Project updates

Pavement Management Program (PMP)

The updates listed below refer to the Pavement Management Program (PMP) . To find updates regarding other projects, go to major road construction projects.

November 2011

November 29, 2011
2012-101 PMP Street Improvement Project

The public hearing was held on November 21. All streets were ordered by Council, except for Harriet Avenue, Garfield Avenue, Stanley Circle and American Boulevard West. The hearing for these four segments has been continued and will be heard at the Monday, December 5 Council meeting.

November 10, 2011
2012-101 PMP Street Improvement Project

Notices regarding the 2012 PMP Street Improvement Project have been mailed to all affected properties. Public information meetings are scheduled for November 14 at 2:00 p.m. and 5:30 p.m. in the Public Works Training Room. The public hearing is scheduled for November 21.

2011-101 PMP Street Improvement Project
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Final striping is complete. Punch list work remains.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Sod/Seed installation is complete. Punch list work remains.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Sod/seed installation is complete. Punch list work remains.
November 4, 2011
2011-101 PMP Street Improvement Project
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Sod/Seed installation is complete. The final layer of bituminous has been paved and E 90th St has been opened to traffic. Final striping of E 90th St is anticipated to complete by the end of the day Friday, November 4. Punch list work remains.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Sod/Seed installation is anticipated to complete by the end of the day Friday, November 4. Punch list work remains.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Sod/seed installation is anticipated to complete by the end of the day Friday, November 4. Punch list work remains.

October 2011

October 28, 2011
2011-101 PMP Street Improvement Project
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    The first two layers of bituminous have been paved. Manholes and gate valves have been raised. Sod/Seed installation has started and will continue the week of October 31. The final layer of bituminous is scheduled to be paved the week of October 31. E 90th Street from Portland Ave to 12th Ave is currently closed. The duration of this closure will be approximately 6-8 weeks. A detour is provided for this closure.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Sod/Seed installation has started and will continue the week of October 31. The final layer of bituminous has been paved.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    The final layer of bituminous has been paved. Sod/seed installation will start the week of October 31.
October 21, 2011
2011-101 PMP Street Improvement Project
  • 101st and Utah Traffic Circle

    Plantings are complete. Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    The contractor has been granted a noise exception from 7am - 9am on Saturday, October 22 in this area. Concrete work is complete. The first two layers of bituminous have been placed. Boulevard restoration has started and will continue the week of October 24. The contractor plans to raise manholes and gate valves the week of October 24. Sod/Seed installation is scheduled for late in the week of October 24 and will continue into the week of October 31. The final layer of bituminous is anticipated to be placed the week of October 31. E 90th Street from Portland Ave to 12th Ave is currently closed. The duration of this closure will be approximately 6-8 weeks. A detour is provided for this closure.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    The contractor has been granted a noise exception from 7am - 9am on Saturday, October 22 in this area. Sod/seed installation has started and will continue the week of October 24. Manholes and gate valves have been raised. The final layer of bituminous is anticipated to be placed late in the week of October 24 or the week of October 31.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Manholes and gate valves have been raised. The final layer of bituminous is anticipated to complete by the end of the day on Friday, October21. Sod/seed installation is scheduled for the week of October 24.
October 13, 2011
2011-101 PMP Street Improvement Project
  • Queen Avenue area Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    City Staff continues to work with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in late October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • 101st and Utah Traffic Circle

    Now that the weather pattern has changed, the contractor anticipates planting late this week or during the week of October 17.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Punch list work remains. City Staff continues to work with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in late October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Concrete work continues in the area and is anticipated to complete early in the week of October 17. Final grading in preparation for paving of the first layer of bituminous will complete the week of October 17. The contractor anticipates paving the first layer of bituminous the week of October 17 with boulevard restoration to follow. E 90th Street from Portland Ave to 12th Ave is currently closed. The duration of this closure will be approximately 6-8 weeks. A detour is provided for this closure.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Boulevard restoration continues in the area and will continue into the week of October 17. Sod/seed installation is anticipated to occur the week of October 17. The contractor also plans to raise manholes and gate valves the week of October 17. The final layer of bituminous will be placed upon completion of sod/seed installation and is anticipated to occur the week of October 24.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Boulevard restoration will continue the week of October 17. Sod/seed installation is anticipated to occur the week of October 17. The contractor also plans to raise manholes and gate valves the week of October 17. The final layer of bituminous will be placed upon completion of sod/seed installation and is anticipated to occur the week of October 24.
October 7, 2011
2011-101 PMP Street Improvement Project

Many area only have punch list work remaining, which include:

  • Hyland Greens Drive area
  • W 106th Street
  • W 82nd Street
  • W 96th Street area
  • Queen Avenue area Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Punch list work remains. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early-mid October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • 101st and Utah Traffic Circle

    Due to the current unseasonably warm/dry pattern, the Contractor desires to wait until the weather breaks to finish the plantings in this area. This work is now anticipated to occur late in the week of October 10 or early the following.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Paving of the final layer of bituminous is complete. Punch list work remains. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early-mid October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Paving of the final layer of bituminous is complete. Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Sanitary and storm sewer replacements are complete. Concrete work continues in the area and will continue the week of October 10. Grading in preparation for paving of the first layer of bituminous continues and will continue the week of October 10. The contractor anticipates paving the first layer of bituminous the week of October 17. E 90th Street from Portland Ave to 12th Ave is currently closed. The duration of this closure will be approximately 6-8 weeks. A detour is provided for this closure.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    The contractor has been granted a noise exception from 7am - 9am on Saturday, October 10 in this area. Boulevard restoration continues in the area and will continue into the week of October 10.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Boulevard restoration has started and will continue the week of October 10.

September 2011

September 30, 2011
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Punch list work remains.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Punch list work remains. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early-mid October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    Punch list work remains.
  • 101st and Utah Traffic Circle

    Plantings have been slightly delayed and are anticipated to occur the week of October 3.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    Punch list work remains.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Sod installation is complete. Manholes and gate valves have been raised in the area. Paving of the final layer of bituminous is anticipated to occur the week of October 3. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early-mid October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Sod installation is complete. The Contractor has started raising manholes and gate valves in preparation for the final layer of bituminous. Paving of the final layer of bituminous is anticipated to occur the week of October 3.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    The contractor has been granted noise exception from 7am - 9am on Saturday, October 1 in this area. Sanitary and storm sewer replacements are anticipated to complete by the end of the day Friday, September 30. Concrete work has started in the area and will continue the week of October 3. Grading and placement of Class 5 is scheduled for the week of October 3. E 90th Street from Portland Ave to 12th Ave is currently closed. The duration of this closure will be approximately 6-8 weeks. A detour is provided for this closure.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    The contractor has been granted a noise exception from 7am - 9am on Saturday, October 1 in this area. Paving of the first layer of bituminous and driveways in the area is complete. Boulevard restoration has started and will continue the week of October 3.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Paving of the first layer of bituminous and driveways in the area is complete. Boulevard restoration has started and will continue the week of October 3.
September 23, 2011
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Punch list work remains.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    The final layer of bituminous has been placed. Punch list work remains. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    Striping in the area is complete. Punch list work remains.
  • 101st and Utah Traffic Circle

    Plantings are scheduled for the week of September 26.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    The final layer of bituminous has been placed and final striping is complete. Punch list work remains.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Sod installation has started in the area and is anticipated to complete Friday, September 23. The Contractor plans to raise manholes and gate valves the week of September 26 in preparation for the final layer of bituminous. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Sod installation has started in the area and will continue the week of September 26. The Contractor plans to raise manholes and gate valves the week of September 26 in preparation for the final layer of bituminous.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Pavement removal is complete. Sanitary and storm sewer replacements have started in the area and will continue the week of September 26. E 90th Street from Portland Ave to 12th Ave is currently closed. The duration of this closure will be approximately 6-8 weeks. A detour is provided for this closure.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Concrete work is complete. Grading in preparation for the first layer of bituminous is nearly complete. Paving of the first layer of bituminous is scheduled for early in the week of September 26 in the area with paving of bituminous driveways to follow. Boulevard restoration is scheduled to begin the week of September 26.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Concrete work is complete. Grading in preparation for the first layer of bituminous will complete early in the week of September 26. Paving of the first layer of bituminous is scheduled for the week of September 26 with paving of bituminous driveways and boulevard restoration to follow.
2011-102 PMP Street Maintenance Project

The contractor will continue working on various punch list items.

September 16, 2011
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Punch list work remains.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    The final layer of bituminous has been placed. Punch list work remains. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The final layer of bituminous has been placed and final striping is nearly complete in the area and will complete early in the week of September 19. Punch list work remains.
  • 101st and Utah Traffic Circle

    Plantings are scheduled to be complete by the end of September.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    The contractor has been granted a noise exception for Saturday, September 17 from 6am - 9am in this area. Electrical work for the signal system at 82nd St/E Bloomington Fwy is complete. W 82nd St will be closed from I-35W to Aldrich Ave on Saturday, September 17 from 6am - 6pm to pave the final layer of bituminous. This will include the closure of the on and off ramps for northbound I-35W at W 82nd St. A detour will be provided for this closure. Final striping is scheduled for early in the week of September 19.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Sod installation in the area has been slightly delayed and is scheduled to begin the week of September 19. City Staff will be working with rain garden residents on scheduling plantings. Planting of the rain gardens is anticipated to occur in early October. Installation of mulch within the rain gardens will occur upon completion of planting.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Bituminous driveways have been placed. Boulevard restoration will continue the week of September 19.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    E 90th Street from Portland Ave to 12th Ave will be closed beginning Monday, September 19. The duration of this closure will be approximately 6-8 weeks. A detour will be provided for this closure. The contractor plans to begin pavement removal on Monday, September 19. Storm and Sanitary sewer work is scheduled to begin the week of September 19.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Concrete work has started in the area and will complete early in the week of September 19. Grading in preparation for the first layer of bituminous is scheduled for the week of September 19.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Pavement removal is complete. Storm sewer work is complete. Initial grading/placement of class 5 will be complete by the end of the day Friday, September 16. Concrete work is scheduled to begin early in the week of September 19 with grading for the first layer of bituminous to follow.
2011-102 PMP Street Maintenance Project

The contractor will begin working on various punch list items.

September 9, 2011
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Punch list work remains.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Planting of the rain gardens is anticipated to occur in mid-late September. Sod installation is complete. Placement of the final layer of bituminous will be complete by the end of the day Friday, September 9.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The contractor has been granted a noise exception for Saturday, September 10 from 6am - 9am in this area. The signal system at W 106th St/Humboldt Ave has been activated. W 106th St from Humboldt Ave to I-35W will be closed on Saturday, September 10 from 6am - 6pm to pave the final layer of bituminous. This will include the closure of the on and off ramps for southbound I-35W. A detour will be provided for this closure. Final striping for the area is scheduled for Tuesday, September 13 (weather permitting).
  • 101st and Utah Traffic Circle

    Planting soil within the traffic circle has been placed with plantings scheduled for early fall.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    Sod installation is complete. Electrical work for the signal system at 82nd St/E Bloomington Fwy has started and will complete early in the week of September 12. W 82nd St will be closed from I-35W to Lyndale Ave on Saturday, September 17 from 6am - 6pm to pave the final layer of bituminous. This will include the closure of the on and off ramps for northbound I-35W at W 82nd St. A detour will be provided for this closure.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Boulevard restoration and grading of the rain gardens in the area is complete. Sod installation is scheduled for the week of September 12.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    The contractor has been granted a noise exception for Saturday, September 10 from 7am - 9am in this area. Concrete work is complete. The first layer of bituminous has been placed. Bituminous driveways are scheduled to be paved starting Monday, September 12 with boulevard restoration to follow.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    The contractor anticipates beginning pavement removal in this area the week of September 19. E 90th Street from Portland Ave to 12th Ave will be closed beginning Monday, September 19. The duration of this closure will be approximately 6-8 weeks. A detour will be provided for this closure.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    The contractor has been granted a noise exception for Saturday, September 10 from 7am - 9am in this area. Storm sewer work is complete. Initial grading/placement of class 5 in the area is complete. Concrete work is scheduled for the week of September 12.
  • Halsey Lane
    Halsey Lane from Lyndale Avenue to East Terminus

    Pavement removals are scheduled to begin Monday, September 12. Initial grading/placement of Class 5 and storm sewer work is scheduled for the week of September 12.
2011-102 PMP Street Maintenance Project
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    Paving is complete. Punchlist work remains. Centerpoint needs to repair irrigation lines and resod in areas that were disturbed with their gas main replacement project. This has caused some confusion in the neighborhood as to why some areas have been restored and others have yet to be.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    Placement of sod has begun and will continue the week of September 12.
  • Old Cedar Avenue
    Old Cedar Avenue from American Blvd to E. 80th Street

    Paving is complete. Punchlist work remains.
  • E. 84th Street
    E. 84th Street from Stevens Avenue to 2nd Avenue

    Paving is complete. Punchlist work remains.
September 6, 2011
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Punch list work remains.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Final grading of the planting soil in the rain gardens is nearly complete. Planting of the rain gardens is anticipated to occur in mid-late September when the weather is more accommodating for planting. Sod placement is anticipated to complete by the end of the day Friday, September 2 (weather permitting). The contractor has started raising manholes and gate valves in preparation for the final layer of bituminous and will continue the week of September 5. Placement of the final layer of bituminous is anticipated to occur either the week of September 5 or September 12.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    Sod installation is complete. Final wiring for the signal at W 106th St/Humboldt Ave will be complete by the end of the day Friday, September 2. Activation of the signal system is anticipated to occur Tuesday, September 6. The Bloomington Police Department will be on hand the morning of Tuesday, September 6 to aid in traffic control prior to activating the signal system due to the start of school. All lane closures will be removed by the end of the day Friday, September 2 in advance of school starting on September 6. The contractor plans to close W 106th St from Humboldt Ave to I-35W on Saturday, September 10 from 6am - 6pm to pave the final layer of bituminous. This will include the closure of the on and off ramps for southbound I-35W. A detour will be provided for this closure.
  • 101st and Utah Traffic Circle

    Planting soil within the traffic circle has been placed with plantings scheduled for early fall when the weather is more accommodating.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    The contractor has completed raising manholes and gate valves in the area. Boulevard restoration and sod installation is anticipated to complete by the end of the day Friday, September 2 (weather permitting). Electrical work for the signal system at 82nd St/E Bloomington Fwy is anticipated to occur the weeks of September 5 and 12. The contractor anticipates closing W 82nd St from I-35W to Aldrich Ave on Saturday, September 17 to pave the final layer of bituminous. A detour will be provided for this closure.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    The first layer of bituminous has been placed. Concrete work and bituminous driveway installation is complete. Boulevard restoration and grading of the rain gardens in the area has started and will continue the week of September 5.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Concrete work has started and will complete the week of September 5. Grading of class 5 in preparation for the first layer of bituminous will occur the week of September 5. The first layer of bituminous is scheduled to be placed late in the week of September 5.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    The contractor anticipates starting this area in mid-September.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Pavement removal in the area is complete. Storm sewer work has started in the area and will continue the week of September 5. Initial grading/placement of class 5 has started in the area and will continue the week of September 5.
2011-102 PMP Street Maintenance Project
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    The paving is anticipated to be complete by end of day, September 2. It may be necessary to finish a few paving items on Tuesday, September 6 depending on the weather on Friday.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    Placement of sod is scheduled for the week of September 5.
  • Old Cedar Avenue
    Old Cedar Avenue from American Blvd to E. 80th Street

    Paving is scheduled for Tuesday, September 6, weather dependant. Striping the road is tentatively scheduled for Friday, September 9.
  • E. 84th Street
    E. 84th Street from Stevens Avenue to 2nd Avenue

    Paving is scheduled for Tuesday, September 6, weather dependant.

 

August 2011

August 26, 2011
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Punch list work remains.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Final grading of the planting soil in the rain gardens is anticipated to occur the week of August 29. Planting of the rain gardens is anticipated to occur in mid-late September when the weather is more accommodating for planting.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The contractor has been granted a noise exception for Saturday, August 27 from 7am - 9am in this area and plans to raise manholes and gate valves in the area. Bituminous path installation on the north side of W 106th St is complete. Concrete work on W 106th Street is complete. Boulevard restoration and topsoil placement has started and will continue the week of August 29. Sod installation is scheduled for the week of August 29. Final wiring for the signal at W 106th St/Humboldt Ave is dependent on when all remaining material is delivered, which is anticipated to occur the week of August 29. The contractor anticipates paving the final layer of bituminous on Saturday, September 10.
  • 101st and Utah Traffic Circle

    Planting soil within the traffic circle has been placed with plantings scheduled for early fall when the weather is more accommodating.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    The contractor has been granted a noise exception from Friday, August 26 at 10pm to 9am Saturday, August 27, and also from 9pm Saturday, August 27 through 7am Monday, August 29 for street reconstruction and paving of the first two layers of bituminous in the area of the on and off ramps from northbound I-35W on W 82nd St. The contractor will be closing W 82nd St at the on and off ramps from northbound I-35W Friday, August 26 at 7pm until Monday, August 29 at 5am. A detour will be provided for this closure. The first two layers of bituminous have been placed on the south side of W 82nd St. Upon completion of street reconstruction and paving at the on and off ramps, the contractor plans to switch traffic to the center lanes both EB and WB and close the outer lanes to allow for boulevard restoration the week of August 29.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    The contractor has been granted a noise exception for Saturday, August 27 from 7am-9am in this area and plans to pave the first layer of bituminous on Grand Ave and W 83rd St. The first layer of bituminous for the remainder of the area is scheduled to occur early in the week of August 29. Concrete work in the area is anticipated to complete the week of August 29. Boulevard restoration and grading of the rain gardens in the area is anticipated to begin the week of August 29.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Storm sewer work is complete. Initial grading/placement of Class 5 has started in the area and will continue the week of August 29. Concrete work is scheduled for the week of August 29.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy has completed service installation in the area. The contractor anticipates starting this area in mid-September.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    The contractor has started pavement removal in the area and will continue the week of August 29. Storm sewer work is scheduled to begin the week of August 29.
2011-102 PMP Street Maintenance Project
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    Sod installation for the areas disturbed with the City project will be wrapping up the week of August 29. Please note that areas disturbed by Centerpoint Energy for their new gas main and services that need sod likely will not be complete on this same schedule and will occur later. Milling is scheduled for Tuesday & Wednesday, August 30 & 31 with paving to start on Wednesday, August 31 and continue through Friday, September 2, weather dependant.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    Placement of sod and repair of irrigation system is scheduled for the week of August 29.
  • Old Cedar Avenue
    Old Cedar Avenue from American Blvd to E. 80th Street

    Curb removals and replacement will begin on Monday, August 29. Milling is scheduled for Wednesday, August 31.
  • E. 84th Street
    E. 84th Street from Stevens Avenue to 2nd Avenue

    Curb removals and replacement will begin on Monday, August 29. Milling is scheduled for Wednesday, August 31.
August 22, 2011
2011-101 PMP Street Improvement Project
W 82nd Street closed for reconstruction

W 82nd St will be closed at the northbound on and off ramps to I-35W starting at 7 p.m. Friday, August 26. This closure will be re-opened by 5 a.m. on Monday, August 29. The contractor will be reconstructing W 82nd St in this area during the closure. Those that wish to exit to W 82nd St from Northbound I-35W will be detoured to I-494 East and then south on Lyndale Ave to get back to W 82nd St for the duration of this closure.

detour map
August 19, 2011
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    The final layer of bituminous has been placed. Final clean up and punch list work remains.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Rain garden excavation is complete and planting soil has started to be placed and will continue the week of August 22.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The contractor has been granted a noise exception for Saturday, August 20 from 7am - 9am in this area and plans to begin grading/restoring the boulevards in the area. Power poles have been relocated on W 106th Street with wire transfer nearly complete. Existing poles in need of removal for bituminous path installation have been removed and bituminous path installation is anticipated to complete by the end of the day August 19 (weather permitting). Final concrete work on W 106th Street will occur the week of August 22. Boulevard restoration and sod installation is scheduled to occur the weeks of August 22 and 29.
  • 101st and Utah Traffic Circle

    Planting soil within the traffic circle has been placed with plantings scheduled for early fall when the weather is more accommodating.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    Initial grading/placement of class 5 has completed on the south side of W 82nd Street. Concrete work has started on the south side and will continue the week of August 22. Final grading prior to placement of the first layer of bituminous is scheduled to occur the week of August 22. The Contractor plans to close W 82nd Street at the on and off ramps of northbound I-35W on Friday, August 26 at 7pm until Monday, August 29 at 5am. A detour will be provided for this closure. Street reconstruction and paving of the first two layers of bituminous will take place during this closure. The Contractor also plans to pave the first two layer of bituminous on the south side of W 82nd Street during this closure.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Initial grading prior to curb and gutter placement is complete. Concrete work has started and will continue the week of August 22. Final grading prior to paving of the first layer of bituminous is scheduled to occur the week of August 22.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Center point has completed service installation in the area. The contractor has been granted a noise exception for Saturday, August 20 from 7am - 9am in this area. Pavement removal in the area is complete. Storm sewer work and grading/placement of Class 5 is scheduled to occur the week of August 22.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    The final layer of bituminous has been placed. Final clean up and punch list work remains.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy has completed service installation in the area.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Centerpoint Energy has completed service installation in the area. The contractor anticipates to begin pavement removal on Park Ave from 96th - 92nd the week of August 22 with storm sewer work to follow.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites. There are several locations where work was also performed by Centerpoint Energy within the City construction areas. While the City's contractor has installed sod for areas disturbed with the City project, Centerpoint has not installed sod in the areas they disturbed which has created some confusion for some residents as to why some spots have sod and others do not. Centerpoint does not anticipate beginning sod installation until after August 15 nor do they include a clause in their contract for watering like the City does for the first 30 days and each individual resident is responsible for the initial watering.

  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    Installation of topsoil will begin August 22 with sod installation to follow. The contractor will also be working on adjusting manholes and gate valves in the street in preparation for milling the road. Milling is scheduled for Tuesday, August 30 with paving to follow later in the week.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    W. 102nd Street was paved this past week. Stripes will be placed on Monday, August 22. Placement of sod and repair of irrigation system remains.
  • Old Cedar Avenue
    Old Cedar Avenue from American Blvd to E. 80th Street

    The contractor anticipates moving into this area sometime the week of August 29.
August 15, 2011
2011-102 PMP Street Maintenance Project
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    W. 102nd Street between Abbott Avenue and Normandale Avenue will be closed on Wednesday & Thursday, August 17 & 18 starting at 7 am for two days to pave the road. (Rain day-Friday, August 19). Driveway access for residents who live on W. 102nd Street and access to Toledo Circle will be allowed during the closure. The no parking restriction on the side streets will not be enforced while the paving operation is under way in case some residents choose to park there instead. Bloomington Jefferson High School has "Jump Start" which is freshman orientation scheduled for both of these days. The paving schedule has been tweaked to accommodate these program sessions as much as possible and access to Bloomington Jefferson High School from Johnson Road via Heritage Hill Drive will not be affected.

August 12, 2011
2010-101 PMP Street Improvement Project
  • Russell Avenue area
    Russel Avenue between 81st Street and 82nd Street,
    82nd Street from Russell Avenue to Penn Avenue


    The final layer of pavement has been placed. Only punchlist work remains.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Sod installation is complete. Manholes and gate valves have been adjusted. The contractor anticipates placing the final layer of bituminous early in the week of August 15.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    The contractor has been granted a noise exception for Saturday, August 13 from 7am - 9am in this area and plans to begin excavation for rain water gardens. Concrete work and sod installation is complete, except for in the areas of the proposed rain water gardens. Rain garden excavation will continue the week of August 15.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The contractor has been granted a noise exception for Saturday, August 13 from 7am - 9am in this area and plans to grade the bituminous path. Power poles have been relocated on W 106th Street with wire transfer to the new poles remaining and this work is anticipated to complete the week of August 15. Wiring for the signal work at W. 106th/Humboldt continues and will continue the week of August 15. Concrete work on the south side of W 106th Street is complete. Bituminous path installation and remaining concrete work on the north side of W 106th Street is anticipated to occur upon completion of power pole relocation and wire transfer to the new poles.
  • 101st and Utah Traffic Circle

    Sod installation is complete. Planting soil within the traffic circle is anticipated to be placed by the week of August 15, with plantings scheduled for early fall when the weather is more accommodating.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    The contractor has been granted a noise exception for Saturday, August 13 from 7am - 9am in this area and plans to begin grading the south half of W 82nd Street which will continue the week of August 15. Concrete work and paving of the first two layers of bituminous on the north side of W 82nd Street is complete. Traffic has been switched to the north half of W 82nd Street. Pavement removal on the south half of W 82nd Street is anticipated to complete by the end of the day August 12.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Storm sewer work is complete. Grading has started in the area and will continue the week of August 15. Concrete work is anticipated to begin late in the week of August 15.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Centerpoint Energy anticipates completing service installation by the end of the day August 12. The contractor anticipates beginning pavement removals the week of August 15 with storm sewer work to follow late in the week.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Sod installation is complete. Manholes and gate valves have been adjusted. The contractor anticipates paving the final layer of the bituminous the week of August 15.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy has started installing services in the area and will continue the week of August 15.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Centerpoint Energy has started installing services in the area and will continue the week of August 15.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites. There are several locations where work was also performed by Centerpoint Energy within the City construction areas. While the City's contractor has installed sod for areas disturbed with the City project, Centerpoint has not installed sod in the areas they disturbed which has created some confusion for some residents as to why some spots have sod and others do not. Centerpoint does not anticipate beginning sod installation until after August 15 nor do they include a clause in their contract for watering like the City does for the first 30 days and each individual resident is responsible for the initial watering.

  • Briar area
    Briar Road from Vessey Road to Wildwood Circle,
    Briar Circle,
    Wildwood Circle from Wildwood Road to east terminus,
    Wildwood Road from 102nd Street to Wildwood Circle


    Punchlist work remains on this site along with clean up work from Comcast under their utility permit.
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    The contractor has a noise variance to allow work to begin at 7 am on Saturday, August 13. Concrete curb and gutter replacement is underway and is likely to finish on Monday, August 15. Paving the base layer of pavement in areas where the watermain replacement occurred is scheduled for Tuesday, August 16, weather permitting. Site work will continue the remainder of the week.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    The contractor has a noise variance to allow work to begin at 7 am on Saturday, July 13 and will be adjusting manholes, valve box covers and other items in advance of paving.

    On Wednesday & Thursday, August 17 & 18 the City of Bloomington plans on CLOSING W. 102nd Street between Abbott Avenue and Normandale Avenue for two days to pave the road. (Rain day-Friday, August 19). Driveway access for residents who live on W. 102nd Street and access to Toledo Circle will be allowed during the closure. The no parking restriction on the side streets will not be enforced while the paving operation is under way in case some residents choose to park there instead. The tentative schedule (weather dependant) has the contractor paving 102nd Street mainline and side street connections between France Avenue and Abbott Avenue and paving the side street connections to 102nd Street that were impacted by construction between France Avenue and Normandale Blvd on Wednesday, August 17. The schedule for Thursday, August 18 includes paving the mainline road between France Avenue and Normandale Blvd, starting at France on the south side.

    Bloomington Jefferson High School has "Jump Start" which is freshman orientation scheduled for both of these days. The paving schedule has been tweaked to accommodate these program sessions as much as possible and access to the High School from Johnson Road via Heritage Hill Drive will not be affected.

August 5, 2011
2010-101 PMP Street Improvement Project
  • Russell Avenue area
    Russel Avenue between 81st Street and 82nd Street,
    82nd Street from Russell Avenue to Penn Avenue


    The contractor has a noise variance to allow work to begin at 7 am on Saturday, July 23. The contractor will be installing seed and sod in the remaining boulevard areas and anticipates paving the road the week of August 1.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    The contractor has been granted a noise exception from 7am b in the area and plans to continue sod installation in the area. Due to the wet conditions earlier this week, sod installation was delayed but is winding down. The contractor plans to adjust manholes and gate valves the week of August 8.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Placement of the first layer of bituminous is complete. Paving of bituminous driveways is complete. Concrete work is anticipated to complete on Saturday, August 6. Boulevard grading and placement of topsoil continues and sod installation will occur the week of August 8.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    Due to the recent storms in the area, Xcel Energy has been slightly delayed, but continues power pole relocation in the area and anticipates completing late in the week of August 8. Wiring for the signal work at W. 106th/Humboldt continues and will continue the week of August 8. Concrete curb and gutter work on the east end of W 106th at I-35W is anticipated to complete the week of August 8. Bituminous path installation and remaining concrete work is anticipated to occur upon completion of power pole relocation.
  • 101st and Utah Traffic Circle

    Sod installation will be complete by early in the week of August 8. Planting soil within the traffic circle is anticipated to be placed by the week of August 15, with plantings scheduled for early fall when the weather is more accommodating.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    The contractor has been granted a noise exception from 7am b concrete work on the north half of W 82nd St. Grading and placement of Class 5 is anticipated to complete early in the week of August 8. Paving of the first two layers of bituminous on the north half of W 82nd St is scheduled for mid week of August 8 (weather permitting). If weather allows, when paving is complete, the contractor anticipates switching traffic to the north half of W 82nd St and beginning pavement removal on the south half late in the week of August 8.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Centerpoint Energy has completed gas main and service installation in the area. The contractor has started pavement removals in the area and will continue the week of August 8. Grading work has also started in the area and will continue the week of August 8. Storm sewer work will occur the week of August 8.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Centerpoint Energy has completed gas main installation in the area and are now installing services, which will continue the week of August 8. The contractor anticipates beginning pavement removals the week of August 15.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Sod installation will occur the week of August 8.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy finished gas main installation in the area with services remaining.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Centerpoint Energy has finished gas main installation in the area with services remaining.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites. There are several locations where work was also performed by Centerpoint Energy within the City construction areas. While the City's contractor has installed sod for areas disturbed with the City project, Centerpoint has not installed sod in the areas they disturbed which has created some confusion for some residents as to why some spots have sod and others do not. Centerpoint does not anticipate beginning sod installation until after August 15 nor do they include a clause in their contract for watering like the City does for the first 30 days and each individual resident is responsible for the initial watering.

  • Briar area
    Briar Road from Vessey Road to Wildwood Circle,
    Briar Circle,
    Wildwood Circle from Wildwood Road to east terminus,
    Wildwood Road from 102nd Street to Wildwood Circle


    The road has been milled and paving is scheduled for Monday, August 8, weather dependant.
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    The contractor has a noise variance to allow work to begin at 7 am on Saturday, August 6. The water system did pass the follow up bacteria testing and residents have been switched to the new system and the temporary water system has been removed. Grading of the area continues. Concrete curb and gutter replacement is scheduled to begin on Tuesday, August 9 and continue the rest of the week.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    The contractor has a noise variance to allow work to begin at 7 am on Saturday, August 6. Topsoil installation at the disturbed areas continues. The milling of the road is scheduled for August 10 and 11 with paving scheduled for the following week.

July 2011

July 29, 2011
2010-101 PMP Street Improvement Project
  • Russell Avenue area
    Russel Avenue between 81st Street and 82nd Street,
    82nd Street from Russell Avenue to Penn Avenue


    The contractor has a noise variance to allow work to begin at 7 am on Saturday, July 23. The contractor will be installing seed and sod in the remaining boulevard areas and anticipates paving the road the week of August 1.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    Paving of bituminous driveways is complete in the area. Boulevard restoration and placement of topsoil is winding down. Sod installation in the area is scheduled for the week of August 1 (weather permitting). Temporary mailboxes that were installed due to construction will be removed the week of August 1.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    The contractor has been granted a noise exception from 7am - 9am on Saturday, July 30 in the area. Placement of the first layer of bituminous has started and the contractor hopes to be complete by end of the day on July 29. Prepping and paving of bituminous driveways has started and will continue the week of August 1. Boulevard grading and placement of topsoil will also occur the week of August 1.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The contractor has been granted a noise exception from 7am - 9am on Saturday, July 30 in the area. Xcel Energy has started power pole relocation in the area and anticipates completing late in the week of August 1. Wiring for the signal work at W. 106th/Humboldt continues and will continue the week of August 1. Storm sewer work has completed in the area. Concrete curb and gutter work has completed on the south half of W 106th Street. Paving of the first two layers of bituminous on the south half of W 106th Street is anticipated to complete by the end of the day on July 29. The contractor anticipates opening up the south half of W 106th Street to traffic upon completion of paving Saturday, July 30 or early in the week of August 1, with lane closures in the outer lanes both east and westbound to allow for bituminous path and concrete walk installation.
  • 101st and Utah Traffic Circle

    Sod installation is scheduled to occur the week of August 1 (weather permitting).
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    Traffic control has been set up and traffic is now traveling on the south half of W 82nd Street from I-35W to Aldrich Ave. Pavement removal is complete on the north half of W 82nd Street. Grading work has started and will continue the week of August 1. Concrete work is anticipated to begin the week of August 1.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Centerpoint Energy has completed gas main installation in the area with service work anticipated to complete the week of August 1. The contractor anticipates starting bituminous pavement removal the week of August 1 with storm sewer work to begin late in the week upon completion of gas service installation.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Centerpoint Energy has completed gas main installation in the area with a service crew scheduled to begin the week of August 1.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    The first layer of bituminous has been placed in the area. Boulevard grading and placement of topsoil has started and will continue the week of August 1.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy finished gas main installation in the area with services remaining.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Centerpoint Energy has finished gas main installation in the area with services remaining.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites. There are several locations where work was also performed by Centerpoint Energy within the City construction areas. While the City's contractor has installed sod for areas disturbed with the City project, Centerpoint has not installed sod in the areas they disturbed which has created some confusion for some residents as to why some spots have sod and others do not. Centerpoint does not anticipate beginning sod installation until after August 15 nor do they include a clause in their contract for watering like the City does for the first 30 days and each individual resident is responsible for the initial watering.

  • Briar area
    Briar Road from Vessey Road to Wildwood Circle,
    Briar Circle,
    Wildwood Circle from Wildwood Road to east terminus,
    Wildwood Road from 102nd Street to Wildwood Circle


    Milling of the road is anticipated August 3, with paving to occur on either August 5 or August 8, weather dependant.
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    The contractor has a noise variance to allow work to begin at 7 am on Saturday, July 30. Water service installation is complete and the system did not pass the initial bacteria testing. It will need to be reflushed and tested again. Once the system passes the test, the contractor will begin switching residents back from the temporary water system to the permanent system and will begin removing the temporary water system. The contractor will be grading the areas disturbed for the watermain installation the week of August 1 and hopes to have rock on the road by the end of the week. Concrete curb and gutter replacement is scheduled for the week of August 8.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    The contractor has a noise variance to allow work to begin at 7 am on Saturday, July 30. Installation of concrete curb and gutter, sidewalks and pedestrian ramps are winding down and anticipated to be completed by end of day on Monday, August 1. The contractor will be patching the road and beginning to install topsoil at the disturbed areas the week of August 1. Sign bases will be installed on August 3 and 4, weather permitting.

    Hennepin County and Progressive Rail will be installing a new railroad crossing at France Avenue north of Old Shakopee Road. This work will require that France Avenue be closed from Thursday, August 4 through Tuesday, August 9. Given the proximity of the road closure to 102nd Street and the need for approximately 17,000 vehicles to use alternative routes, the milling that was scheduled for the week of August 1 along 102nd Street has been postponed for the safety of the crews and convenience of the motoring public.

    The milling of the road has been pushed back to August 10 and 11 with paving scheduled for the following week.

July 22, 2011
2010-101 PMP Street Improvement Project
  • Russell Avenue area
    Russel Avenue between 81st Street and 82nd Street,
    82nd Street from Russell Avenue to Penn Avenue


    The contractor has a noise variance to allow work to begin at 7 am on Saturday, July 23. The contractor will be working on adjusting the manholes and gate valve covers on the road for paving which is likely to occur the week of August 1. The contractor will be installing topsoil on July 25 and 26, weather permitting in advance of the sod installation.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    The contractor has been granted a noise exception from 7am - 9am on Saturday, July 23 in this area and plans to grade boulevards in preparation for topsoil/sod which will continue into the week of July 25. The first layer of bituminous has been placed in this area. Due to the extreme heat conditions concrete sidewalk work did not complete this week and is anticipated to complete early in the week of July 25. Paving of bituminous driveways continues in the area and will complete the week of July 25.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Initial grading work and placement of Class 5 has completed in the area. Concrete work has started in the area and will continue the week of July 25. Grading in preparation for bituminous placement will occur the week of July 25.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The contractor has been granted a noise exception from 7am - 9am on Saturday, July 23 in this area and plans to grade the bituminous path area along with boulevards. Due to the extreme heat conditions and numerous power outages throughout the state, Xcel energy was not in this week to begin power pole relocation on the north side of W 106th Street. Upon completion of the power pole relocation, the bituminous path will be placed and the retaining wall will be finished on the north half of W 106th Street. Wiring for the signal work at W 106th/Humboldt continues and will continue the week of July 25. Storm sewer work on the south half of W 106th St is anticipated to complete by the end of the day on July 22. Grading work and placement of Class 5 continues and will complete early in the week of July 25. Concrete work on the south half of W 106th Street is anticipated to occur early in the week of July 25. Grading in preparation for bituminous placement is scheduled for the middle of the week of July 25 with paving of the first two layers of bituminous scheduled for late in the week (weather permitting).
  • 101st and Utah Traffic Circle

    Bituminous patching in front of the replaced curb and topsoil placement around concrete sidewalk in the area has completed. Sod installation in the area and plantings within the traffic circle remain and due to the recent weather conditions are anticipated to be done when the weather allows.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    Traffic control has been set up and traffic is now traveling on the south half of W 82nd Street from I-35W to Aldrich Ave. Pavement removal on the north half of W 82nd Street is anticipated to complete by the end of the day on July 22. Minor storm sewer work and grading is scheduled for the week of July 25.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Centerpoint Energy has completed gas main installation in the area and is now working on services. Due to the extreme heat conditions service installation was delayed, but has started and will continue the week of July 25. The contractor anticipates starting bituminous pavement removal late in the week of July 25 or early in the week of August 1.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Centerpoint Energy has completed gas main installation in the area with service work remaining.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Initial grading work and placement of Class 5 has completed in the area. Concrete work has started and will complete early in the week of July 25. Grading in preparation for bituminous is scheduled for the week of July 25 along with paving of the first layer of bituminous.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy has started gas main installation in the area and will continue the week of July 25.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Centerpoint Energy has started gas main installation in the area and will continue the week of July 25.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites. There are several locations where work was also performed by Centerpoint Energy within the City construction areas. While the City's contractor has installed sod for areas disturbed with the City project, Centerpoint has not installed sod in the areas they disturbed which has created some confusion for some residents as to why some spots have sod and others do not. Centerpoint does not anticipate beginning sod installation until after August 15 nor do they include a clause in their contract for watering like the City does for the first 30 days and each individual resident is responsible for the initial watering.

  • Briar area
    Briar Road from Vessey Road to Wildwood Circle,
    Briar Circle,
    Wildwood Circle from Wildwood Road to east terminus,
    Wildwood Road from 102nd Street to Wildwood Circle


    Sod was installed in the neighborhood. The contractor will be adjusting manholes and gate valve covers the week of July 25. Milling of the road is anticipated sometime between August 3-5 with paving to follow soon after.
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    Water service installation has begun and will continue into the week of July 25. The water service installation is anticipated to be complete next week, and the City will flush and test the system prior to putting it into service. Storm sewer installation will begin after the water services are complete, likely around July 28 or 29. The contractor will be grading the areas disturbed for the watermain installation the week of August 1.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    Concrete curb and gutter, sidewalk and pedestrian ramps work will continue through the week of July 25. Milling of the road is tentatively scheduled for the end of the week of August 2 with paving to follow the end of the week of August 8.
July 15, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area
    Lyndale Avenue from 99th Street to 94th Street,
    96th Street west of Lyndale


    The waste receptacles and liners were installed this past week.
  • Russell Avenue area
    Russel Avenue between 81st Street and 82nd Street,
    82nd Street from Russell Avenue to Penn Avenue


    The concrete walk has been installed. The area is being prepped for installation of sod and seed, but given the extremely hot forecast, this work may not occur next week.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    The contractor anticipates finishing the first layer of bituminous in the area by the end of the day Friday, July 15 (weather permitting). Concrete sidewalk work remains on Hyland Greens Drive and will be finished the week of July 18. Paving of bituminous driveways has started in the area and will continue the week of July 18. Topsoil restoration is anticipated to begin the week of July 18.

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Storm sewer work has completed in the area. Grading work and placement of Class 5 will complete early in the week of July 18. Concrete work is anticipated to begin early in the week of July 18.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    Paving of the first two of three layers of bituminous has completed on the north half of W 106th Street. Xcel energy anticipates to be in the area the week of July 18 to begin power pole relocation on the north side of W 106th Street. Upon completion of the power pole relocation, the bituminous path will be placed and the retaining wall will be finished on the north half of W 106th Street. Placing of conduits for electrical work at the intersection of W 106th/Humboldt has completed and wiring/handhole placement will continue the week of July 18. The contractor plans to switch traffic to the north half of W 106th Street on Monday, July 18 and remove pavement on the south half on Tuesday, July 19. Storm sewer work will follow after pavement removal the week of July 18 along with grading late in the week of July 18. Concrete work on the south half of W 106th Street is anticipated to begin the week of July 25.
  • 101st and Utah Traffic Circle

    The concrete traffic circle has been installed and the additional concrete work for the pedestrian ramps in the intersection is complete. Bituminous patching in front of the replaced curb will occur the week of July 18.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    Bituminous pavement removal on the north half of this area is anticipated to occur late in the week of July 18. Traffic will be traveling on the south half of W 82nd Street from I-35W to Aldrich Ave for the duration of this phase. Minor storm sewer work and grading will occur the week of July 25.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Centerpoint Energy has completed gas main installation in the area and is now working on services. Service work will continue the week of July 18 and is anticipated to complete the week of July 25. The contractor anticipates starting bituminous pavement removal late in the week of July 25.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Centerpoint Energy has completed gas main installation in the area with service work remaining.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    Bituminous pavement removal has completed in the area. Grading will begin the week of July 18, with concrete work anticipated to begin the week of July 25.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy has started gas main installation in the area and will continue the week of July 18.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Centerpoint Energy has started gas main installation in the area and will continue the week of July 18.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites.

  • Briar area
    Briar Road from Vessey Road to Wildwood Circle,
    Briar Circle,
    Wildwood Circle from Wildwood Road to east terminus,
    Wildwood Road from 102nd Street to Wildwood Circle


    The first lift of pavement has been installed. The area is being prepped for installation of sod, but given the extremely hot forecast, this work may not occur next week. The contractor will be adjusting the various manhole and valve covers in preparation for milling of the road.
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    Watermain installation will continue into the week of July 18. Water service installation is likely to begin towards the end of the week after the main is installed.
  • Auto Club Road area
    Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave,
    Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road,
    W. 113th Street from Minnesota Bluffs Drive to east terminus,
    W. 114th Street from Auto Club Road to Minnesota Bluffs Drive,
    W. 114th Street Circles


    Punch list work remains to be completed in the area.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    Additional curb and gutter removals that were not associated with the storm sewer utility work will begin on Monday, July 18. The concrete crew is expected to begin installing the new curb and gutter on Wednesday, July 20, weather permitting. The Bloomington Utility crew will be working on replacement of a water valve at the intersection of W. 102nd Street and France Avenue on Monday, July 18. Milling of the road is tentatively scheduled for the end of the week of August 2 with paving to follow the end of the week of August 8.
July 8, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area
    Lyndale Avenue from 99th Street to 94th Street,
    96th Street west of Lyndale


    The remaining waste receptacles and liners will arrive and be installed the week of July 11.
  • Russell Avenue area
    Russel Avenue between 81st Street and 82nd Street,
    82nd Street from Russell Avenue to Penn Avenue


    The first layer of pavement has been installed. The Contractor will be grading the area for the new sidewalk, starting on Saturday, July 9. New concrete walk will be installed on approximately July 14 and 15, weather dependant.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive area
    Hyland Greens Drive from Nesbitt Avenue to Briar Road,
    Yosemite Road from Hyland Greens Drive to W 99th Street,
    Yosemite Circle from Yosemite Road to west terminus,
    W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
    W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
    W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus


    The contractor has been granted a noise exception from 7am b in this area and plans to grade Class 5 in preparation for paving. Concrete work continues in the area and will complete the week of July 11. Grading of Class 5 in preparation for paving has started and will continue into the week of July 11. Paving of the first layer of bituminous is anticipated for the week of the July 18th (weather permitting).

  • Queen Avenue area
    Queen Avenue from W 91st Street to south terminus,
    W 91st Street from Russell Avenue to Penn Avenue,
    W 92nd Street from Russell Avenue to Penn Avenue


    Bituminous pavement removals have started in the area along with reclamation of the bituminous stabilized base. Storm sewer work has also started in the area and will complete early in the week of July 11. Grading work has started and will continue into the week of July 11.
  • W 106th Street
    W 106th Streetfrom Humboldt Ave to I-35W

    The contractor has been granted a noise exception from 7am b this area and plans on removing pavement and grading the north half of the intersections of W 106th/Humboldt and W 106th/W Bloomington Fwy. Initial grading on W 106th St between Humboldt and W Bloomington Fwy is anticipated to complete by early in the week of July 11. Retaining wall work has started on the north side of W 106th St and is anticipated to complete early in the week of July 11. Placing of conduits for electrical work at the intersection of W 106th/Humboldt is scheduled for Monday, July 11. Concrete work has started in the area and will complete on the north half of W 106th St the week of July 11 (weather permitting). Grading in preparation for paving is anticipated to begin late in the week of July 11.
  • 101st and Utah Traffic Circle

    The concrete traffic circle has been installed and the additional concrete work for the pedestrian ramps in the intersection is complete. Restoration and plantings within the traffic circle remain.
  • W 82nd Street
    W 82nd Street from I-35W to Aldrich Avenue

    Centerpoint Energy crews have finished work in the area. Work in this area involves work within MnDOT ROW at the on and off ramps to northbound I-35W. Due to the current state government shutdown, no work can occur within MnDOT ROW, therefore this area will not begin until the shutdown has ended.
  • W 83rd Street area
    W 83rd Street from Lyndale Avenue to Grand Avenue,
    Garfield Avenue from W 82nd Street to south terminus,
    Harriet Avenue from W 82nd Street to south terminus,
    Grand Avenue from W 82nd Street to W 83rd Street


    Centerpoint Energy has completed gas main installation in the area with service work remaining.
  • E 82nd Street area
    E 82nd Street from Portland Avenue to Park Avenue,
    Oakland Avenue from E 81st Street to E 83rd Street


    Centerpoint Energy has completed gas main installation in the area with service work remaining.
  • W 96th Street area
    W 96th Street from Lyndale Avenue to west terminus,
    Aldrich Avenue from W 96th Street to south terminus


    The contractor anticipates to begin pavement removal in this area late in the week of July 11.
  • E 90th Street
    E 90th Street from Portland Avenue to 12th Avenue

    Centerpoint Energy has started gas main installation in the area and will continue the week of July 11.
  • Park area
    Park Avenue from E 90th Street to E 96th Street,
    E 93rd Street from Oakland Avenue to Chicago Avenue,
    Oakland Avenue from E 92nd Street to E 93rd Street


    Centerpoint Energy has started gas main installation in the area and will continue the week of July 11.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites.

  • Briar area
    Briar Road from Vessey Road to Wildwood Circle,
    Briar Circle,
    Wildwood Circle from Wildwood Road to east terminus,
    Wildwood Road from 102nd Street to Wildwood Circle


    Concrete curb and gutter has been installed. The contractor will be grading the road in preparation for paving the first lift of bituminous. This is tentatively scheduled for either July 14 or 15, but may change based on weather or other construction issues.
  • Southbrook neighborhood
    Upton Road,
    Upton Circle,
    Southbrook Drive,
    W. 97th Street,
    Xerxes Road,
    W. 96th Street,
    W. 96th Street Circle,
    Washburn Avenue,
    Vincent Avenue)


    The contractor will be switching people to the temporary water system the week of July 11. Once everyone is on the temporary system removals will begin to facilitate the installation of the new watermain.
  • Auto Club Road area
    Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave,
    Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road,
    W. 113th Street from Minnesota Bluffs Drive to east terminus,
    W. 114th Street from Auto Club Road to Minnesota Bluffs Drive,
    W. 114th Street Circles


    Sod was installed in the area this past week.
  • West 102nd Street
    West 102nd Street from Normandale Boulevard to Abbott Avenue

    Underground utility work is winding down. The contractor will be prepping the areas for curb and gutter installation where it has been removed. The concrete curb and gutter is expected to be installed either late in the week of July 11 or more likely the week of July 18.
July 1, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The contractor will be replacing the caps on the walls and painting the railings in the next few weeks.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    Concrete curb and gutter has been installed on the remaining section of the road. The contractor will be fine grading the road starting July 5 in preparation for paving the first layer of pavement.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street Circle for W 98-1/2 Street to Northwest Terminus)
    Subgrade correction and storm sewer work has completed in this area. Concrete work has started in the area and will continue the week of July 4. Grading of Class 5 in preparation for paving is anticipated to begin late in the week of July 4.
  • Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus, W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to Penn Avenue)
    Tree removal continues in the area. The contractor plans to begin removing pavement early in the week of July 4 with storm sewer work to begin late in the week of July 4.
  • W 106th Street (from Humboldt Ave to I-35W)

    The contractor has been granted a noise exception from 7am - 9am in this area and plans on grading the boulevard on the north side of W 106th St in preparation for bituminous trail installation.

    Storm sewer work has completed on the north side of W 106th St. Grading work began this week and will continue the week of July 4. Concrete work is anticipated to begin late in the week of July 4.

  • 101st and Utah Traffic Circle
    The concrete traffic circle has been installed. Additional concrete sidewalk work will continue in the area the week of July 4 with restoration and plantings within the traffic circle to follow.
  • W 82nd Street (from I-35W to Aldrich Ave)
    Centerpoint Energy crews have finished work in the area. The contractor anticipates to begin construction in the area the week of July 11.
  • W 83rd Street Area (includes W 83rd Street from Lyndale Avenue to Grand Avenue, Garfield Avenue from W 82nd Street to South Terminus, Harriet Avenue from W 82nd Street to South Terminus, Grand Avenue from W 82nd Street to W 83rd Street)
    Centerpoint Energy has completed gas main installation in the area with service work remaining.
  • E 82nd Street Area (includes E 82nd Street from Portland Avenue to Park Avenue, Oakland Avenue from E 81st Street to E 83rd Street)
    Centerpoint Energy has started gas main installation in the area and will continue the week of July 4.
2011-102 PMP Street Maintenance Project

Punch list work remains on several sites.

  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)
    The new water services have been installed. The new watermain passed all the required tests and has been put in service. The water pressure to the neighborhood should be back to normal. The contractor will be prepping the area for installation of curb and gutter the week of July 5.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    The contractor will continue installing material for the temporary water service during the week of July 5 and probably part of the week of July 11.
  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    With the hot temperatures, sod installation has been pushed back.
  • West 102nd Street (from Normandale Blvd to Abbott Avenue)
    The contractor will begin storm sewer maintenance work the week of July 5. The contractor will begin with the items located in the middle of the road, so the two inside lanes will be shut down. Traffic will be allowed to drive on the outside lanes, one lane in each direction. Once this utility work in the middle of the road is complete traffic will be moved to the two inside lanes while work continues on the outside lanes.

June 2011

June 24, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The planters have been installed and all but two waste receptacles along with the inserts for the receptacles have been installed. The remaining inserts and waste receptacles are on order and will be installed upon delivery. Concrete punch list work has completed in this area.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    Utility installation has completed in the area. Due to the recent weather conditions, grading and concrete work has been moved to the week of June 27.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street Circle for W 98-1/2 Street to Northwest Terminus)
    The contractor has been granted a noise exception from 7am - 9am for Saturday, June 25 in this area and plans on continuing subgrade correction/grading/placing class 5 in the area. Subgrade correction/grading/class 5 will continue the week of June 27. Storm sewer work has completed in the area. Concrete replacement is anticipated to begin late in the week of June 27 (weather permitting).
  • Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus, W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to Penn Avenue)
    Tree removal has started in the area and will continue the week of June 27. Due to the recent weather conditions, the schedule for bituminous pavement removal has adjusted once again, and the contractor plans to start removing pavement late in the week of June 27.
  • W 106th Street (from Humboldt Ave to I-35W)

    The contractor has been granted a noise exception from Friday, June 24 at 10pm to 9am Saturday, June 25, and also from 9pm Saturday, June 25 through 7am Monday, June 27 for storm sewer and street reconstruction in the area.

    The contractor will be closing W 106th St at the on and off ramps from southbound I-35W Friday, June 24 at 7pm until Monday, June 27 at 5am. A detour will be provided for this closure. Storm sewer replacements and street reconstruction will take place during this closure on W 106th St in the area of the on and off ramps. The contractor will also be removing pavement on the north side (WB side) of W 106th St from Humboldt Ave to W Bloomington Fwy on the weekend of June 25, with two-way traffic running on the south side (EB side) of W 106th St beginning June 24. Storm sewer work will continue the week of June 27 with grading/Class 5 to follow later in the week of June 27 on the closed WB portion of W 106th from Humboldt Ave to W Bloomington Fwy.

  • 101st and Utah Traffic Circle
    Due to the recent weather conditions, the contractor has adjusted their schedule and now plans to begin removals the week of June 27.
  • W 82nd Street (from I-35W to Aldrich Ave)
    Centerpoint Energy crews have finished work in the area. The contractor anticipates to begin construction in the area the week of July 11.
  • W 83rd Street Area (includes W 83rd Street from Lyndale Avenue to Grand Avenue, Garfield Avenue from W 82nd Street to South Terminus, Harriet Avenue from W 82nd Street to South Terminus, Grand Avenue from W 82nd Street to W 83rd Street)
    Centerpoint Energy continues gas main installation in the area and is anticipating to complete the main installation the week of June 27. Service crews will follow shortly after.
  • E 82nd Street Area (includes E 82nd Street from Portland Avenue to Park Avenue, Oakland Avenue from E 81st Street to E 83rd Street)
    Centerpoint Energy anticipates to begin gas main installation the week of June 27 in this area.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)

    The contractor may finish installing services on June 24, if not, early in the week of June 27, but due to recent weather conditions progress was slightly slowed. After service installation is complete, the line will be tested the week of June 27, with possible full service back up by late in the week of June 27 or early the following week.

    The contractor will begin storm sewer work and grading in the area the week of June 27.

    Mailboxes for properties in this area where the watermain is being replaced remain relocated.

  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • 107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen Avenue)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Quebec Road Area (between 106th Street and Bush Lake Road)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)

    Centerpoint Energy crews plan to finish work in the area by early in the week of June 27. The contractor will begin laying out material for the temporary water service late in the week of June 27 for portions of Upton Road, Upton Circle and W. 97th Street.

    An informal "tailgate" neighborhood meeting was held by staff on Thursday, June 23 from 5-7pm in Upton Circle to give residents information about the upcoming water main project on W 97th St, Upton Circle and Upton Road in this area and to answer any questions they may have prior to construction.

  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    The contractor has been granted a noise exception from 7am - 9am for Saturday, June 25 in this area and plans to finish the paving of Minnesota Bluffs Drive and Auto Club Road, which will complete paving for the area. Pavement striping is anticipated to occur the week of June 27 with possible sod installation beginning late in the week.
  • West 102nd Street (from Normandale Blvd to Abbott Avenue)
    Centerpoint Energy crews plan to finish work in the area by early in the week of June 27. The contractor anticipates moving into the area the week of June 27 with saw cutting of concrete/bituminous for removals.
June 20, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The planters and waste receptacles are tentatively scheduled to be installed late in the week of June 20, weather permitting. Concrete punch list work has completed in this area.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    Due to the rain on Wed, June 15, the contractor was not able to complete the storm sewer and water main installation. Therefore, installation will continue the week of June 20 and is anticipated to be complete by Tuesday, June 21. The intersection of 81st Street and Russell Avenue will be re-opened on Friday, June 17 for the weekend and then be reduced back down to one lane on Monday, June 20 and the segment of Russell Avenue under construction to the south will be utilized once again. Weather permitting, the intersection of 81st Street and Russell Avenue will re-open on the evening of Tuesday, June 21. Letters have been sent to adjacent residents informing them of the access changes since this intersection is the only route to the neighborhood. The fire department has been informed of this closure.
    Removals, grading and concrete work will begin late in the week of June 20 after storm sewer and water main installation has completed.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street Circle for W 98-1/2 Street to Northwest Terminus)
    The Contractor has been granted a noise exception from 7am - 9am for Saturday, June 18 in this area and plans on beginning subgrade correction/grading/placing class 5 in the area. Subgrade correction/grading/class 5 as well as storm sewer replacements will continue next week in the area.
  • Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus, W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to Penn Avenue)
    The Contractor adjusted their schedule slightly and now anticipates moving into this area late in the week of June 20 with bituminous pavement and driveway removals.
  • W 106th Street (from Humboldt Ave to I-35W)
    The Contractor plans to close W 106th St at the on and off ramps from southbound I-35W on Friday, June 24 at 7pm until Monday, June 27 at 5am. A detour will be provided for this closure. Storm sewer replacements and street reconstruction will take place during this closure on W 106th St in the area of the on and off ramps. The Contractor will also be removing pavement on the north side of W 106th St from Humboldt Ave to W Bloomington Fwy on the weekend of June 24-26, with two-way traffic running on the south side of W 106th St.
  • 101st and Utah Traffic Circle
    The Contractor plans to begin removals late in the week of June 20.
  • W 82nd Street (from I-35W to Aldrich Ave)
    Centerpoint Energy will continue gas main crossing installation and service work in this area the week of June 20.
  • W 83rd Street Area (includes W 83rd Street from Lyndale Avenue to Grand Avenue, Garfield Avenue from W 82nd Street to South Terminus, Harriet Avenue from W 82nd Street to South Terminus, Grand Avenue from W 82nd Street to W 83rd Street)
    Centerpoint Energy anticipates to begin gas main installation the week of June 20.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)

    The larger portion of the watermain work has been completed, though the new system is not yet ready for service. The contractor will be installing services the week of June 20. After this is complete the line will be tested. Full service is anticipated to return to normal within two weeks. Crews were able to phase construction so that one of the high pressure lines could be placed back into service sooner than anticipated. With one of the high pressure services currently back on line, the water pressure to the area has increased, although it will still be reduced from normal until the project is complete.

    Late in the week of June 20, the contractor will begin replacing storm sewer sections that had to be removed for the new watermain. Following that operation the contractor will begin to restore the roadway.

    Mailboxes for properties in this area where the watermain is being replaced remain relocated.

  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • 107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen Avenue)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains.
  • Quebec Road Area (between 106th Street and Bush Lake Road)
    Sod has been installed in the neighborhood. Upon final inspection, punch list work remains..
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    Centerpoint Energy crews continue to work in the area. Two service crews will be working in the area and the gas service work is estimated to be complete by the end of the week of June 20. Weather pending, the contractor will begin installing temporary water service the week of June 27 for portions of Upton Road, Upton Circle and W. 97th Street.
  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    The contractor has completed all concrete work and street milling. Crews will be raising manholes and water valves the week of June 20. Weather permitting, the contractor will be paving in the area late in the week of June 20.
  • West 102nd Street (from Normandale Blvd to Abbott Avenue)
    Centerpoint Energy crews continue work in the area. The contractor will move into the area approximately June 27.
June 10, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The planters and waste receptacles are tentatively scheduled to be installed on Saturday, June 11, weather permitting. The contractor will be removing and replacing sections of cracked curb and sidewalk that are on the concrete punch list on Monday and Tuesday, June 13 and 14. There will be lane closures on Lyndale Avenue to facilitate this work.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    The contractor will be installing storm sewer and watermain during the week of June 13. On Tuesday, June 14 the intersection of 81st Street and Russell Avenue will be down to one lane and utilize the segment of Russell Avenue under construction to the south. Letters have been sent to adjacent residents informing them of the access changes since this intersection is the only route to the neighborhood. The fire department has been informed of this closure.
2011-101 PMP Street Improvement Project
  • Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street Circle for W 98-1/2 Street to Northwest Terminus)
    The Contractor has been granted a noise exception from 7am - 9am for Saturday, June 11 in this area and plans on continuing to install drain tile in the area. Drain tile installation will continue next week along with bituminous pavement removal.
  • Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus, W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to Penn Avenue)
    The Contractor anticipates moving into this area late in the week of June 13 with bituminous pavement and driveway removals.
  • W 82nd Street (from I-35W to Aldrich Ave)
    Centerpoint Energy anticipates moving into this area the week of June 13 for gas main crossing installation and service work.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Sod has been installed in the neighborhood.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Sod has been installed in the neighborhood.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    Sod has been installed in the neighborhood.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    Sod has been installed in the neighborhood.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    Sod has been installed in the neighborhood.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)

    The area under construction is located in a high pressure water main area. With the construction two of the high pressure connections that loop to serve this area were temporarily turned off while the water main is replaced. This has decreased the pressure serving the neighborhood under construction and the area to the south. The area affected is bounded by Normandale Blvd to the east/Nesbitt Avenue to the west and by Yosemite Road to the south/102nd Street to the north. Normally the pressure in the area varies between 60 to 80 psi and with the two high pressure valves closed the pressure in the water main is currently about half of that in the 30 to 40 psi range. The required minimum pressure for a fire hydrant to adequately fight a fire is 20 psi which is being provided to the neighborhood. However, staff has received numerous complaints related to the reduced pressure since it is half of what is usual for the neighborhood. The reduced pressure is especially noticeable for showers on the second floor. The contractor was finishing up the reinstallation of water main pipe at Briar Road and Wildwood Circle where one of the high pressure feeds is located on Friday, June 10. This line will be tested during the week of June 13 with the hopes to reopen the high pressure valve towards the end of the week. With one of the high pressure services back on line it is anticipated that the water pressure will increase to the area, although it will still be reduced from normal until the project is complete

    Watermain installation will continue during the week of June 13. The contractor will be installing from Wildwood Road and head south with the new main installation. The water main should be installed by the end of the week and the following week the contractor will be installing services. Mailboxes for properties in this area where the water main is being replaced have temporarily been relocated.

  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    Sod has been installed in the neighborhood.
  • 107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen Avenue)
    Sod has been installed in the neighborhood.
  • Quebec Road Area (between 106th Street and Bush Lake Road)
    Sod has been installed in the neighborhood.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    Centerpoint Energy crews continue to work in the area. Two service crews will be working in the area. The gas service work is estimated to be complete by the end of the week of June 20. The contractor will begin installing temporary water service the week of June 27 for portions of Upton Road, Upton Circle and W. 97th Street.
  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    The contractor will be reconstructing various storm and sanitary sewer manholes the week of June 13. The roads are scheduled to be milled on Thursday and Friday, June 16 and 17, weather permitting. Paving would follow the following week.
  • West 102nd Street (from Normandale Blvd to Abbott Avenue)
    Centerpoint Energy will be working on the gas main the week of June 13. The contractor will move into the area approximately June 27.
June 3, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The planters, waste receptacles and other street furniture will be installed over the next few weeks as they are is delivered from the manufacture.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    The asbestos and regulated waste debris removal is complete. The Contractor will begin installing watermain on Thursday, June 9 (tentative).
  • Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street to E 86th Street)
    The contractor continues to work on landscape punch list items.
2011-101 PMP Street Improvement Project

A pre-construction conference was held on Thursday, June 2.

  • Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street Circle for W 98-1/2 Street to Northwest Terminus)
    The Contractor anticipates starting work in this neighborhood late in the week of June 6 with drain tile installation.
  • Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus, W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to Penn Avenue)
    Centerpoint Energy has completed installing new gas main in this area. The Contractor anticipates moving into this neighborhood the week of June 13.
  • W 82nd Street (from I-35W to Aldrich Ave)
    Centerpoint Energy anticipates moving into this area the week of June 13 for gas main crossing installation and service work.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Sod installation will continue in a number of neighborhoods over the next few weeks.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Sod installation will continue in a number of neighborhoods over the next few weeks.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    Sod installation will continue in a number of neighborhoods over the next few weeks.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    Sod installation will continue in a number of neighborhoods over the next few weeks.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    Sod installation will continue in a number of neighborhoods over the next few weeks.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)
    The temporary water installation continues. The contractor expects to begin connecting residents to the temporary water system on Tuesday, June 7 and will continue throughout the week. Removals will begin in the area on Monday, June 6. Watermain construction will hopefully begin at the end of the week, once everyone is connected to the temporary system.
  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    The road has been milled and paved. Sod installation will follow in a few weeks.
  • 107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen Avenue)
    The road has been milled and paved. Sod installation will follow in a few weeks.
  • Quebec Road Area (between 106th Street and Bush Lake Road)
    The road has been milled and paved. Sod installation will follow in a few weeks.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    Centerpoint Energy crews continue to work in the area. They are complete with the new gas main installation. One service crew continues to work in the area and a second crew will be brought in on approximately June 13. The gas service work is estimated to be complete by the end of the week of June 20.
  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    Concrete curb and gutter removal and replacement continues in the area.
  • West 102nd Street (from Normandale Blvd to Abbott Avenue)
    Major road construction will not begin until school is out. City staff has been marking removals, but is not complete with the area yet.

May 2011

May 27, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The plants and mulch have been installed in the medians.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    The contractor will continue removing the asbestos and regulated waste debris away. It is anticipated that this work will be completed the week of May 30.
  • Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street to E 86th Street)
    The final layer of pavement has been place. A few landscape punchlist items remain to be completed.
  • 17th Avenue (from 82nd Street to the north)
    Work is complete in the area.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    With the rain, sod installation was delayed it has been rescheduled for the week of May 30.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    With the rain, sod installation was delayed it has been rescheduled for the week of May 30.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    With the rain, sod installation was delayed it has been rescheduled for the week of May 30.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    With the rain, sod installation was delayed it has been rescheduled for the week of May 30.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)
    The Contractor has pushed back the installation of the temporary watermain system to the week of May 30.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    The pavement was placed on May 27.
  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of the following two days.
  • 107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen Avenue)
    Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of the following two days.
  • Quebec Road Area (between 106th Street and Bush Lake Road)
    Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of the following two days.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    Centerpoint Energy crews continue to work in the area. The service work will take approximately one month and Centerpoint is complete with approximately half of the neighborhood. In addition to the new services, there will be a new main installed in part of the neighborhood along with some new fittings.
  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    The Contractor will be repairing existing manholes and storm sewer structures including some storm pipe installation. Curb and gutter removal and replacement is scheduled for the end of the week of May 30 and likely will continue to the following week.
  • West 102nd Street (from Normandale Blvd to Abbott Avenue)
    Major road construction will not begin until school is out
May 25, 2011
2011-102 PMP Street Maintenance Project
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    The frontage road will be closed to northbound traffic starting 8 pm Thursday, May 26. Southbound traffic will still be allowed but will be relocated to the northbound side of the road at different points to facilitate construction operations. A noise variance has been granted to allow the contractor to work the overnight from May 26 to May 27. The contractor will be milling and paving the road during this closure.

Bloomington Freeway detour

 

May 20, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The contractor will be planting the medians during the week of May 23.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    The required manifests for disposal were signed by the City Engineer this past week. The contractor will be on site on Tuesday, May 24, to begin hauling the asbestos and regulated waste debris away.
  • Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street to E 86th Street)
    The sod has been placed. The contractor will be in on May 23 and 24 to finish the plantings. Paving the final lift of pavement is scheduled Thursday, May 26, weather permitting.
  • 17th Avenue (from 82nd Street to the north)
    The sod has been placed. The contractor will be in to finish the plantings for the berm the week of May 23.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    The road was paved this past week. Sod installation is scheduled for the week of May 23.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    The road was paved this past week. Sod installation is scheduled for the week of May 23.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    The road was paved this past week. Sod installation is scheduled for the week of May 23.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    Sod installation is scheduled for the week of May 23.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)
    The Contractor has pushed back the installation of the temporary watermain system to the week of May 23.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    The contractor will be working on the loops as part of the signal system on Monday, May 23. The frontage road will be closed to northbound traffic starting 8 pm Thursday, May 26. Southbound traffic will still be allowed but will be relocated to the northbound side of the road at different points to facilitate construction operations. A noise variance has been granted to allow the contractor to work the overnight from May 26 to May 27. The contractor will be milling and paving the road during this closure.
  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of the following two days.
  • 107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen Avenue)
    Concrete curb and gutter along with pedestrian ramps will be placed on Monday, May 23, weather permitting. Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of the following two days.
  • Quebec Road Area (between 106th Street and Bush Lake Road)
    Concrete curb and gutter along with pedestrian ramps will be placed on Monday, May 23, weather permitting. Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of the following two days.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    Centerpoint Energy crews continue to work in the area. The service work will take approximately one month and Centerpoint is complete with approximately half of the neighborhood. In addition to the new services, there will be a new main installed in part of the neighborhood along with some new fittings.
  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    The Contractor anticipates moving into this neighborhood the week of May 30.
  • West 102nd Street (from Normandale Blvd to Abbott Avenue)
    The contractor will begin working on the loops at the various signal systems during the week of May 23. Major road construction will not begin until school is out.
May 13, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    Concrete work and median preparation along Lyndale Avenue, West Old Shakopee Road, Grand Avenue, and 97-1/2 Street has occurred. Work will continue on the medians during the week of May 16.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    The test pit completed on Wednesday, May 11 did not encounter any debris, but was limited in size due to utilities and lane restrictions. The environmental consultant is working on the required manifests to dispose of the other regulated waste material found on site.
  • Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street to E 86th Street)
    With the rain, the sod fields have been too wet and placement was delayed. The contractor anticipates beginning installation sometime after Wednesday, May 18 if the rain stops on Saturday, May 14 as forecasted. Due to the sod not being installed, the date for the final lift of pavement has been pushed back.
  • 17th Avenue (from 82nd Street to the north)
    With the rain, the sod fields have been too wet and placement was delayed. The contractor anticipates beginning installation sometime after Wednesday, May 18 if the rain stops on Saturday as forecasted.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Paving of the road was delayed due to rain and is scheduled for Monday, May 16, weather permitting. Sod installation is scheduled for the week of May 23.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Paving is scheduled for Monday, May 16, weather permitting. Sod installation is scheduled for the week of May 23.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    Qwest and Centerpoint plan on adjusting manholes and other items to final grade on Monday, May 16. Paving is scheduled for Tuesday, May 17, weather permitting. The contractor will be modifying the detection at the traffic signal during the week of May 16. Sod installation is scheduled for the week of May 23.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    Removals will begin the week of May 16. The contractor will have flaggers directing traffic during both the curb removal and placements. Motorists may encounter delays in the area due to construction.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)
    The Contractor has pushed back the installation of the temporary watermain system to the week of May 23.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    Removals will begin the week of May 16. The contractor will have flaggers directing traffic during both the curb removal and placements. Motorists may encounter delays in the area due to construction.
  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    The Contractor anticipates moving into this neighborhood the week of May 16.
  • 107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen Avenue)
    The Contractor anticipates moving into this neighborhood the week of May 16.
  • Quebec Road Area (between 106th Street and Bush Lake Road)
    The Contractor anticipates moving into this neighborhood on Thursday, May 19, weather permitting.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    Centerpoint Energy crews continue to work in the area. The service work will take approximately one month. In addition to the new services, there will be a new main installed in part of the neighborhood along with some new fittings.
  • Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club Road to Minnesota Bluffs Drive, W. 114th Street Circles)
    The Contractor anticipates moving into this neighborhood the week of May 23.
May 6, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    The contractor will be preparing the median beds for planting during the week of May 9. The median planting beds include not only Lyndale Avenue, but also West Old Shakopee Road, Grand Avenue, and 97-1/2 Street. Concrete maintenance edger strips near the curb and gutter of the medians will also be installed. There will be various lane closures on these roads to facilitate construction.
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
    The contractor will be out on Wednesday, May 11, weather permitting, along with the environmental consultant and the certified asbestos removal contractor to dig test holes at the intersection of Russell Avenue and 81st Street to determine the limits of the debris.
  • Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street to E 86th Street)
    Sod will be installed during the week of May 9. The final lift of pavement will be placed during the week of May 16.
  • 17th Avenue (from 82nd Street to the north)
    Sod will be installed during the week of May 9.
  • Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old Shakopee Road and Baliff Place)
    Rain water gardens will have additional soil and mulch installed during the week of May 9.
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Milling the road is scheduled for Tuesday, May 10, weather dependant, with paving planned for two days later.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Concrete replacement is scheduled for Monday, May 9, weather dependant. The contractor will also be patching and backfilling curb areas once the concrete work is complete. Milling the road is scheduled for Wednesday, May 11, weather dependant, with paving to follow during the week of May 16.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    Concrete replacement is scheduled for Monday, May 9, weather dependant. The contractor will also be patching and backfilling curb areas once the concrete work is complete. Milling the road is scheduled for Wednesday, May 11, weather dependant, with paving to follow during the week of May 16. Manholes, gates valve and other items will be adjusted to final grade after the milling occurs late next week.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    Milling the road is scheduled for Tuesday, May 10, weather dependant, with paving planned for two days later.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)
    The Contractor has pushed back the installation of the temporary watermain system to the week of May 16.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    The Contractor anticipates moving into this neighborhood the week of May 9.
  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    The Contractor anticipates moving into this neighborhood the week of May 9.
  • Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent Avenue)
    Centerpoint Energy plans on having a gas service crew begin installation of new services the week of May 9. The service work will take approximately one month. In addition to the new services, there will be a new main installed in part of the neighborhood along with some new fittings.

 

April 2011

April 29, 2011
2011-102 PMP Street Maintenance Project
  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Centerpoint Energy anticipates completing the gas main service work early the week of May 2. The rain during the past week delayed them a couple of days. The Contractor will start work on the project on May 2 with removals and underground utility repair.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Centerpoint Energy completed installing new gas main crossings at Pillsbury Avenue and Wentworth Avenue. The Contractor will start work on the project the week of May 2 with removals and underground utility repair.
  • Old Cedar Avenue (between 86th Street and 87th Street)
    The Contractor will start work on the project the week of May 2 with removals and underground utility repair.
  • 12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th Street)
    The Contractor will start work on the project the week of May 2 with removals and underground utility repair.
  • Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd Street to Wildwood Circle)
    The Contractor will begin to install the temporary watermain system during the week of May 2 in preparation for moving into the neighborhood the week of May 16.
  • Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes West Bloomington Freeway, W. 99th Street and Dupont Avenue)
    The Contractor anticipates moving into this neighborhood the week of May 9.
  • Vincent Avenue (between Old Shakopee Road and W. 106th Street)
    The Contractor anticipates moving into this neighborhood the week of May 9.
April 25, 2011
2011-102 PMP Street Maintenance Project

A preconstruction conference is schedule for the week of April 25.

  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Centerpoint Energy anticipates beginning gas service work the week of April 25. The Contractor anticipates starting work on the project on May 2, provided road restrictions have been rescinded.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Centerpoint Energy anticipates installing new gas main crossings at Pillsbury Avenue and Wentworth Avenue during the week of April 25.
April 15, 2011
2010-101 PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
  • Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street from Russell Avenue to Penn Avenue)
  • Clinton Ave Area (from E 79 1/2 Street to E 82nd Street and from E 84th Street to E 86th Street)

With the improving weather, people have inquired when the project will restart. Currently there are spring load restrictions in place that restrict the weight on any single axle on all non-exempt trucks and commercial vehicles to a maximum of five tons on non-concrete state highways, county highways, town roads and city streets. These went in place on March 14. Historically they have gone in place about a month earlier in February. Mn/DOT uses actual and forecasted daily air temperatures to determine the placement and removal of spring load restrictions. Typically the end of spring load restrictions is about eight weeks after they went into place. We are hoping road restrictions come off around May 1, but with the possibly freezing temperatures in the forecast that may not be realistic, especially since it would only be about six weeks from when they went into effect. Restart of construction will be based on road restrictions being removed and we may have to wait until May 15 or longer based on MnDOT's calculation.

April 15, 2011
2011-102 PMP Street Maintenance Project

The Contractor anticipates starting work on the project on May 2, but this is dependent on removal of road restrictions as described above.

  • Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd Avenue between 95th Street and Maplewood Drive)
    Centerpoint Energy anticipates beginning gas service work the week of April 23.
  • 83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
    Centerpoint Energy anticipates installing new gas main crossings at Pillsbury Avenue and Wentworth Avenue during the week of April 23.

December 2010

December 10, 2010
PMP Street Improvement Project
  • Lyndale area (from 99th Street to 94th Street includes 96th Street west of Lyndale)
    Activation of the signal at 95th Street has been tentatively scheduled for Tuesday, December 14, weather permitting.

 

For more information, contact:

Shelly Pederson, City Engineer
1700 W. 98th Street
PH: 952-563-4870, FAX: 952-563-4868
E-mail: engineering@ci.bloomington.mn.us