 work will continue into next week.
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
Removals on Pennsylvania have begun. Grading the subbase will occur next week.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road.
Detour signs indicating how to get to Izaak Walton are in place. The storm sewer work
is complete in the area.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint continues to work along Lyndale and plans on being complete with their
work gas main work by the end of June. The Signal Contractor will continue working
at the signal system at the intersection of 95th Street and Lyndale. The Contractor
will begin their storm pipe installation work on Lyndale the week of July 5.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
Centerpoint Energy continues to work in the area and hopes to be complete with their
main work by June 21, weather dependant. The new gas main to be installed along new
Russell Avenue adjacent to the Applewood Point development will not occur until later
in the summer. The contractor plans on potholing utilities on Penn Avenue during the
week of June 21.
-
Beard Avenue (from 109th Street to 110th Street)
Centerpoint has begun gas main and service work on Beard Ave. They anticipate being
complete with the work around June 24, weather dependant.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
Centerpoint plans on beginning gas main installation in this area sometime the week of
June 21.
-
86th Street (between Penn Avenue and Humboldt Avenue)
This area will not begin until sometime in July as the recent rains have delayed both
Centerpoint and the contractor.
PMP Street Maintenance Project
-
Wellswood Area (includes Towerview Circle)
Milling of the road is scheduled for June 23 with paving hopefully occurring by the
end of the week, weather dependant.
-
Maryland area (includes Maryland Circle and Oregon Avenue)
This area was paved on June 17.
-
E. 90th Street (between Stevens and Portland)
The weather has delayed the contractor who now plans on moving into the area to begin
work the week of June 21. Installation of loop detectors for the signal at E.90th
Street and Portland Avenue will begin the week of June 21.
-
W. 90th Street (between France and Penn)
The loop detector work on W. 90th Street at the intersection of Penn and W. 90th
Street is complete.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Centerpoint Energy continues to work in the area and hopes to be complete with their
work by June 21, weather dependant.
-
82nd Street (between Stevens and Portland, includes 1st Avenue between 81st
Street and American Blvd)
Patching in front of curb and gutter and at various utility locations is scheduled for
June 21 in advance of milling of the surface. The loop detector work on 82nd Street and
Portland Avenue is complete.
-
Collegeview Road (between 98th Street to north of Little Road)
Milling was again postponed due to the rain but finally occurred on Thursday, June 17.
The Contractor will be raising manholes in advance of paving the road which is
scheduled for Tuesday, June 22.
-
Metro Drive Area (includes both Metro Drive and Metro Parkway)
Patching in front of curb and gutter and at various utility locations is scheduled for
June 21 in advance of milling of the surface. Topsoil installation will begin the week
of June 21.
-
12th Avenue (from I-494 to American Blvd)
MnDOT has suggested that video detection may be a possibility for the signal at 12th
Avenue at the off ramp from I-494. City and MnDOT staffs continue to work on the issue.
Installation of some type of signal detection (either in pavement loop or video) will
begin the week of June 21.
June 11, 2010
PMP Street Improvement Project
-
West Bush Lake area (from W. 95th Street to Veness Road)
West Bush Lake Road will continue to be closed. The detour route is West Bush Lake
Road to East Bush Lake Road to W. 86th Street. There will also be detour signs
posted on Bloomington Ferry Road and Lindstrom. Motorists should plan for addition
time while traveling round the area.
The rain delayed some of the grading of the road along with encountering some
rubble in the road bed that will need to be hauled to a landfill. Some grading was
completed with the installation of class 5 rock material in the area. Grading of
the road will continue along with concrete removals next week.
-
Pennsylvania area (from Old Shakopee Road to 109th Street)
With the rain the Contractor has postponed beginning removals on this street until the
end of the week of June 14. The contractor plans on sawcutting the existing road at Old
Shakopee Road on Saturday, June 12 in preparation for removing the road next week.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Izaak Walton has been officially closed from East Bush Lake Road to Lakeview Road. The
notice of the permanent closure due to the road removal has been sent to various public
safety organizations, Bloomington School District, Hennepin County, and Met Transit
officials. The contractor plans on sawcutting the existing road at East Bush Lake Road
on Saturday, June 12. A storm sewer crew is scheduled to begin on Monday, June 14. The
new power pole has been installed on Izaak Walton but the Xcel and Qwest wires have not
been moved over yet.
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Centerpoint Energy continues to install new gas main in Lyndale Avenue and has
brought in a second crew to work in the area. Starting June 14, Centerpoint will
need to connect to existing facilities located in Old Shakopee Road. This will
reduce the east bound traffic lane for Old Shakopee Road to one lane. Motorists
should plan for addition time while traveling in the area. Centerpoint plans on
being complete with their work gas main work on Lyndale Avenue by the end of June.
The Signal Contractor plans on working on the signal system at the intersection of
95th Street and Lyndale tentatively beginning June 17. The Contractor will begin
their storm pipe installation work on Lyndale in the block between 98th Street and
99th Street the week of June 28.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
Centerpoint Energy continues to work in the area and hopes to be complete with their
main work by June 21, weather dependant. The new gas main to be installed along new
Russell Avenue adjacent to the Applewood Point development will not occur until later
in the summer. The contractor plans on sawcutting the existing road at 82nd Street and
Penn Avenue on Saturday, June 12 in preparation for potholing the utilities on Penn
Avenue.
-
Beard Avenue (from 109th Street to 110th Street)
Centerpoint plans on beginning gas service work in this area sometime the week of June
21.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
The contractor anticipates moving into this area at the end of June. Both Qwest and
Centerpoint will have work in the area.
-
86th Street (between Penn Avenue and Humboldt Avenue)
The contractor thinks this area may not get started until sometime in July if the rain
continues next week as forecast.
PMP Street Maintenance Project
June 4, 2010
PMP Street Improvement Project
-
West Bush Lake area
West Bush Lake Road between W. 95th Street and Veness Road will continue to be
closed. With the completion of the paving and striping of West Bush Lake Road north
of Veness, the project will enter phase 3 of the detour plan. The detour route will
be West Bush Lake Road to East Bush Lake Road to W. 86th Street. There will also be
detour signs posted on Bloomington Ferry Road and Lindstrom. Motorists should plan
for addition time while traveling round the area.
Grading of the road will continue and concrete removals are scheduled for the week
of June 7.
-
Pennsylvania area
With the rain the Contractor has postponed beginning removals on this street until the
end of the week of June 7.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
The new power pole has been installed on Izaak Walton but the Xcel and Qwest wires
have not been moved over yet.
-
Lyndale area (includes 96th Street)
Centerpoint Energy continues to install new gas main in Lyndale Avenue. During the
week of June 14, Centerpoint will need to connect to existing facilities located in
Old Shakopee Road. This will reduce the east bound traffic lane for Old Shakopee
Road to one lane. Motorists should plan for addition time while traveling in the
area.
-
Russell Avenue Area (includes 82nd Street)
Centerpoint Energy anticipates beginning gas main installation during the week of June
7.
-
86th Street
The contractor anticipates moving into this area at the end of June. Both Qwest and
Centerpoint will have work in the area.
PMP Street Maintenance Project
May 2010
May 28, 2010
PMP Street Improvement Project
-
West Bush Lake area
West Bush Lake Road between W. 95th Street and W. 86th Street will continue to be
closed. The detour route will be West Bush Lake Road to East Bush Lake Road to W.
86th Street. There will also be detour signs posted on Bloomington Ferry Road and
Lindstrom. Local residents will be able to access their homes, but there will be a
hard closure that prohibits through movements north of Birchwood Lane. Residents
will need to plan their access accordingly since they will not be able to cross
West Bush Lake Road north of Birchwood. Motorists should plan for addition time
while traveling round the area.
Storm sewer installation will continue during the week of June 1. Soft subgrade
areas will be cut out.
-
Pennsylvania area
The Contractor plans on beginning removals towards the end of the week of June 1.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Removal of the fence along with work by Xcel and Qwest to relocate a power pole and
some wires is planned for the week of June 1.
-
Lyndale area (includes 96th Street)
Removals along the east side of Lyndale have occurred and traffic has been reduced
to one lane in each direction and shifted to the west side of the road. Centerpoint
Energy will begin their work on June 1 starting approximately fifty feet south of
the intersection of Lyndale and 98th Street/Old Shakopee Road.
The traffic shift has gone fairly well, although some backups did occur for west
bound traffic on Old Shakopee Road. City staff has worked with Hennepin County to
adjust the signal timing which has helped traffic flow. Staff will continue to
monitor and make adjustments as necessary.
-
Russell Avenue Area (includes 82nd Street)
Centerpoint Energy anticipates mobilizing into the area on either June 3 or 4 and
beginning gas main installation during the week of June 7.
-
86th Street
The contractor anticipates moving into this area at the end of June. Both Qwest and
Centerpoint will have work in the area.
PMP Street Maintenance Project
-
Pleasant area (includes 3rd Avenue)
The road was paved on Thursday, May 27.
-
Garfield area (includes Grand Avenue & 97 ½ Street)
This area has been complete with only punch list items remaining.
-
Portland area
The road was paved on Friday, May 28.
-
Wellswood Area (includes Towerview Circle)
Centerpoint Energy anticipates completing the gas service week next week. Once this is
complete, removal and replacement of curb would occur. Milling of this segment is
anticipated sometime during the week of June 7.
-
Lakeview area (includes Lakeview Circle, Texas Avenue, W. 87th Street, Walton
Oaks Drive)
Milling of the street is anticipated on June 1. The contractor will be raising the
iron (manholes, valves, handholes) in advance of paving which would occur the week of
June 7. The disturbed areas behind the curb will also be sodded next week.
-
Maryland area (includes Maryland Circle and Oregon Avenue)
The disturbed areas behind the curb will be sodded the week of June 1. Milling of this
segment is anticipated sometime during the week of June 7.
-
West Bush Lake Road
West Bush Lake Road between W. 95th Street and W. 86th Street is closed. The
detour route is West Bush Lake Road to East Bush Lake Road to W. 86th Street. There
will also be detour signs posted on Bloomington Ferry Road and Lindstrom for Phases
2 and 3. Local residents will be able to access their homes, but there will be a
hard closure that prohibits through movements north of Birchwood Lane. Residents
will need to plan their access accordingly since they will not be able to cross
north of Birchwood. Motorists should plan for addition time while traveling through
the area.
The road has been milled. Sod and seed installation will occur during the week of
June 1. Next week the contractor will be raising the iron along the road with
paving tentatively planned for Friday, June 4 depending on weather. Striping of the
road would occur the following Monday, June 7 with the road segment between Veness
and W. 86th Street being reopened to traffic after the traffic markings are in
place.
-
E. 90th Street
Tree removal along E. 90th Street in front of Valley View is complete. Some residents
have expressed concern regarding the tree removal. The trees were removed along the
road to accommodate the Core Linking Trail as proposed in the Alternative
Transportation Plan to serve pedestrians and bicyclists that is to be constructed with
the project. Approximately two-thirds of the trees removed were green ash, including a
number that were rated as fair or poor by the City Forester. The Minnesota Department
of Agriculture has recommended that agencies remove green ash in these categories as a
way to combat the spread of the Emerald Ash Borer. These trees would have been removed
regardless of the project. Many of the existing trees were also located beneath utility
wires which would have required trimming as the trees grew. This trimming would likely
further weaken the trees making them more susceptible to the Emerald Ash Borer. A stand
of hackberries that was determined to be of higher value were left based on the
recommendation of the City Forester. The removed trees will be replaced on a one to one
basis and will be planted within Valley View Park. Given the space constrictions in
some areas where the trail, street curb and parking lot curb are in close proximity
some of the trees cannot be replaced in the same general location for safety reasons.
The preferred location will be to plant the replacement trees will be near the trail
along 90th Street.
-
Washburn area (includes Vincent, Upton, Thomas, Sheridan, Russell, Queen &
W. 81st)
Centerpoint Energy is complete with the gas main installation in this area and will
begin installing services from the new main to the houses.
-
82nd Street
82nd Street will be closed between 2nd Avenue and Clinton Avenue from 9 am to 5 pm on
both June 1 and June 2 to allow for the safe removal of large trees near power lines.
No detour route will be provided. Storm sewer work is scheduled to begin on June 3.
-
Collegeview Road
Storm sewer work is scheduled to begin on June 1. Removal and replacement of curb and
sidewalk would also occur next week. Milling of this segment is anticipated sometime
during the week of June 7.
-
Metro Drive Area (includes both Metro Drive and Metro Parkway)
Storm sewer work is scheduled to begin on June 2.
-
12th Avenue
Storm sewer work is scheduled to begin on June 2.
May 21, 2010
PMP Street Improvement Project
-
A preconstruction conference was held Monday, May 17.
-
West Bush Lake area
Work on the 2010-101 (Reconstruct) Project is scheduled to begin Monday, May 24 at
West Bush Lake Road. The closure will be along West Bush Lake Road between W. 95th
Street and W. 86th Street. The detour route will be West Bush Lake Road to East
Bush Lake Road to W. 86th Street. There will also be detour signs posted on
Bloomington Ferry Road and Lindstrom. Local residents will be able to access their
homes, but there will be a hard closure that prohibits through movements north of
Birchwood Lane. Residents will need to plan their access accordingly since they
will not be able to cross West Bush Lake Road north of Birchwood.
This closure has been coordinated with Hennepin County. Hennepin County plans on
performing some culvert repair and replacement along East Bush Lake Road starting
May 24. The County work is scheduled for non rush hour. There will be times when
East Bush Lake Road is down to one lane with flaggers as the County completes their
work. Motorists should plan for additional time while traveling through the area.
Installation of erosion control, tree removals along with hardscape removals are
the first activities planned for West Bush Lake Road. Storm sewer pipe installation
will follow the removals.
-
Pennsylvania area
The Contractor plans on beginning removals on during the week of June 1.
-
Colorado area (includes Colorado Circle, W. 93rd Street, and Izaak
Walton)
Installations of erosion control and tree removals are planned for the week of May 24
in the Izaak Walton area.
-
Lyndale area (includes 96th Street)
The Contractor plans on beginning work on the signal at Lyndale and 98th Street on
Monday, May 24. There may be lane closures Monday and Tuesday to accommodate the signal
modifications including removing medians. The major traffic switch will occur on
Wednesday, May 26. The traffic will be reduced to one lane in each direction on Lyndale
and shifted to the west side of the road. The contractor will remove the existing
pavement on the east side. Once the removals occur, the site will be turned over to
Centerpoint Energy who has approximately two months of gas installation work.
PMP Street Maintenance Project
-
Pleasant area
The milling that was to occur this week has been delayed due to the gas company work.
The plan is to mill and pave the road the week of May 24. The disturbed areas will be
sodded the week of May 24.
-
Garfield area
The area has been paved. There are a few areas where sod replacement needs to still
occur. Restriping will occur late next week.
-
Portland area
The disturbed areas will be sodded the week of May 24. With milling and paving also
anticipated that week.
-
Wellswood area
The Centerpoint Energy crew has not been in the area to install new services. The
Contractor wants to wait until the gas service work is complete to perform the curb
repairs in the area so that the new curb is not damaged. However, this may not be
possible depending on Centerpoint’s schedule.
-
Lakeview area
The disturbed areas will be sodded the week of May 24. Milling of the street is
anticipated the week of June 1.
-
Maryland area
Patching of disturbed areas will continue. The disturbed areas behind the curb will be
sodded the week of May 24.
-
West Bush Lake Road
Phase 2 of the road closure begins Monday, May 24 with West Bush Lake Road between
W. 95th Street and W. 86th Street being closed. This closure is anticipated to be
for approximately two weeks. The detour route for all three phases will be West
Bush Lake Road to East Bush Lake Road to W. 86th Street. There will also be detour
signs posted on Bloomington Ferry Road and Lindstrom for Phases 2 and 3. Local
residents will be able to access their homes, but there will be a hard closure that
prohibits through movements north of Birchwood Lane. Residents will need to plan
their access accordingly since they will not be able to cross north of Birchwood.
This closure has been coordinated with Hennepin County. Hennepin County plans on
performing some culvert repair and replacement along East Bush Lake Road starting
May 24. The County work is scheduled for non rush hour. There will be times when
East Bush Lake Road is down to one lane with flaggers as the County completes their
work. Motorists should plan for addition time while traveling through the area.
The curb and storm sewer removal and replacement have been completed. The road is
scheduled to be milled on Friday, May 28 with paving tentatively planned for
Friday, June 4 depending on weather.
-
E. 90th Street
Xcel plans on beginning work along E. 90th Street to relocate power poles out of the
way of the new trail segment.
-
Washburn area
Qwest plans on beginning work on Russell Avenue sometime during the week of May 24 to
relocate a vault in advance of the contractor.
May 14, 2010
PMP Street Maintenance Project
-
Pleasant Area
Curb, gutter and storm sewer repairs are occurring. Centerpoint Energy is working in
the area to comply with the MNOPS alert requirements and digging down to each sewer
service. Milling of the area is projected to occur around May 18, although this may
need to change if Centerpoint is not complete with their work.
-
Garfield Area
Sod was not installed last week as it was too wet. The contractor hopes to install it
this upcoming week provided that the ground and the sod field both dry out enough.
Milling and overlaying of Garfield, Grand and 97 ½ is planned to occur during the week
of May 17. The Contractor will be raising iron in advance of this work.
-
Portland Area
Centerpoint Energy is only a day behind in completely the bonding work in this area
and plans on being complete on Monday, May 17. The Contractor will be installing
topsoil and sod if the ground and the sod field both dry out enough. Milling of the
road is scheduled for mid to late next week.
-
Wellswood Area
Centerpoint Energy has installed a new main and will be working on new services. They
expect to be complete with the service work around May 25. It is unclear if this
schedule will be met based on the new requirements from MNOPS. Curb replacement in the
area will not occur until after the gas service work is complete.
-
Lakeview Area
Storm sewer construction, curb and gutter removal and replacement have begun and will
continue into next week.
-
Maryland Area
Storm sewer construction, curb and gutter removal and replacement have begun and will
continue into next week.
-
West Bush Lake Road
Work on the 2010-102 (Overlay) project is being coordinated with the 2010-101 PMP
reconstruct project so that the West Bush Lake Road closures overlap and reduce the
closure time impact on the traveling public from two months to one month.
There will be three phases of West Bush Lake Road closures. The first phase of the
closure will begin on Monday, May 17 with the 2010-102 PMP overlay project initially
closing the segment of West Bush Lake Road between Veness Road and W. 86th Street. The
following week Phase 2 of the closure begins with West Bush Lake Road between W. 95th
Street and W. 86th Street will be closed. This closure is anticipated to be for
approximately two weeks. The third phase of the closure will be West Bush Lake Road
between W. 95th Street and Veness Road. The detour route for all three phases will be
West Bush Lake Road to East Bush Lake Road to W. 86th Street. There will also be detour
signs posted on Bloomington Ferry Road and Lindstrom for Phase 2 and 3. By keeping the
detour route the same we hope to eliminate some confusion between the phases. This
closure has been coordinated with Hennepin County. Local residents will be able to
access their homes, but there will be a hard closure that prohibits through movements
north of Birchwood Lane. Residents will need to plan their access accordingly since
they will not be able to cross north of Birchwood. Phase 1 closure information has been
posted on the website and emergency service staff has been notified. Staff will
continue to update the website and notify the emergency service staff and will be
speaking on Bloomington Today.
May 14, 2010
PMP Street Improvement Project
The contract has been signed. The preconstruction conference is scheduled for Monday, May
17.
-
West Bush Lake Road
Work on the 2010-101 (Reconstruct) Project is scheduled to begin Monday, May 24 at
West Bush Lake Road. West Bush Lake Road will be closed to enable the work to occur.
This work is being coordinated with the 2010-102 PMP overlay project so that the West
Bush Lake Road closures overlap and reduce the closure time impact on the traveling
public from two months to one month.
-
Pennsylvania Area
The Contractor plans on beginning work on Monday, May 24.
-
Colorado Area
The Contractor plans on beginning work on Monday, May 24.
-
Lyndale Area
The Contractor plans on beginning removals on Monday, May 24. Once the removals occur,
the site will be turned over to Centerpoint Energy who has approximately two months of
work.
May 10, 2010
PMP Street Maintenance Project
-
Pleasant Area
Curb, gutter and storm sewer repairs are occurring. Centerpoint Energy is complete
with their work in this area. Milling of the area is projected to occur around May 18.
-
Garfield Area
Sod will be installed along Garfield the week of May 10 provided that the sod field
does not get too wet with the weekend rain.
-
Portland Area
Storm sewer installation, removal and replacement of curb, gutter and sidewalk are
under way. Centerpoint Energy plans on using a keyhole technology to bond couplings on
their facility along Portland Avenue which is expected to be completed by May 14,
weather dependent.
-
Wellswood Area
Storm sewer construction, curb and gutter removal and replacement have begun.
Centerpoint Energy has installed a new main and will be working on new services. They
expect to be complete with the service work around May 25. Curb replacement in the area
will not occur until after the gas service work is complete.
-
Lakeview Area
Storm sewer construction, curb and gutter removal and replacement were delayed and
will begin the week of May 10.
-
Maryland Area
Storm sewer construction, curb and gutter removal and replacement were delayed and
will begin the week of May 10.
-
West Bush Lake Road
Signs informing the motoring public regarding the upcoming closure of West Bush Lake
Road will be in place on May 10. West Bush Lake Road between Veness Road and W. 86th
Street will be closed one week starting May 17 to facilitate the storm sewer
construction. The detour route will be West Bush Lake Road to East Bush Lake Road to W.
86th Street. This closure has been coordinated with Hennepin County who will be doing
some culvert work on East Bush Lake Road during the week of May 10. This will be the
first of two closures expected for the overlay project construction work. Local
residents will be able to access their homes, but there will be a hard closure that
prohibits through movements north of Birchwood Lane. Residents will need to plan their
access accordingly since they will not be able to cross north of Birchwood.
May 10, 2010
PMP Street Improvement Project
The contractor has signed the contract books and returned them to the City. The contract is
currently at the Legal Department for signatures.
April 2010
April 30, 2010
PMP Overlay
-
Pleasant Area
Curb, gutter and storm sewer repairs are occurring. Centerpoint Energy will be on site
to replace some services starting May 1.
-
Garfield Area
Curb, gutter and sidewalk will continue to be reconstructed. Bituminous pavement
patching is occurring and topsoil will be installed.
-
Portland Area
Storm sewer installation, removal and replacement of curb, gutter and sidewalk is
under way. Centerpoint Energy plans on using a keyhole technology to bond couplings on
their facility along Portland Avenue which will begin on May 7.
-
Wellswood Area
Storm sewer construction, curb and gutter removal and replacement will begin the week
of May 3rd.
-
Lakeview Area
Storm sewer construction, curb and gutter removal and replacement will begin the week
of May 3rd.
-
Maryland Area
Storm sewer construction, curb and gutter removal and replacement will begin the week
of May 3rd.
-
West Bush Lake Road
Storm sewer construction, curb and gutter removal and replacement will begin the week
of May 3rd.
April 23, 2010
PMP Reconstruct
The project is being advertised and is scheduled to open bids on April 30.
-
W. 86th Street Area
Centerpoint Energy has a project in the NE corner of Penn Ave. at 86th Street
underway. Centerpoint needs to weld an electrostop onto an existing 8" steel gas main
to insulate the main. This work is in advance of the City's contractor and has created
some confusion that the City's project is starting. The City's project will not begin
until after the bids are opened and awarded. The project is anticipated to begin at the
end of May although the Contractor may not elect to begin on W. 86th Street.
April 23, 2010
PMP Overlay
The Contractor hopes to begin the project during the week of April 26 provided that the
contract books are signed and the proper insurance is submitted. The Contractor plans on
beginning the project at Pleasant, Wellswood area and the Garfield area.
-
Pleasant Area
Street construction is scheduled to begin the week of April 26. Removal of curb and
gutter and storm sewer work will be the first construction activities.
-
Garfield Area
Street construction is scheduled to begin the week of April 26. Removal of curb and
gutter and storm sewer work will be the first construction activities.
-
Portland Area
Street construction is scheduled to begin the week of April 26. Centerpoint Energy
plans on using a keyhole technology to bond couplings on their facility along Portland
Avenue.
-
Wellswood Area
Street construction is scheduled to begin the week of May 2. Removal of curb and
gutter and storm sewer work will be the first construction activities.
December 2009
December 4, 2009
2010 PMP Reconstruct
The public hearing is planned for December 7 in front of City Council for the 2010 PMP
reconstruction project. Staff has requested deferment of two streets (Izaak Walton Road and
River Ridge Circle) to the December 21, 2009 meeting as some neighborhood issues are still
being worked out. A neighborhood open house is scheduled to discuss Izaak Walton Road on
Thursday, December 10 from 4:30-6:00 pm in the Public Works Training Room (1700 W. 98th
Street).
For more information, contact:
Shelly Pederson, City Engineer
1700 W. 98th Street
PH: 952-563-4870, FAX: 952-563-4868
E-mail: engineering@ci.bloomington.mn.us
Streets HOME |
Current projects |
PMP |
Specifications
|