Project updates
Pavement Management Program (PMP)
The updates listed below refer to the Pavement Management Program (PMP) .
To find updates regarding other projects, go to major road construction
projects.
November 2011
November 29, 2011
2012-101 PMP Street Improvement Project
The public hearing was held on November 21. All streets were ordered by Council, except
for Harriet Avenue, Garfield Avenue, Stanley Circle and American Boulevard West. The hearing
for these four segments has been continued and will be heard at the Monday, December 5 Council
meeting.
November 10, 2011
2012-101 PMP Street Improvement Project
Notices regarding the 2012 PMP Street Improvement Project have been mailed to all affected
properties. Public information meetings are scheduled for November 14 at 2:00 p.m. and 5:30
p.m. in the Public Works Training Room. The public hearing is scheduled for November 21.
2011-101 PMP Street Improvement Project
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Final striping is complete. Punch list work remains.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Sod/Seed installation is complete. Punch list work remains.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Sod/seed installation is complete. Punch list work remains.
November 4, 2011
2011-101 PMP Street Improvement Project
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Sod/Seed installation is complete. The final layer of bituminous has been paved and E
90th St has been opened to traffic. Final striping of E 90th St is anticipated to
complete by the end of the day Friday, November 4. Punch list work remains.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Sod/Seed installation is anticipated to complete by the end of the day Friday,
November 4. Punch list work remains.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Sod/seed installation is anticipated to complete by the end of the day Friday,
November 4. Punch list work remains.
October 2011
October 28, 2011
2011-101 PMP Street Improvement Project
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
The first two layers of bituminous have been paved. Manholes and gate valves have been
raised. Sod/Seed installation has started and will continue the week of October 31. The
final layer of bituminous is scheduled to be paved the week of October 31. E 90th
Street from Portland Ave to 12th Ave is currently closed. The duration of this closure
will be approximately 6-8 weeks. A detour is provided for this closure.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Sod/Seed installation has started and will continue the week of October 31. The final
layer of bituminous has been paved.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
The final layer of bituminous has been paved. Sod/seed installation will start the
week of October 31.
October 21, 2011
2011-101 PMP Street Improvement Project
-
101st and Utah Traffic Circle
Plantings are complete. Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
The contractor has been granted a noise exception from 7am - 9am on Saturday, October
22 in this area. Concrete work is complete. The first two layers of bituminous have
been placed. Boulevard restoration has started and will continue the week of October
24. The contractor plans to raise manholes and gate valves the week of October 24.
Sod/Seed installation is scheduled for late in the week of October 24 and will continue
into the week of October 31. The final layer of bituminous is anticipated to be placed
the week of October 31. E 90th Street from Portland Ave to 12th Ave is currently
closed. The duration of this closure will be approximately 6-8 weeks. A detour is
provided for this closure.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
The contractor has been granted a noise exception from 7am - 9am on Saturday, October
22 in this area. Sod/seed installation has started and will continue the week of
October 24. Manholes and gate valves have been raised. The final layer of bituminous is
anticipated to be placed late in the week of October 24 or the week of October 31.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Manholes and gate valves have been raised. The final layer of bituminous is
anticipated to complete by the end of the day on Friday, October21. Sod/seed
installation is scheduled for the week of October 24.
October 13, 2011
2011-101 PMP Street Improvement Project
-
Queen Avenue area Queen Avenue from W 91st Street to south
terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
City Staff continues to work with rain garden residents on scheduling plantings.
Planting of the rain gardens is anticipated to occur in late October. Installation of
mulch within the rain gardens will occur upon completion of planting.
-
101st and Utah Traffic Circle
Now that the weather pattern has changed, the contractor anticipates planting late
this week or during the week of October 17.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Punch list work remains. City Staff continues to work with rain garden residents on
scheduling plantings. Planting of the rain gardens is anticipated to occur in late
October. Installation of mulch within the rain gardens will occur upon completion of
planting.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Concrete work continues in the area and is anticipated to complete early in the week
of October 17. Final grading in preparation for paving of the first layer of bituminous
will complete the week of October 17. The contractor anticipates paving the first layer
of bituminous the week of October 17 with boulevard restoration to follow. E 90th
Street from Portland Ave to 12th Ave is currently closed. The duration of this closure
will be approximately 6-8 weeks. A detour is provided for this closure.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Boulevard restoration continues in the area and will continue into the week of October
17. Sod/seed installation is anticipated to occur the week of October 17. The
contractor also plans to raise manholes and gate valves the week of October 17. The
final layer of bituminous will be placed upon completion of sod/seed installation and
is anticipated to occur the week of October 24.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Boulevard restoration will continue the week of October 17. Sod/seed installation is
anticipated to occur the week of October 17. The contractor also plans to raise
manholes and gate valves the week of October 17. The final layer of bituminous will be
placed upon completion of sod/seed installation and is anticipated to occur the week of
October 24.
October 7, 2011
2011-101 PMP Street Improvement Project
Many area only have punch list work remaining, which include:
-
Hyland Greens Drive area
-
W 106th Street
-
W 82nd Street
-
W 96th Street area
-
Queen Avenue area Queen Avenue from W 91st Street to south
terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Punch list work remains. City Staff will be working with rain garden residents on
scheduling plantings. Planting of the rain gardens is anticipated to occur in early-mid
October. Installation of mulch within the rain gardens will occur upon completion of
planting.
-
101st and Utah Traffic Circle
Due to the current unseasonably warm/dry pattern, the Contractor desires to wait until
the weather breaks to finish the plantings in this area. This work is now anticipated
to occur late in the week of October 10 or early the following.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Paving of the final layer of bituminous is complete. Punch list work remains. City
Staff will be working with rain garden residents on scheduling plantings. Planting of
the rain gardens is anticipated to occur in early-mid October. Installation of mulch
within the rain gardens will occur upon completion of planting.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Paving of the final layer of bituminous is complete. Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Sanitary and storm sewer replacements are complete. Concrete work continues in the
area and will continue the week of October 10. Grading in preparation for paving of the
first layer of bituminous continues and will continue the week of October 10. The
contractor anticipates paving the first layer of bituminous the week of October 17. E
90th Street from Portland Ave to 12th Ave is currently closed. The duration of this
closure will be approximately 6-8 weeks. A detour is provided for this closure.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
The contractor has been granted a noise exception from 7am - 9am on Saturday, October
10 in this area. Boulevard restoration continues in the area and will continue into the
week of October 10.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Boulevard restoration has started and will continue the week of October 10.
September 2011
September 30, 2011
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Punch list work remains.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Punch list work remains. City Staff will be working with rain garden residents on
scheduling plantings. Planting of the rain gardens is anticipated to occur in early-mid
October. Installation of mulch within the rain gardens will occur upon completion of
planting.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
Punch list work remains.
-
101st and Utah Traffic Circle
Plantings have been slightly delayed and are anticipated to occur the week of October
3.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
Punch list work remains.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Sod installation is complete. Manholes and gate valves have been raised in the area.
Paving of the final layer of bituminous is anticipated to occur the week of October 3.
City Staff will be working with rain garden residents on scheduling plantings. Planting
of the rain gardens is anticipated to occur in early-mid October. Installation of mulch
within the rain gardens will occur upon completion of planting.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Sod installation is complete. The Contractor has started raising manholes and gate
valves in preparation for the final layer of bituminous. Paving of the final layer of
bituminous is anticipated to occur the week of October 3.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
The contractor has been granted noise exception from 7am - 9am on Saturday, October 1
in this area. Sanitary and storm sewer replacements are anticipated to complete by the
end of the day Friday, September 30. Concrete work has started in the area and will
continue the week of October 3. Grading and placement of Class 5 is scheduled for the
week of October 3. E 90th Street from Portland Ave to 12th Ave is currently closed. The
duration of this closure will be approximately 6-8 weeks. A detour is provided for this
closure.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
The contractor has been granted a noise exception from 7am - 9am on Saturday, October
1 in this area. Paving of the first layer of bituminous and driveways in the area is
complete. Boulevard restoration has started and will continue the week of October 3.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Paving of the first layer of bituminous and driveways in the area is complete.
Boulevard restoration has started and will continue the week of October 3.
September 23, 2011
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Punch list work remains.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
The final layer of bituminous has been placed. Punch list work remains. City Staff
will be working with rain garden residents on scheduling plantings. Planting of the
rain gardens is anticipated to occur in early October. Installation of mulch within the
rain gardens will occur upon completion of planting.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
Striping in the area is complete. Punch list work remains.
-
101st and Utah Traffic Circle
Plantings are scheduled for the week of September 26.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
The final layer of bituminous has been placed and final striping is complete. Punch
list work remains.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Sod installation has started in the area and is anticipated to complete Friday,
September 23. The Contractor plans to raise manholes and gate valves the week of
September 26 in preparation for the final layer of bituminous. City Staff will be
working with rain garden residents on scheduling plantings. Planting of the rain
gardens is anticipated to occur in early October. Installation of mulch within the rain
gardens will occur upon completion of planting.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Sod installation has started in the area and will continue the week of September 26.
The Contractor plans to raise manholes and gate valves the week of September 26 in
preparation for the final layer of bituminous.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Pavement removal is complete. Sanitary and storm sewer replacements have started in
the area and will continue the week of September 26. E 90th Street from Portland Ave to
12th Ave is currently closed. The duration of this closure will be approximately 6-8
weeks. A detour is provided for this closure.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Concrete work is complete. Grading in preparation for the first layer of bituminous is
nearly complete. Paving of the first layer of bituminous is scheduled for early in the
week of September 26 in the area with paving of bituminous driveways to follow.
Boulevard restoration is scheduled to begin the week of September 26.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Concrete work is complete. Grading in preparation for the first layer of bituminous
will complete early in the week of September 26. Paving of the first layer of
bituminous is scheduled for the week of September 26 with paving of bituminous
driveways and boulevard restoration to follow.
2011-102 PMP Street Maintenance Project
The contractor will continue working on various punch list items.
September 16, 2011
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Punch list work remains.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
The final layer of bituminous has been placed. Punch list work remains. City Staff
will be working with rain garden residents on scheduling plantings. Planting of the
rain gardens is anticipated to occur in early October. Installation of mulch within the
rain gardens will occur upon completion of planting.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The final layer of bituminous has been placed and final striping is nearly complete in
the area and will complete early in the week of September 19. Punch list work remains.
-
101st and Utah Traffic Circle
Plantings are scheduled to be complete by the end of September.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
The contractor has been granted a noise exception for Saturday, September 17 from 6am
- 9am in this area. Electrical work for the signal system at 82nd St/E Bloomington Fwy
is complete. W 82nd St will be closed from I-35W to Aldrich Ave on Saturday, September
17 from 6am - 6pm to pave the final layer of bituminous. This will include the closure
of the on and off ramps for northbound I-35W at W 82nd St. A detour will be provided
for this closure. Final striping is scheduled for early in the week of September 19.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Sod installation in the area has been slightly delayed and is scheduled to begin the
week of September 19. City Staff will be working with rain garden residents on
scheduling plantings. Planting of the rain gardens is anticipated to occur in early
October. Installation of mulch within the rain gardens will occur upon completion of
planting.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Bituminous driveways have been placed. Boulevard restoration will continue the week of
September 19.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
E 90th Street from Portland Ave to 12th Ave will be closed beginning Monday, September
19. The duration of this closure will be approximately 6-8 weeks. A detour will be
provided for this closure. The contractor plans to begin pavement removal on Monday,
September 19. Storm and Sanitary sewer work is scheduled to begin the week of September
19.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Concrete work has started in the area and will complete early in the week of September
19. Grading in preparation for the first layer of bituminous is scheduled for the week
of September 19.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Pavement removal is complete. Storm sewer work is complete. Initial grading/placement
of class 5 will be complete by the end of the day Friday, September 16. Concrete work
is scheduled to begin early in the week of September 19 with grading for the first
layer of bituminous to follow.
2011-102 PMP Street Maintenance Project
The contractor will begin working on various punch list items.
September 9, 2011
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Punch list work remains.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Planting of the rain gardens is anticipated to occur in mid-late September. Sod
installation is complete. Placement of the final layer of bituminous will be complete
by the end of the day Friday, September 9.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The contractor has been granted a noise exception for Saturday, September 10 from 6am
- 9am in this area. The signal system at W 106th St/Humboldt Ave has been activated. W
106th St from Humboldt Ave to I-35W will be closed on Saturday, September 10 from 6am -
6pm to pave the final layer of bituminous. This will include the closure of the on and
off ramps for southbound I-35W. A detour will be provided for this closure. Final
striping for the area is scheduled for Tuesday, September 13 (weather permitting).
-
101st and Utah Traffic Circle
Planting soil within the traffic circle has been placed with plantings scheduled for
early fall.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
Sod installation is complete. Electrical work for the signal system at 82nd St/E
Bloomington Fwy has started and will complete early in the week of September 12. W 82nd
St will be closed from I-35W to Lyndale Ave on Saturday, September 17 from 6am - 6pm to
pave the final layer of bituminous. This will include the closure of the on and off
ramps for northbound I-35W at W 82nd St. A detour will be provided for this closure.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Boulevard restoration and grading of the rain gardens in the area is complete. Sod
installation is scheduled for the week of September 12.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
The contractor has been granted a noise exception for Saturday, September 10 from 7am
- 9am in this area. Concrete work is complete. The first layer of bituminous has been
placed. Bituminous driveways are scheduled to be paved starting Monday, September 12
with boulevard restoration to follow.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
The contractor anticipates beginning pavement removal in this area the week of
September 19. E 90th Street from Portland Ave to 12th Ave will be closed beginning
Monday, September 19. The duration of this closure will be approximately 6-8 weeks. A
detour will be provided for this closure.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
The contractor has been granted a noise exception for Saturday, September 10 from 7am
- 9am in this area. Storm sewer work is complete. Initial grading/placement of class 5
in the area is complete. Concrete work is scheduled for the week of September 12.
-
Halsey Lane
Halsey Lane from Lyndale Avenue to East Terminus
Pavement removals are scheduled to begin Monday, September 12. Initial
grading/placement of Class 5 and storm sewer work is scheduled for the week of
September 12.
2011-102 PMP Street Maintenance Project
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
Paving is complete. Punchlist work remains. Centerpoint needs to repair irrigation
lines and resod in areas that were disturbed with their gas main replacement project.
This has caused some confusion in the neighborhood as to why some areas have been
restored and others have yet to be.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
Placement of sod has begun and will continue the week of September 12.
-
Old Cedar Avenue
Old Cedar Avenue from American Blvd to E. 80th Street
Paving is complete. Punchlist work remains.
-
E. 84th Street
E. 84th Street from Stevens Avenue to 2nd Avenue
Paving is complete. Punchlist work remains.
September 6, 2011
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Punch list work remains.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Final grading of the planting soil in the rain gardens is nearly complete. Planting of
the rain gardens is anticipated to occur in mid-late September when the weather is more
accommodating for planting. Sod placement is anticipated to complete by the end of the
day Friday, September 2 (weather permitting). The contractor has started raising
manholes and gate valves in preparation for the final layer of bituminous and will
continue the week of September 5. Placement of the final layer of bituminous is
anticipated to occur either the week of September 5 or September 12.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
Sod installation is complete. Final wiring for the signal at W 106th St/Humboldt Ave
will be complete by the end of the day Friday, September 2. Activation of the signal
system is anticipated to occur Tuesday, September 6. The Bloomington Police Department
will be on hand the morning of Tuesday, September 6 to aid in traffic control prior to
activating the signal system due to the start of school. All lane closures will be
removed by the end of the day Friday, September 2 in advance of school starting on
September 6. The contractor plans to close W 106th St from Humboldt Ave to I-35W on
Saturday, September 10 from 6am - 6pm to pave the final layer of bituminous. This will
include the closure of the on and off ramps for southbound I-35W. A detour will be
provided for this closure.
-
101st and Utah Traffic Circle
Planting soil within the traffic circle has been placed with plantings scheduled for
early fall when the weather is more accommodating.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
The contractor has completed raising manholes and gate valves in the area. Boulevard
restoration and sod installation is anticipated to complete by the end of the day
Friday, September 2 (weather permitting). Electrical work for the signal system at 82nd
St/E Bloomington Fwy is anticipated to occur the weeks of September 5 and 12. The
contractor anticipates closing W 82nd St from I-35W to Aldrich Ave on Saturday,
September 17 to pave the final layer of bituminous. A detour will be provided for this
closure.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
The first layer of bituminous has been placed. Concrete work and bituminous driveway
installation is complete. Boulevard restoration and grading of the rain gardens in the
area has started and will continue the week of September 5.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Concrete work has started and will complete the week of September 5. Grading of class
5 in preparation for the first layer of bituminous will occur the week of September 5.
The first layer of bituminous is scheduled to be placed late in the week of September
5.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
The contractor anticipates starting this area in mid-September.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Pavement removal in the area is complete. Storm sewer work has started in the area and
will continue the week of September 5. Initial grading/placement of class 5 has started
in the area and will continue the week of September 5.
2011-102 PMP Street Maintenance Project
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
The paving is anticipated to be complete by end of day, September 2. It may be
necessary to finish a few paving items on Tuesday, September 6 depending on the weather
on Friday.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
Placement of sod is scheduled for the week of September 5.
-
Old Cedar Avenue
Old Cedar Avenue from American Blvd to E. 80th Street
Paving is scheduled for Tuesday, September 6, weather dependant. Striping the road is
tentatively scheduled for Friday, September 9.
-
E. 84th Street
E. 84th Street from Stevens Avenue to 2nd Avenue
Paving is scheduled for Tuesday, September 6, weather dependant.
August 2011
August 26, 2011
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Punch list work remains.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Final grading of the planting soil in the rain gardens is anticipated to occur the
week of August 29. Planting of the rain gardens is anticipated to occur in mid-late
September when the weather is more accommodating for planting.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The contractor has been granted a noise exception for Saturday, August 27 from 7am -
9am in this area and plans to raise manholes and gate valves in the area. Bituminous
path installation on the north side of W 106th St is complete. Concrete work on W 106th
Street is complete. Boulevard restoration and topsoil placement has started and will
continue the week of August 29. Sod installation is scheduled for the week of August
29. Final wiring for the signal at W 106th St/Humboldt Ave is dependent on when all
remaining material is delivered, which is anticipated to occur the week of August 29.
The contractor anticipates paving the final layer of bituminous on Saturday, September
10.
-
101st and Utah Traffic Circle
Planting soil within the traffic circle has been placed with plantings scheduled for
early fall when the weather is more accommodating.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
The contractor has been granted a noise exception from Friday, August 26 at 10pm to
9am Saturday, August 27, and also from 9pm Saturday, August 27 through 7am Monday,
August 29 for street reconstruction and paving of the first two layers of bituminous in
the area of the on and off ramps from northbound I-35W on W 82nd St. The contractor
will be closing W 82nd St at the on and off ramps from northbound I-35W Friday, August
26 at 7pm until Monday, August 29 at 5am. A detour will be provided for this closure.
The first two layers of bituminous have been placed on the south side of W 82nd St.
Upon completion of street reconstruction and paving at the on and off ramps, the
contractor plans to switch traffic to the center lanes both EB and WB and close the
outer lanes to allow for boulevard restoration the week of August 29.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
The contractor has been granted a noise exception for Saturday, August 27 from 7am-9am
in this area and plans to pave the first layer of bituminous on Grand Ave and W 83rd
St. The first layer of bituminous for the remainder of the area is scheduled to occur
early in the week of August 29. Concrete work in the area is anticipated to complete
the week of August 29. Boulevard restoration and grading of the rain gardens in the
area is anticipated to begin the week of August 29.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Storm sewer work is complete. Initial grading/placement of Class 5 has started in the
area and will continue the week of August 29. Concrete work is scheduled for the week
of August 29.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Punch list work remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy has completed service installation in the area. The contractor
anticipates starting this area in mid-September.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
The contractor has started pavement removal in the area and will continue the week of
August 29. Storm sewer work is scheduled to begin the week of August 29.
2011-102 PMP Street Maintenance Project
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
Sod installation for the areas disturbed with the City project will be wrapping up the
week of August 29. Please note that areas disturbed by Centerpoint Energy for their new
gas main and services that need sod likely will not be complete on this same schedule
and will occur later. Milling is scheduled for Tuesday & Wednesday, August 30 &
31 with paving to start on Wednesday, August 31 and continue through Friday, September
2, weather dependant.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
Placement of sod and repair of irrigation system is scheduled for the week of August
29.
-
Old Cedar Avenue
Old Cedar Avenue from American Blvd to E. 80th Street
Curb removals and replacement will begin on Monday, August 29. Milling is scheduled
for Wednesday, August 31.
-
E. 84th Street
E. 84th Street from Stevens Avenue to 2nd Avenue
Curb removals and replacement will begin on Monday, August 29. Milling is scheduled
for Wednesday, August 31.
August 22, 2011
2011-101 PMP Street Improvement Project
W 82nd Street closed for reconstruction
W 82nd St will be closed at the northbound on and off ramps to I-35W starting at 7
p.m. Friday, August 26. This closure will be re-opened by 5 a.m. on Monday, August
29. The contractor will be reconstructing W 82nd St in this area during the closure. Those
that wish to exit to W 82nd St from Northbound I-35W will be detoured to I-494 East and
then south on Lyndale Ave to get back to W 82nd St for the duration of this closure.
August 19, 2011
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
The final layer of bituminous has been placed. Final clean up and punch list work
remains.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Rain garden excavation is complete and planting soil has started to be placed and will
continue the week of August 22.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The contractor has been granted a noise exception for Saturday, August 20 from 7am -
9am in this area and plans to begin grading/restoring the boulevards in the area. Power
poles have been relocated on W 106th Street with wire transfer nearly complete.
Existing poles in need of removal for bituminous path installation have been removed
and bituminous path installation is anticipated to complete by the end of the day
August 19 (weather permitting). Final concrete work on W 106th Street will occur the
week of August 22. Boulevard restoration and sod installation is scheduled to occur the
weeks of August 22 and 29.
-
101st and Utah Traffic Circle
Planting soil within the traffic circle has been placed with plantings scheduled for
early fall when the weather is more accommodating.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
Initial grading/placement of class 5 has completed on the south side of W 82nd Street.
Concrete work has started on the south side and will continue the week of August 22.
Final grading prior to placement of the first layer of bituminous is scheduled to occur
the week of August 22. The Contractor plans to close W 82nd Street at the on and off
ramps of northbound I-35W on Friday, August 26 at 7pm until Monday, August 29 at 5am. A
detour will be provided for this closure. Street reconstruction and paving of the first
two layers of bituminous will take place during this closure. The Contractor also plans
to pave the first two layer of bituminous on the south side of W 82nd Street during
this closure.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Initial grading prior to curb and gutter placement is complete. Concrete work has
started and will continue the week of August 22. Final grading prior to paving of the
first layer of bituminous is scheduled to occur the week of August 22.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Center point has completed service installation in the area. The contractor has been
granted a noise exception for Saturday, August 20 from 7am - 9am in this area. Pavement
removal in the area is complete. Storm sewer work and grading/placement of Class 5 is
scheduled to occur the week of August 22.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
The final layer of bituminous has been placed. Final clean up and punch list work
remains.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy has completed service installation in the area.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Centerpoint Energy has completed service installation in the area. The contractor
anticipates to begin pavement removal on Park Ave from 96th - 92nd the week of August
22 with storm sewer work to follow.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites. There are several locations where work was also
performed by Centerpoint Energy within the City construction areas. While the City's
contractor has installed sod for areas disturbed with the City project, Centerpoint has not
installed sod in the areas they disturbed which has created some confusion for some
residents as to why some spots have sod and others do not. Centerpoint does not anticipate
beginning sod installation until after August 15 nor do they include a clause in their
contract for watering like the City does for the first 30 days and each individual resident
is responsible for the initial watering.
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
Installation of topsoil will begin August 22 with sod installation to follow. The
contractor will also be working on adjusting manholes and gate valves in the street in
preparation for milling the road. Milling is scheduled for Tuesday, August 30 with
paving to follow later in the week.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
W. 102nd Street was paved this past week. Stripes will be placed on Monday, August 22.
Placement of sod and repair of irrigation system remains.
-
Old Cedar Avenue
Old Cedar Avenue from American Blvd to E. 80th Street
The contractor anticipates moving into this area sometime the week of August 29.
August 15, 2011
2011-102 PMP Street Maintenance Project
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
W. 102nd Street between Abbott Avenue and Normandale Avenue will be closed on
Wednesday & Thursday, August 17 & 18 starting at 7 am for
two days to pave the road. (Rain day-Friday, August 19). Driveway access for
residents who live on W. 102nd Street and access to Toledo Circle will be allowed
during the closure. The no parking restriction on the side streets will not be
enforced while the paving operation is under way in case some residents choose to
park there instead. Bloomington Jefferson High School has "Jump Start"
which is freshman orientation scheduled for both of these days. The paving schedule
has been tweaked to accommodate these program sessions as much as possible and
access to Bloomington Jefferson High School from Johnson Road via Heritage Hill
Drive will not be affected.
August 12, 2011
2010-101 PMP Street Improvement Project
-
Russell Avenue area
Russel Avenue between 81st Street and 82nd Street,
82nd Street from Russell Avenue to Penn Avenue
The final layer of pavement has been placed. Only punchlist work remains.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Sod installation is complete. Manholes and gate valves have been adjusted. The
contractor anticipates placing the final layer of bituminous early in the week of
August 15.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
The contractor has been granted a noise exception for Saturday, August 13 from 7am -
9am in this area and plans to begin excavation for rain water gardens. Concrete work
and sod installation is complete, except for in the areas of the proposed rain water
gardens. Rain garden excavation will continue the week of August 15.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The contractor has been granted a noise exception for Saturday, August 13 from 7am -
9am in this area and plans to grade the bituminous path. Power poles have been
relocated on W 106th Street with wire transfer to the new poles remaining and this work
is anticipated to complete the week of August 15. Wiring for the signal work at W.
106th/Humboldt continues and will continue the week of August 15. Concrete work on the
south side of W 106th Street is complete. Bituminous path installation and remaining
concrete work on the north side of W 106th Street is anticipated to occur upon
completion of power pole relocation and wire transfer to the new poles.
-
101st and Utah Traffic Circle
Sod installation is complete. Planting soil within the traffic circle is anticipated
to be placed by the week of August 15, with plantings scheduled for early fall when the
weather is more accommodating.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
The contractor has been granted a noise exception for Saturday, August 13 from 7am -
9am in this area and plans to begin grading the south half of W 82nd Street which will
continue the week of August 15. Concrete work and paving of the first two layers of
bituminous on the north side of W 82nd Street is complete. Traffic has been switched to
the north half of W 82nd Street. Pavement removal on the south half of W 82nd Street is
anticipated to complete by the end of the day August 12.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Storm sewer work is complete. Grading has started in the area and will continue the
week of August 15. Concrete work is anticipated to begin late in the week of August 15.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Centerpoint Energy anticipates completing service installation by the end of the day
August 12. The contractor anticipates beginning pavement removals the week of August 15
with storm sewer work to follow late in the week.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Sod installation is complete. Manholes and gate valves have been adjusted. The
contractor anticipates paving the final layer of the bituminous the week of August 15.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy has started installing services in the area and will continue the
week of August 15.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Centerpoint Energy has started installing services in the area and will continue the
week of August 15.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites. There are several locations where work was also
performed by Centerpoint Energy within the City construction areas. While the City's
contractor has installed sod for areas disturbed with the City project, Centerpoint has not
installed sod in the areas they disturbed which has created some confusion for some
residents as to why some spots have sod and others do not. Centerpoint does not anticipate
beginning sod installation until after August 15 nor do they include a clause in their
contract for watering like the City does for the first 30 days and each individual resident
is responsible for the initial watering.
-
Briar area
Briar Road from Vessey Road to Wildwood Circle,
Briar Circle,
Wildwood Circle from Wildwood Road to east terminus,
Wildwood Road from 102nd Street to Wildwood Circle
Punchlist work remains on this site along with clean up work from Comcast under their
utility permit.
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
The contractor has a noise variance to allow work to begin at 7 am on Saturday, August
13. Concrete curb and gutter replacement is underway and is likely to finish on Monday,
August 15. Paving the base layer of pavement in areas where the watermain replacement
occurred is scheduled for Tuesday, August 16, weather permitting. Site work will
continue the remainder of the week.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
The contractor has a noise variance to allow work to begin at 7 am on Saturday,
July 13 and will be adjusting manholes, valve box covers and other items in advance
of paving.
On Wednesday & Thursday, August 17 & 18 the City of Bloomington plans on
CLOSING W. 102nd Street between Abbott Avenue and Normandale Avenue for two days to
pave the road. (Rain day-Friday, August 19). Driveway access for residents who live
on W. 102nd Street and access to Toledo Circle will be allowed during the closure.
The no parking restriction on the side streets will not be enforced while the
paving operation is under way in case some residents choose to park there instead.
The tentative schedule (weather dependant) has the contractor paving 102nd Street
mainline and side street connections between France Avenue and Abbott Avenue and
paving the side street connections to 102nd Street that were impacted by
construction between France Avenue and Normandale Blvd on Wednesday, August 17. The
schedule for Thursday, August 18 includes paving the mainline road between France
Avenue and Normandale Blvd, starting at France on the south side.
Bloomington Jefferson High School has "Jump Start" which is freshman
orientation scheduled for both of these days. The paving schedule has been tweaked
to accommodate these program sessions as much as possible and access to the High
School from Johnson Road via Heritage Hill Drive will not be affected.
August 5, 2011
2010-101 PMP Street Improvement Project
-
Russell Avenue area
Russel Avenue between 81st Street and 82nd Street,
82nd Street from Russell Avenue to Penn Avenue
The contractor has a noise variance to allow work to begin at 7 am on Saturday, July
23. The contractor will be installing seed and sod in the remaining boulevard areas and
anticipates paving the road the week of August 1.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
The contractor has been granted a noise exception from 7am b in the area and plans
to continue sod installation in the area. Due to the wet conditions earlier this
week, sod installation was delayed but is winding down. The contractor plans to
adjust manholes and gate valves the week of August 8.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Placement of the first layer of bituminous is complete. Paving of bituminous driveways
is complete. Concrete work is anticipated to complete on Saturday, August 6. Boulevard
grading and placement of topsoil continues and sod installation will occur the week of
August 8.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
Due to the recent storms in the area, Xcel Energy has been slightly delayed, but
continues power pole relocation in the area and anticipates completing late in the week
of August 8. Wiring for the signal work at W. 106th/Humboldt continues and will
continue the week of August 8. Concrete curb and gutter work on the east end of W 106th
at I-35W is anticipated to complete the week of August 8. Bituminous path installation
and remaining concrete work is anticipated to occur upon completion of power pole
relocation.
-
101st and Utah Traffic Circle
Sod installation will be complete by early in the week of August 8. Planting soil
within the traffic circle is anticipated to be placed by the week of August 15, with
plantings scheduled for early fall when the weather is more accommodating.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
The contractor has been granted a noise exception from 7am b concrete work on the
north half of W 82nd St. Grading and placement of Class 5 is anticipated to complete
early in the week of August 8. Paving of the first two layers of bituminous on the
north half of W 82nd St is scheduled for mid week of August 8 (weather permitting). If
weather allows, when paving is complete, the contractor anticipates switching traffic
to the north half of W 82nd St and beginning pavement removal on the south half late in
the week of August 8.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Centerpoint Energy has completed gas main and service installation in the area. The
contractor has started pavement removals in the area and will continue the week of
August 8. Grading work has also started in the area and will continue the week of
August 8. Storm sewer work will occur the week of August 8.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Centerpoint Energy has completed gas main installation in the area and are now
installing services, which will continue the week of August 8. The contractor
anticipates beginning pavement removals the week of August 15.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Sod installation will occur the week of August 8.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy finished gas main installation in the area with services remaining.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Centerpoint Energy has finished gas main installation in the area with services
remaining.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites. There are several locations where work was also
performed by Centerpoint Energy within the City construction areas. While the City's
contractor has installed sod for areas disturbed with the City project, Centerpoint has not
installed sod in the areas they disturbed which has created some confusion for some
residents as to why some spots have sod and others do not. Centerpoint does not anticipate
beginning sod installation until after August 15 nor do they include a clause in their
contract for watering like the City does for the first 30 days and each individual resident
is responsible for the initial watering.
-
Briar area
Briar Road from Vessey Road to Wildwood Circle,
Briar Circle,
Wildwood Circle from Wildwood Road to east terminus,
Wildwood Road from 102nd Street to Wildwood Circle
The road has been milled and paving is scheduled for Monday, August 8, weather
dependant.
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
The contractor has a noise variance to allow work to begin at 7 am on Saturday, August
6. The water system did pass the follow up bacteria testing and residents have been
switched to the new system and the temporary water system has been removed. Grading of
the area continues. Concrete curb and gutter replacement is scheduled to begin on
Tuesday, August 9 and continue the rest of the week.
July 2011
July 29, 2011
2010-101 PMP Street Improvement Project
-
Russell Avenue area
Russel Avenue between 81st Street and 82nd Street,
82nd Street from Russell Avenue to Penn Avenue
The contractor has a noise variance to allow work to begin at 7 am on Saturday, July
23. The contractor will be installing seed and sod in the remaining boulevard areas and
anticipates paving the road the week of August 1.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
Paving of bituminous driveways is complete in the area. Boulevard restoration and
placement of topsoil is winding down. Sod installation in the area is scheduled for
the week of August 1 (weather permitting). Temporary mailboxes that were installed
due to construction will be removed the week of August 1.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
The contractor has been granted a noise exception from 7am - 9am on Saturday, July 30
in the area. Placement of the first layer of bituminous has started and the contractor
hopes to be complete by end of the day on July 29. Prepping and paving of bituminous
driveways has started and will continue the week of August 1. Boulevard grading and
placement of topsoil will also occur the week of August 1.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The contractor has been granted a noise exception from 7am - 9am on Saturday, July 30
in the area. Xcel Energy has started power pole relocation in the area and anticipates
completing late in the week of August 1. Wiring for the signal work at W.
106th/Humboldt continues and will continue the week of August 1. Storm sewer work has
completed in the area. Concrete curb and gutter work has completed on the south half of
W 106th Street. Paving of the first two layers of bituminous on the south half of W
106th Street is anticipated to complete by the end of the day on July 29. The
contractor anticipates opening up the south half of W 106th Street to traffic upon
completion of paving Saturday, July 30 or early in the week of August 1, with lane
closures in the outer lanes both east and westbound to allow for bituminous path and
concrete walk installation.
-
101st and Utah Traffic Circle
Sod installation is scheduled to occur the week of August 1 (weather permitting).
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
Traffic control has been set up and traffic is now traveling on the south half of W
82nd Street from I-35W to Aldrich Ave. Pavement removal is complete on the north half
of W 82nd Street. Grading work has started and will continue the week of August 1.
Concrete work is anticipated to begin the week of August 1.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Centerpoint Energy has completed gas main installation in the area with service work
anticipated to complete the week of August 1. The contractor anticipates starting
bituminous pavement removal the week of August 1 with storm sewer work to begin late in
the week upon completion of gas service installation.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Centerpoint Energy has completed gas main installation in the area with a service crew
scheduled to begin the week of August 1.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
The first layer of bituminous has been placed in the area. Boulevard grading and
placement of topsoil has started and will continue the week of August 1.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy finished gas main installation in the area with services remaining.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Centerpoint Energy has finished gas main installation in the area with services
remaining.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites. There are several locations where work was also
performed by Centerpoint Energy within the City construction areas. While the City's
contractor has installed sod for areas disturbed with the City project, Centerpoint has not
installed sod in the areas they disturbed which has created some confusion for some
residents as to why some spots have sod and others do not. Centerpoint does not anticipate
beginning sod installation until after August 15 nor do they include a clause in their
contract for watering like the City does for the first 30 days and each individual resident
is responsible for the initial watering.
-
Briar area
Briar Road from Vessey Road to Wildwood Circle,
Briar Circle,
Wildwood Circle from Wildwood Road to east terminus,
Wildwood Road from 102nd Street to Wildwood Circle
Milling of the road is anticipated August 3, with paving to occur on either August 5
or August 8, weather dependant.
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
The contractor has a noise variance to allow work to begin at 7 am on Saturday, July
30. Water service installation is complete and the system did not pass the initial
bacteria testing. It will need to be reflushed and tested again. Once the system passes
the test, the contractor will begin switching residents back from the temporary water
system to the permanent system and will begin removing the temporary water system. The
contractor will be grading the areas disturbed for the watermain installation the week
of August 1 and hopes to have rock on the road by the end of the week. Concrete curb
and gutter replacement is scheduled for the week of August 8.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
The contractor has a noise variance to allow work to begin at 7 am on Saturday,
July 30. Installation of concrete curb and gutter, sidewalks and pedestrian ramps
are winding down and anticipated to be completed by end of day on Monday, August 1.
The contractor will be patching the road and beginning to install topsoil at the
disturbed areas the week of August 1. Sign bases will be installed on August 3 and
4, weather permitting.
Hennepin County and Progressive Rail will be installing a new railroad crossing at
France Avenue north of Old Shakopee Road. This work will require that France Avenue
be closed from Thursday, August 4 through Tuesday, August 9. Given the proximity of
the road closure to 102nd Street and the need for approximately 17,000 vehicles to
use alternative routes, the milling that was scheduled for the week of August 1
along 102nd Street has been postponed for the safety of the crews and convenience
of the motoring public.
The milling of the road has been pushed back to August 10 and 11 with paving
scheduled for the following week.
July 22, 2011
2010-101 PMP Street Improvement Project
-
Russell Avenue area
Russel Avenue between 81st Street and 82nd Street,
82nd Street from Russell Avenue to Penn Avenue
The contractor has a noise variance to allow work to begin at 7 am on Saturday, July
23. The contractor will be working on adjusting the manholes and gate valve covers on
the road for paving which is likely to occur the week of August 1. The contractor will
be installing topsoil on July 25 and 26, weather permitting in advance of the sod
installation.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
The contractor has been granted a noise exception from 7am - 9am on Saturday, July
23 in this area and plans to grade boulevards in preparation for topsoil/sod which
will continue into the week of July 25. The first layer of bituminous has been
placed in this area. Due to the extreme heat conditions concrete sidewalk work did
not complete this week and is anticipated to complete early in the week of July 25.
Paving of bituminous driveways continues in the area and will complete the week of
July 25.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Initial grading work and placement of Class 5 has completed in the area. Concrete work
has started in the area and will continue the week of July 25. Grading in preparation
for bituminous placement will occur the week of July 25.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The contractor has been granted a noise exception from 7am - 9am on Saturday, July 23
in this area and plans to grade the bituminous path area along with boulevards. Due to
the extreme heat conditions and numerous power outages throughout the state, Xcel
energy was not in this week to begin power pole relocation on the north side of W 106th
Street. Upon completion of the power pole relocation, the bituminous path will be
placed and the retaining wall will be finished on the north half of W 106th Street.
Wiring for the signal work at W 106th/Humboldt continues and will continue the week of
July 25. Storm sewer work on the south half of W 106th St is anticipated to complete by
the end of the day on July 22. Grading work and placement of Class 5 continues and will
complete early in the week of July 25. Concrete work on the south half of W 106th
Street is anticipated to occur early in the week of July 25. Grading in preparation for
bituminous placement is scheduled for the middle of the week of July 25 with paving of
the first two layers of bituminous scheduled for late in the week (weather permitting).
-
101st and Utah Traffic Circle
Bituminous patching in front of the replaced curb and topsoil placement around
concrete sidewalk in the area has completed. Sod installation in the area and plantings
within the traffic circle remain and due to the recent weather conditions are
anticipated to be done when the weather allows.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
Traffic control has been set up and traffic is now traveling on the south half of W
82nd Street from I-35W to Aldrich Ave. Pavement removal on the north half of W 82nd
Street is anticipated to complete by the end of the day on July 22. Minor storm sewer
work and grading is scheduled for the week of July 25.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Centerpoint Energy has completed gas main installation in the area and is now working
on services. Due to the extreme heat conditions service installation was delayed, but
has started and will continue the week of July 25. The contractor anticipates starting
bituminous pavement removal late in the week of July 25 or early in the week of August
1.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Centerpoint Energy has completed gas main installation in the area with service work
remaining.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Initial grading work and placement of Class 5 has completed in the area. Concrete work
has started and will complete early in the week of July 25. Grading in preparation for
bituminous is scheduled for the week of July 25 along with paving of the first layer of
bituminous.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy has started gas main installation in the area and will continue the
week of July 25.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Centerpoint Energy has started gas main installation in the area and will continue the
week of July 25.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites. There are several locations where work was also
performed by Centerpoint Energy within the City construction areas. While the City's
contractor has installed sod for areas disturbed with the City project, Centerpoint has not
installed sod in the areas they disturbed which has created some confusion for some
residents as to why some spots have sod and others do not. Centerpoint does not anticipate
beginning sod installation until after August 15 nor do they include a clause in their
contract for watering like the City does for the first 30 days and each individual resident
is responsible for the initial watering.
-
Briar area
Briar Road from Vessey Road to Wildwood Circle,
Briar Circle,
Wildwood Circle from Wildwood Road to east terminus,
Wildwood Road from 102nd Street to Wildwood Circle
Sod was installed in the neighborhood. The contractor will be adjusting manholes and
gate valve covers the week of July 25. Milling of the road is anticipated sometime
between August 3-5 with paving to follow soon after.
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
Water service installation has begun and will continue into the week of July 25. The
water service installation is anticipated to be complete next week, and the City will
flush and test the system prior to putting it into service. Storm sewer installation
will begin after the water services are complete, likely around July 28 or 29. The
contractor will be grading the areas disturbed for the watermain installation the week
of August 1.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
Concrete curb and gutter, sidewalk and pedestrian ramps work will continue through the
week of July 25. Milling of the road is tentatively scheduled for the end of the week
of August 2 with paving to follow the end of the week of August 8.
July 15, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area
Lyndale Avenue from 99th Street to 94th Street,
96th Street west of Lyndale
The waste receptacles and liners were installed this past week.
-
Russell Avenue area
Russel Avenue between 81st Street and 82nd Street,
82nd Street from Russell Avenue to Penn Avenue
The concrete walk has been installed. The area is being prepped for installation of
sod and seed, but given the extremely hot forecast, this work may not occur next week.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
The contractor anticipates finishing the first layer of bituminous in the area by
the end of the day Friday, July 15 (weather permitting). Concrete sidewalk work
remains on Hyland Greens Drive and will be finished the week of July 18. Paving of
bituminous driveways has started in the area and will continue the week of July 18.
Topsoil restoration is anticipated to begin the week of July 18.
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Storm sewer work has completed in the area. Grading work and placement of Class 5 will
complete early in the week of July 18. Concrete work is anticipated to begin early in
the week of July 18.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
Paving of the first two of three layers of bituminous has completed on the north half
of W 106th Street. Xcel energy anticipates to be in the area the week of July 18 to
begin power pole relocation on the north side of W 106th Street. Upon completion of the
power pole relocation, the bituminous path will be placed and the retaining wall will
be finished on the north half of W 106th Street. Placing of conduits for electrical
work at the intersection of W 106th/Humboldt has completed and wiring/handhole
placement will continue the week of July 18. The contractor plans to switch traffic to
the north half of W 106th Street on Monday, July 18 and remove pavement on the south
half on Tuesday, July 19. Storm sewer work will follow after pavement removal the week
of July 18 along with grading late in the week of July 18. Concrete work on the south
half of W 106th Street is anticipated to begin the week of July 25.
-
101st and Utah Traffic Circle
The concrete traffic circle has been installed and the additional concrete work for
the pedestrian ramps in the intersection is complete. Bituminous patching in front of
the replaced curb will occur the week of July 18.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
Bituminous pavement removal on the north half of this area is anticipated to occur
late in the week of July 18. Traffic will be traveling on the south half of W 82nd
Street from I-35W to Aldrich Ave for the duration of this phase. Minor storm sewer work
and grading will occur the week of July 25.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Centerpoint Energy has completed gas main installation in the area and is now working
on services. Service work will continue the week of July 18 and is anticipated to
complete the week of July 25. The contractor anticipates starting bituminous pavement
removal late in the week of July 25.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Centerpoint Energy has completed gas main installation in the area with service work
remaining.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
Bituminous pavement removal has completed in the area. Grading will begin the week of
July 18, with concrete work anticipated to begin the week of July 25.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy has started gas main installation in the area and will continue the
week of July 18.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Centerpoint Energy has started gas main installation in the area and will continue the
week of July 18.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites.
-
Briar area
Briar Road from Vessey Road to Wildwood Circle,
Briar Circle,
Wildwood Circle from Wildwood Road to east terminus,
Wildwood Road from 102nd Street to Wildwood Circle
The first lift of pavement has been installed. The area is being prepped for
installation of sod, but given the extremely hot forecast, this work may not occur next
week. The contractor will be adjusting the various manhole and valve covers in
preparation for milling of the road.
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
Watermain installation will continue into the week of July 18. Water service
installation is likely to begin towards the end of the week after the main is
installed.
-
Auto Club Road area
Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave,
Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road,
W. 113th Street from Minnesota Bluffs Drive to east terminus,
W. 114th Street from Auto Club Road to Minnesota Bluffs Drive,
W. 114th Street Circles
Punch list work remains to be completed in the area.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
Additional curb and gutter removals that were not associated with the storm sewer
utility work will begin on Monday, July 18. The concrete crew is expected to begin
installing the new curb and gutter on Wednesday, July 20, weather permitting. The
Bloomington Utility crew will be working on replacement of a water valve at the
intersection of W. 102nd Street and France Avenue on Monday, July 18. Milling of the
road is tentatively scheduled for the end of the week of August 2 with paving to follow
the end of the week of August 8.
July 8, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area
Lyndale Avenue from 99th Street to 94th Street,
96th Street west of Lyndale
The remaining waste receptacles and liners will arrive and be installed the week of
July 11.
-
Russell Avenue area
Russel Avenue between 81st Street and 82nd Street,
82nd Street from Russell Avenue to Penn Avenue
The first layer of pavement has been installed. The Contractor will be grading the
area for the new sidewalk, starting on Saturday, July 9. New concrete walk will be
installed on approximately July 14 and 15, weather dependant.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive area
Hyland Greens Drive from Nesbitt Avenue to Briar Road,
Yosemite Road from Hyland Greens Drive to W 99th Street,
Yosemite Circle from Yosemite Road to west terminus,
W 99th Street from Nesbitt Avenue to Hyland Greens Drive,
W 98-1/2 Street from W 99th Street to Hyland Greens Drive,
W 98-1/2 Street Circle from W 98-1/2 Street to northwest terminus
The contractor has been granted a noise exception from 7am b in this area and
plans to grade Class 5 in preparation for paving. Concrete work continues in the
area and will complete the week of July 11. Grading of Class 5 in preparation for
paving has started and will continue into the week of July 11. Paving of the first
layer of bituminous is anticipated for the week of the July 18th (weather
permitting).
-
Queen Avenue area
Queen Avenue from W 91st Street to south terminus,
W 91st Street from Russell Avenue to Penn Avenue,
W 92nd Street from Russell Avenue to Penn Avenue
Bituminous pavement removals have started in the area along with reclamation of the
bituminous stabilized base. Storm sewer work has also started in the area and will
complete early in the week of July 11. Grading work has started and will continue into
the week of July 11.
-
W 106th Street
W 106th Streetfrom Humboldt Ave to I-35W
The contractor has been granted a noise exception from 7am b this area and plans on
removing pavement and grading the north half of the intersections of W 106th/Humboldt
and W 106th/W Bloomington Fwy. Initial grading on W 106th St between Humboldt and W
Bloomington Fwy is anticipated to complete by early in the week of July 11. Retaining
wall work has started on the north side of W 106th St and is anticipated to complete
early in the week of July 11. Placing of conduits for electrical work at the
intersection of W 106th/Humboldt is scheduled for Monday, July 11. Concrete work has
started in the area and will complete on the north half of W 106th St the week of July
11 (weather permitting). Grading in preparation for paving is anticipated to begin late
in the week of July 11.
-
101st and Utah Traffic Circle
The concrete traffic circle has been installed and the additional concrete work for
the pedestrian ramps in the intersection is complete. Restoration and plantings within
the traffic circle remain.
-
W 82nd Street
W 82nd Street from I-35W to Aldrich Avenue
Centerpoint Energy crews have finished work in the area. Work in this area involves
work within MnDOT ROW at the on and off ramps to northbound I-35W. Due to the current
state government shutdown, no work can occur within MnDOT ROW, therefore this area will
not begin until the shutdown has ended.
-
W 83rd Street area
W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to south terminus,
Harriet Avenue from W 82nd Street to south terminus,
Grand Avenue from W 82nd Street to W 83rd Street
Centerpoint Energy has completed gas main installation in the area with service work
remaining.
-
E 82nd Street area
E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street
Centerpoint Energy has completed gas main installation in the area with service work
remaining.
-
W 96th Street area
W 96th Street from Lyndale Avenue to west terminus,
Aldrich Avenue from W 96th Street to south terminus
The contractor anticipates to begin pavement removal in this area late in the week of
July 11.
-
E 90th Street
E 90th Street from Portland Avenue to 12th Avenue
Centerpoint Energy has started gas main installation in the area and will continue the
week of July 11.
-
Park area
Park Avenue from E 90th Street to E 96th Street,
E 93rd Street from Oakland Avenue to Chicago Avenue,
Oakland Avenue from E 92nd Street to E 93rd Street
Centerpoint Energy has started gas main installation in the area and will continue the
week of July 11.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites.
-
Briar area
Briar Road from Vessey Road to Wildwood Circle,
Briar Circle,
Wildwood Circle from Wildwood Road to east terminus,
Wildwood Road from 102nd Street to Wildwood Circle
Concrete curb and gutter has been installed. The contractor will be grading the road
in preparation for paving the first lift of bituminous. This is tentatively scheduled
for either July 14 or 15, but may change based on weather or other construction issues.
-
Southbrook neighborhood
Upton Road,
Upton Circle,
Southbrook Drive,
W. 97th Street,
Xerxes Road,
W. 96th Street,
W. 96th Street Circle,
Washburn Avenue,
Vincent Avenue)
The contractor will be switching people to the temporary water system the week of July
11. Once everyone is on the temporary system removals will begin to facilitate the
installation of the new watermain.
-
Auto Club Road area
Auto Club Road from Minnesota Bluffs Drive to Louisiana Ave,
Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road,
W. 113th Street from Minnesota Bluffs Drive to east terminus,
W. 114th Street from Auto Club Road to Minnesota Bluffs Drive,
W. 114th Street Circles
Sod was installed in the area this past week.
-
West 102nd Street
West 102nd Street from Normandale Boulevard to Abbott Avenue
Underground utility work is winding down. The contractor will be prepping the areas
for curb and gutter installation where it has been removed. The concrete curb and
gutter is expected to be installed either late in the week of July 11 or more likely
the week of July 18.
July 1, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The contractor will be replacing the caps on the walls and painting the railings in
the next few weeks.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
Concrete curb and gutter has been installed on the remaining section of the road. The
contractor will be fine grading the road starting July 5 in preparation for paving the
first layer of pavement.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to
Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle
from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens
Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street
Circle for W 98-1/2 Street to Northwest Terminus)
Subgrade correction and storm sewer work has completed in this area. Concrete work has
started in the area and will continue the week of July 4. Grading of Class 5 in
preparation for paving is anticipated to begin late in the week of July 4.
-
Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus,
W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to
Penn Avenue)
Tree removal continues in the area. The contractor plans to begin removing pavement
early in the week of July 4 with storm sewer work to begin late in the week of July 4.
-
W 106th Street (from Humboldt Ave to I-35W)
The contractor has been granted a noise exception from 7am - 9am in this area and
plans on grading the boulevard on the north side of W 106th St in preparation for
bituminous trail installation.
Storm sewer work has completed on the north side of W 106th St. Grading work began
this week and will continue the week of July 4. Concrete work is anticipated to
begin late in the week of July 4.
-
101st and Utah Traffic Circle
The concrete traffic circle has been installed. Additional concrete sidewalk work will
continue in the area the week of July 4 with restoration and plantings within the
traffic circle to follow.
-
W 82nd Street (from I-35W to Aldrich Ave)
Centerpoint Energy crews have finished work in the area. The contractor anticipates to
begin construction in the area the week of July 11.
-
W 83rd Street Area (includes W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to South Terminus, Harriet Avenue from W 82nd Street
to South Terminus, Grand Avenue from W 82nd Street to W 83rd Street)
Centerpoint Energy has completed gas main installation in the area with service work
remaining.
-
E 82nd Street Area (includes E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street)
Centerpoint Energy has started gas main installation in the area and will continue the
week of July 4.
2011-102 PMP Street Maintenance Project
Punch list work remains on several sites.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The new water services have been installed. The new watermain passed all the required
tests and has been put in service. The water pressure to the neighborhood should be
back to normal. The contractor will be prepping the area for installation of curb and
gutter the week of July 5.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
The contractor will continue installing material for the temporary water service
during the week of July 5 and probably part of the week of July 11.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
With the hot temperatures, sod installation has been pushed back.
-
West 102nd Street (from Normandale Blvd to Abbott Avenue)
The contractor will begin storm sewer maintenance work the week of July 5. The
contractor will begin with the items located in the middle of the road, so the two
inside lanes will be shut down. Traffic will be allowed to drive on the outside lanes,
one lane in each direction. Once this utility work in the middle of the road is
complete traffic will be moved to the two inside lanes while work continues on the
outside lanes.
June 2011
June 24, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The planters have been installed and all but two waste receptacles along with the
inserts for the receptacles have been installed. The remaining inserts and waste
receptacles are on order and will be installed upon delivery. Concrete punch list work
has completed in this area.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
Utility installation has completed in the area. Due to the recent weather conditions,
grading and concrete work has been moved to the week of June 27.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to
Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle
from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens
Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street
Circle for W 98-1/2 Street to Northwest Terminus)
The contractor has been granted a noise exception from 7am - 9am for Saturday, June 25
in this area and plans on continuing subgrade correction/grading/placing class 5 in the
area. Subgrade correction/grading/class 5 will continue the week of June 27. Storm
sewer work has completed in the area. Concrete replacement is anticipated to begin late
in the week of June 27 (weather permitting).
-
Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus,
W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to
Penn Avenue)
Tree removal has started in the area and will continue the week of June 27. Due to the
recent weather conditions, the schedule for bituminous pavement removal has adjusted
once again, and the contractor plans to start removing pavement late in the week of
June 27.
-
W 106th Street (from Humboldt Ave to I-35W)
The contractor has been granted a noise exception from Friday, June 24 at 10pm to
9am Saturday, June 25, and also from 9pm Saturday, June 25 through 7am Monday, June
27 for storm sewer and street reconstruction in the area.
The contractor will be closing W 106th St at the on and off ramps from southbound
I-35W Friday, June 24 at 7pm until Monday, June 27 at 5am. A detour will be
provided for this closure. Storm sewer replacements and street reconstruction will
take place during this closure on W 106th St in the area of the on and off ramps.
The contractor will also be removing pavement on the north side (WB side) of W
106th St from Humboldt Ave to W Bloomington Fwy on the weekend of June 25, with
two-way traffic running on the south side (EB side) of W 106th St beginning June
24. Storm sewer work will continue the week of June 27 with grading/Class 5 to
follow later in the week of June 27 on the closed WB portion of W 106th from
Humboldt Ave to W Bloomington Fwy.
-
101st and Utah Traffic Circle
Due to the recent weather conditions, the contractor has adjusted their schedule and
now plans to begin removals the week of June 27.
-
W 82nd Street (from I-35W to Aldrich Ave)
Centerpoint Energy crews have finished work in the area. The contractor anticipates to
begin construction in the area the week of July 11.
-
W 83rd Street Area (includes W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to South Terminus, Harriet Avenue from W 82nd Street
to South Terminus, Grand Avenue from W 82nd Street to W 83rd Street)
Centerpoint Energy continues gas main installation in the area and is anticipating to
complete the main installation the week of June 27. Service crews will follow shortly
after.
-
E 82nd Street Area (includes E 82nd Street from Portland Avenue to Park Avenue,
Oakland Avenue from E 81st Street to E 83rd Street)
Centerpoint Energy anticipates to begin gas main installation the week of June 27 in
this area.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Old Cedar Avenue (between 86th Street and 87th Street)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The contractor may finish installing services on June 24, if not, early in the week
of June 27, but due to recent weather conditions progress was slightly slowed.
After service installation is complete, the line will be tested the week of June
27, with possible full service back up by late in the week of June 27 or early the
following week.
The contractor will begin storm sewer work and grading in the area the week of June
27.
Mailboxes for properties in this area where the watermain is being replaced remain
relocated.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen
Avenue)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Quebec Road Area (between 106th Street and Bush Lake Road)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy crews plan to finish work in the area by early in the week of
June 27. The contractor will begin laying out material for the temporary water
service late in the week of June 27 for portions of Upton Road, Upton Circle and W.
97th Street.
An informal "tailgate" neighborhood meeting was held by staff on
Thursday, June 23 from 5-7pm in Upton Circle to give residents information about
the upcoming water main project on W 97th St, Upton Circle and Upton Road in this
area and to answer any questions they may have prior to construction.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
The contractor has been granted a noise exception from 7am - 9am for Saturday, June 25
in this area and plans to finish the paving of Minnesota Bluffs Drive and Auto Club
Road, which will complete paving for the area. Pavement striping is anticipated to
occur the week of June 27 with possible sod installation beginning late in the week.
-
West 102nd Street (from Normandale Blvd to Abbott Avenue)
Centerpoint Energy crews plan to finish work in the area by early in the week of June
27. The contractor anticipates moving into the area the week of June 27 with saw
cutting of concrete/bituminous for removals.
June 20, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The planters and waste receptacles are tentatively scheduled to be installed late in
the week of June 20, weather permitting. Concrete punch list work has completed in this
area.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
Due to the rain on Wed, June 15, the contractor was not able to complete the storm
sewer and water main installation. Therefore, installation will continue the week of
June 20 and is anticipated to be complete by Tuesday, June 21. The intersection of 81st
Street and Russell Avenue will be re-opened on Friday, June 17 for the weekend and then
be reduced back down to one lane on Monday, June 20 and the segment of Russell Avenue
under construction to the south will be utilized once again. Weather permitting, the
intersection of 81st Street and Russell Avenue will re-open on the evening of Tuesday,
June 21. Letters have been sent to adjacent residents informing them of the access
changes since this intersection is the only route to the neighborhood. The fire
department has been informed of this closure.
Removals, grading and concrete work will begin late in the week of June 20 after storm
sewer and water main installation has completed.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to
Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle
from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens
Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street
Circle for W 98-1/2 Street to Northwest Terminus)
The Contractor has been granted a noise exception from 7am - 9am for Saturday, June 18
in this area and plans on beginning subgrade correction/grading/placing class 5 in the
area. Subgrade correction/grading/class 5 as well as storm sewer replacements will
continue next week in the area.
-
Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus,
W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to
Penn Avenue)
The Contractor adjusted their schedule slightly and now anticipates moving into this
area late in the week of June 20 with bituminous pavement and driveway removals.
-
W 106th Street (from Humboldt Ave to I-35W)
The Contractor plans to close W 106th St at the on and off ramps from southbound I-35W
on Friday, June 24 at 7pm until Monday, June 27 at 5am. A detour will be provided for
this closure. Storm sewer replacements and street reconstruction will take place during
this closure on W 106th St in the area of the on and off ramps. The Contractor will
also be removing pavement on the north side of W 106th St from Humboldt Ave to W
Bloomington Fwy on the weekend of June 24-26, with two-way traffic running on the south
side of W 106th St.
-
101st and Utah Traffic Circle
The Contractor plans to begin removals late in the week of June 20.
-
W 82nd Street (from I-35W to Aldrich Ave)
Centerpoint Energy will continue gas main crossing installation and service work in
this area the week of June 20.
-
W 83rd Street Area (includes W 83rd Street from Lyndale Avenue to Grand Avenue,
Garfield Avenue from W 82nd Street to South Terminus, Harriet Avenue from W 82nd Street
to South Terminus, Grand Avenue from W 82nd Street to W 83rd Street)
Centerpoint Energy anticipates to begin gas main installation the week of June 20.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Old Cedar Avenue (between 86th Street and 87th Street)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The larger portion of the watermain work has been completed, though the new system
is not yet ready for service. The contractor will be installing services the week
of June 20. After this is complete the line will be tested. Full service is
anticipated to return to normal within two weeks. Crews were able to phase
construction so that one of the high pressure lines could be placed back into
service sooner than anticipated. With one of the high pressure services currently
back on line, the water pressure to the area has increased, although it will still
be reduced from normal until the project is complete.
Late in the week of June 20, the contractor will begin replacing storm sewer
sections that had to be removed for the new watermain. Following that operation the
contractor will begin to restore the roadway.
Mailboxes for properties in this area where the watermain is being replaced remain
relocated.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen
Avenue)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains.
-
Quebec Road Area (between 106th Street and Bush Lake Road)
Sod has been installed in the neighborhood. Upon final inspection, punch list work
remains..
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy crews continue to work in the area. Two service crews will be
working in the area and the gas service work is estimated to be complete by the end of
the week of June 20. Weather pending, the contractor will begin installing temporary
water service the week of June 27 for portions of Upton Road, Upton Circle and W. 97th
Street.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
The contractor has completed all concrete work and street milling. Crews will be
raising manholes and water valves the week of June 20. Weather permitting, the
contractor will be paving in the area late in the week of June 20.
-
West 102nd Street (from Normandale Blvd to Abbott Avenue)
Centerpoint Energy crews continue work in the area. The contractor will move into the
area approximately June 27.
June 10, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The planters and waste receptacles are tentatively scheduled to be installed on
Saturday, June 11, weather permitting. The contractor will be removing and replacing
sections of cracked curb and sidewalk that are on the concrete punch list on Monday and
Tuesday, June 13 and 14. There will be lane closures on Lyndale Avenue to facilitate
this work.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The contractor will be installing storm sewer and watermain during the week of June
13. On Tuesday, June 14 the intersection of 81st Street and Russell Avenue will be down
to one lane and utilize the segment of Russell Avenue under construction to the south.
Letters have been sent to adjacent residents informing them of the access changes since
this intersection is the only route to the neighborhood. The fire department has been
informed of this closure.
2011-101 PMP Street Improvement Project
-
Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to
Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle
from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens
Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street
Circle for W 98-1/2 Street to Northwest Terminus)
The Contractor has been granted a noise exception from 7am - 9am for Saturday, June 11
in this area and plans on continuing to install drain tile in the area. Drain tile
installation will continue next week along with bituminous pavement removal.
-
Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus,
W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to
Penn Avenue)
The Contractor anticipates moving into this area late in the week of June 13 with
bituminous pavement and driveway removals.
-
W 82nd Street (from I-35W to Aldrich Ave)
Centerpoint Energy anticipates moving into this area the week of June 13 for gas main
crossing installation and service work.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Sod has been installed in the neighborhood.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Sod has been installed in the neighborhood.
-
Old Cedar Avenue (between 86th Street and 87th Street)
Sod has been installed in the neighborhood.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
Sod has been installed in the neighborhood.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
Sod has been installed in the neighborhood.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The area under construction is located in a high pressure water main area. With the
construction two of the high pressure connections that loop to serve this area were
temporarily turned off while the water main is replaced. This has decreased the
pressure serving the neighborhood under construction and the area to the south. The
area affected is bounded by Normandale Blvd to the east/Nesbitt Avenue to the west
and by Yosemite Road to the south/102nd Street to the north. Normally the pressure
in the area varies between 60 to 80 psi and with the two high pressure valves
closed the pressure in the water main is currently about half of that in the 30 to
40 psi range. The required minimum pressure for a fire hydrant to adequately fight
a fire is 20 psi which is being provided to the neighborhood. However, staff has
received numerous complaints related to the reduced pressure since it is half of
what is usual for the neighborhood. The reduced pressure is especially noticeable
for showers on the second floor. The contractor was finishing up the reinstallation
of water main pipe at Briar Road and Wildwood Circle where one of the high pressure
feeds is located on Friday, June 10. This line will be tested during the week of
June 13 with the hopes to reopen the high pressure valve towards the end of the
week. With one of the high pressure services back on line it is anticipated that
the water pressure will increase to the area, although it will still be reduced
from normal until the project is complete
Watermain installation will continue during the week of June 13. The contractor
will be installing from Wildwood Road and head south with the new main
installation. The water main should be installed by the end of the week and the
following week the contractor will be installing services. Mailboxes for properties
in this area where the water main is being replaced have temporarily been
relocated.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
Sod has been installed in the neighborhood.
-
107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen
Avenue)
Sod has been installed in the neighborhood.
-
Quebec Road Area (between 106th Street and Bush Lake Road)
Sod has been installed in the neighborhood.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy crews continue to work in the area. Two service crews will be
working in the area. The gas service work is estimated to be complete by the end of the
week of June 20. The contractor will begin installing temporary water service the week
of June 27 for portions of Upton Road, Upton Circle and W. 97th Street.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
The contractor will be reconstructing various storm and sanitary sewer manholes the
week of June 13. The roads are scheduled to be milled on Thursday and Friday, June 16
and 17, weather permitting. Paving would follow the following week.
-
West 102nd Street (from Normandale Blvd to Abbott Avenue)
Centerpoint Energy will be working on the gas main the week of June 13. The contractor
will move into the area approximately June 27.
June 3, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The planters, waste receptacles and other street furniture will be installed over the
next few weeks as they are is delivered from the manufacture.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The asbestos and regulated waste debris removal is complete. The Contractor will begin
installing watermain on Thursday, June 9 (tentative).
-
Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street
to E 86th Street)
The contractor continues to work on landscape punch list items.
2011-101 PMP Street Improvement Project
A pre-construction conference was held on Thursday, June 2.
-
Hyland Greens Drive Area (includes Hyland Greens Drive from Nesbitt Avenue to
Briar Road, Yosemite Road from Hyland Greens Drive to W 99th Street, Yosemite Circle
from Yosemite Road to West Terminus, W 99th Street from Nesbitt Avenue to Hyland Greens
Drive, W 98-1/2 Street from W 99th Street to Hyland Greens Drive, W 98-1/2 Street
Circle for W 98-1/2 Street to Northwest Terminus)
The Contractor anticipates starting work in this neighborhood late in the week of June
6 with drain tile installation.
-
Queen Avenue Area (includes Queen Avenue from W 91st Street to South Terminus,
W 91st Street from Russell Avenue to Penn Avenue, W 92nd Street from Russell Avenue to
Penn Avenue)
Centerpoint Energy has completed installing new gas main in this area. The Contractor
anticipates moving into this neighborhood the week of June 13.
-
W 82nd Street (from I-35W to Aldrich Ave)
Centerpoint Energy anticipates moving into this area the week of June 13 for gas main
crossing installation and service work.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Sod installation will continue in a number of neighborhoods over the next few weeks.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Sod installation will continue in a number of neighborhoods over the next few weeks.
-
Old Cedar Avenue (between 86th Street and 87th Street)
Sod installation will continue in a number of neighborhoods over the next few weeks.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
Sod installation will continue in a number of neighborhoods over the next few weeks.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
Sod installation will continue in a number of neighborhoods over the next few weeks.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The temporary water installation continues. The contractor expects to begin connecting
residents to the temporary water system on Tuesday, June 7 and will continue throughout
the week. Removals will begin in the area on Monday, June 6. Watermain construction
will hopefully begin at the end of the week, once everyone is connected to the
temporary system.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
The road has been milled and paved. Sod installation will follow in a few weeks.
-
107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen
Avenue)
The road has been milled and paved. Sod installation will follow in a few weeks.
-
Quebec Road Area (between 106th Street and Bush Lake Road)
The road has been milled and paved. Sod installation will follow in a few weeks.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy crews continue to work in the area. They are complete with the new
gas main installation. One service crew continues to work in the area and a second crew
will be brought in on approximately June 13. The gas service work is estimated to be
complete by the end of the week of June 20.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
Concrete curb and gutter removal and replacement continues in the area.
-
West 102nd Street (from Normandale Blvd to Abbott Avenue)
Major road construction will not begin until school is out. City staff has been
marking removals, but is not complete with the area yet.
May 2011
May 27, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The plants and mulch have been installed in the medians.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The contractor will continue removing the asbestos and regulated waste debris away. It
is anticipated that this work will be completed the week of May 30.
-
Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street
to E 86th Street)
The final layer of pavement has been place. A few landscape punchlist items remain to
be completed.
-
17th Avenue (from 82nd Street to the north)
Work is complete in the area.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
With the rain, sod installation was delayed it has been rescheduled for the week of
May 30.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
With the rain, sod installation was delayed it has been rescheduled for the week of
May 30.
-
Old Cedar Avenue (between 86th Street and 87th Street)
With the rain, sod installation was delayed it has been rescheduled for the week of
May 30.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
With the rain, sod installation was delayed it has been rescheduled for the week of
May 30.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The Contractor has pushed back the installation of the temporary watermain system to
the week of May 30.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
The pavement was placed on May 27.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of
the following two days.
-
107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen
Avenue)
Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of
the following two days.
-
Quebec Road Area (between 106th Street and Bush Lake Road)
Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of
the following two days.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy crews continue to work in the area. The service work will take
approximately one month and Centerpoint is complete with approximately half of the
neighborhood. In addition to the new services, there will be a new main installed in
part of the neighborhood along with some new fittings.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
The Contractor will be repairing existing manholes and storm sewer structures
including some storm pipe installation. Curb and gutter removal and replacement is
scheduled for the end of the week of May 30 and likely will continue to the following
week.
-
West 102nd Street (from Normandale Blvd to Abbott Avenue)
Major road construction will not begin until school is out
May 25, 2011
2011-102 PMP Street Maintenance Project
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
The frontage road will be closed to northbound traffic starting 8 pm Thursday, May 26.
Southbound traffic will still be allowed but will be relocated to the northbound side
of the road at different points to facilitate construction operations. A noise variance
has been granted to allow the contractor to work the overnight from May 26 to May 27.
The contractor will be milling and paving the road during this closure.
May 20, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The contractor will be planting the medians during the week of May 23.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The required manifests for disposal were signed by the City Engineer this past week.
The contractor will be on site on Tuesday, May 24, to begin hauling the asbestos and
regulated waste debris away.
-
Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street
to E 86th Street)
The sod has been placed. The contractor will be in on May 23 and 24 to finish the
plantings. Paving the final lift of pavement is scheduled Thursday, May 26, weather
permitting.
-
17th Avenue (from 82nd Street to the north)
The sod has been placed. The contractor will be in to finish the plantings for the
berm the week of May 23.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
The road was paved this past week. Sod installation is scheduled for the week of May
23.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
The road was paved this past week. Sod installation is scheduled for the week of May
23.
-
Old Cedar Avenue (between 86th Street and 87th Street)
The road was paved this past week. Sod installation is scheduled for the week of May
23.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
Sod installation is scheduled for the week of May 23.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The Contractor has pushed back the installation of the temporary watermain system to
the week of May 23.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
The contractor will be working on the loops as part of the signal system on Monday,
May 23. The frontage road will be closed to northbound traffic starting 8 pm Thursday,
May 26. Southbound traffic will still be allowed but will be relocated to the
northbound side of the road at different points to facilitate construction operations.
A noise variance has been granted to allow the contractor to work the overnight from
May 26 to May 27. The contractor will be milling and paving the road during this
closure.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
Milling of this road is scheduled for Wednesday, June 1 with paving to occur on one of
the following two days.
-
107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen
Avenue)
Concrete curb and gutter along with pedestrian ramps will be placed on Monday, May 23,
weather permitting. Milling of this road is scheduled for Wednesday, June 1 with paving
to occur on one of the following two days.
-
Quebec Road Area (between 106th Street and Bush Lake Road)
Concrete curb and gutter along with pedestrian ramps will be placed on Monday, May 23,
weather permitting. Milling of this road is scheduled for Wednesday, June 1 with paving
to occur on one of the following two days.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy crews continue to work in the area. The service work will take
approximately one month and Centerpoint is complete with approximately half of the
neighborhood. In addition to the new services, there will be a new main installed in
part of the neighborhood along with some new fittings.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
The Contractor anticipates moving into this neighborhood the week of May 30.
-
West 102nd Street (from Normandale Blvd to Abbott Avenue)
The contractor will begin working on the loops at the various signal systems during
the week of May 23. Major road construction will not begin until school is out.
May 13, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Concrete work and median preparation along Lyndale Avenue, West Old Shakopee Road,
Grand Avenue, and 97-1/2 Street has occurred. Work will continue on the medians during
the week of May 16.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The test pit completed on Wednesday, May 11 did not encounter any debris, but was
limited in size due to utilities and lane restrictions. The environmental consultant is
working on the required manifests to dispose of the other regulated waste material
found on site.
-
Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street
to E 86th Street)
With the rain, the sod fields have been too wet and placement was delayed. The
contractor anticipates beginning installation sometime after Wednesday, May 18 if the
rain stops on Saturday, May 14 as forecasted. Due to the sod not being installed, the
date for the final lift of pavement has been pushed back.
-
17th Avenue (from 82nd Street to the north)
With the rain, the sod fields have been too wet and placement was delayed. The
contractor anticipates beginning installation sometime after Wednesday, May 18 if the
rain stops on Saturday as forecasted.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Paving of the road was delayed due to rain and is scheduled for Monday, May 16,
weather permitting. Sod installation is scheduled for the week of May 23.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Paving is scheduled for Monday, May 16, weather permitting. Sod installation is
scheduled for the week of May 23.
-
Old Cedar Avenue (between 86th Street and 87th Street)
Qwest and Centerpoint plan on adjusting manholes and other items to final grade on
Monday, May 16. Paving is scheduled for Tuesday, May 17, weather permitting. The
contractor will be modifying the detection at the traffic signal during the week of May
16. Sod installation is scheduled for the week of May 23.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
Removals will begin the week of May 16. The contractor will have flaggers directing
traffic during both the curb removal and placements. Motorists may encounter delays in
the area due to construction.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The Contractor has pushed back the installation of the temporary watermain system to
the week of May 23.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
Removals will begin the week of May 16. The contractor will have flaggers directing
traffic during both the curb removal and placements. Motorists may encounter delays in
the area due to construction.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
The Contractor anticipates moving into this neighborhood the week of May 16.
-
107th Avenue (includes W. 107th Street, W. 107th Street Circle and Whalen
Avenue)
The Contractor anticipates moving into this neighborhood the week of May 16.
-
Quebec Road Area (between 106th Street and Bush Lake Road)
The Contractor anticipates moving into this neighborhood on Thursday, May 19, weather
permitting.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy crews continue to work in the area. The service work will take
approximately one month. In addition to the new services, there will be a new main
installed in part of the neighborhood along with some new fittings.
-
Auto Club Road Area (Auto Club Road from Minnesota Bluffs Drive to Louisiana
Ave, Minnesota Bluffs Drive from Bloomington Ferry Road to Auto Club Road, W. 113th
Street from Minnesota Bluffs Drive to east terminus, W. 114th Street from Auto Club
Road to Minnesota Bluffs Drive, W. 114th Street Circles)
The Contractor anticipates moving into this neighborhood the week of May 23.
May 6, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
The contractor will be preparing the median beds for planting during the week of May
9. The median planting beds include not only Lyndale Avenue, but also West Old Shakopee
Road, Grand Avenue, and 97-1/2 Street. Concrete maintenance edger strips near the curb
and gutter of the medians will also be installed. There will be various lane closures
on these roads to facilitate construction.
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
The contractor will be out on Wednesday, May 11, weather permitting, along with the
environmental consultant and the certified asbestos removal contractor to dig test
holes at the intersection of Russell Avenue and 81st Street to determine the limits of
the debris.
-
Clinton Ave Area (from E 79-1/2 Street to E 82nd Street and from E 84th Street
to E 86th Street)
Sod will be installed during the week of May 9. The final lift of pavement will be
placed during the week of May 16.
-
17th Avenue (from 82nd Street to the north)
Sod will be installed during the week of May 9.
-
Baliff Area (includes Washburn, Vincent, Upton and Thomas Avenues between Old
Shakopee Road and Baliff Place)
Rain water gardens will have additional soil and mulch installed during the week of
May 9.
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Milling the road is scheduled for Tuesday, May 10, weather dependant, with paving
planned for two days later.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Concrete replacement is scheduled for Monday, May 9, weather dependant. The contractor
will also be patching and backfilling curb areas once the concrete work is complete.
Milling the road is scheduled for Wednesday, May 11, weather dependant, with paving to
follow during the week of May 16.
-
Old Cedar Avenue (between 86th Street and 87th Street)
Concrete replacement is scheduled for Monday, May 9, weather dependant. The contractor
will also be patching and backfilling curb areas once the concrete work is complete.
Milling the road is scheduled for Wednesday, May 11, weather dependant, with paving to
follow during the week of May 16. Manholes, gates valve and other items will be
adjusted to final grade after the milling occurs late next week.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
Milling the road is scheduled for Tuesday, May 10, weather dependant, with paving
planned for two days later.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The Contractor has pushed back the installation of the temporary watermain system to
the week of May 16.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
The Contractor anticipates moving into this neighborhood the week of May 9.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
The Contractor anticipates moving into this neighborhood the week of May 9.
-
Southbrook Neighborhood (Upton Road, Upton Circle, Southbrook Drive, W. 97th
Street, Xerxes Road, W. 96th Street, W. 96th Street Circle, Washburn Avenue, Vincent
Avenue)
Centerpoint Energy plans on having a gas service crew begin installation of new
services the week of May 9. The service work will take approximately one month. In
addition to the new services, there will be a new main installed in part of the
neighborhood along with some new fittings.
April 2011
April 29, 2011
2011-102 PMP Street Maintenance Project
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Centerpoint Energy anticipates completing the gas main service work early the week of
May 2. The rain during the past week delayed them a couple of days. The Contractor will
start work on the project on May 2 with removals and underground utility repair.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Centerpoint Energy completed installing new gas main crossings at Pillsbury Avenue and
Wentworth Avenue. The Contractor will start work on the project the week of May 2 with
removals and underground utility repair.
-
Old Cedar Avenue (between 86th Street and 87th Street)
The Contractor will start work on the project the week of May 2 with removals and
underground utility repair.
-
12th Avenue Area (between Old Shakopee Road and E. 97th Street, includes 13th
Avenue between E. 96th Street and E. 97th Street, 12th Avenue Circle, and E. 97th
Street)
The Contractor will start work on the project the week of May 2 with removals and
underground utility repair.
-
Briar Area (includes Briar Road from Vessey Road to Wildwood Circle, Briar
Circle, Wildwood Circle from Wildwood Road to East Terminus, Wildwood Road from 102nd
Street to Wildwood Circle)
The Contractor will begin to install the temporary watermain system during the week of
May 2 in preparation for moving into the neighborhood the week of May 16.
-
Bloomington Freeway Area (between W. 98th Street and W. 100th Street, includes
West Bloomington Freeway, W. 99th Street and Dupont Avenue)
The Contractor anticipates moving into this neighborhood the week of May 9.
-
Vincent Avenue (between Old Shakopee Road and W. 106th Street)
The Contractor anticipates moving into this neighborhood the week of May 9.
April 25, 2011
2011-102 PMP Street Maintenance Project
A preconstruction conference is schedule for the week of April 25.
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Centerpoint Energy anticipates beginning gas service work the week of April 25. The
Contractor anticipates starting work on the project on May 2, provided road
restrictions have been rescinded.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Centerpoint Energy anticipates installing new gas main crossings at Pillsbury Avenue
and Wentworth Avenue during the week of April 25.
April 15, 2011
2010-101 PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
-
Russell Avenue Area (between 81st Street and 82nd street includes 82nd Street
from Russell Avenue to Penn Avenue)
-
Clinton Ave Area (from E 79 1/2 Street to E 82nd Street and from E 84th Street
to E 86th Street)
With the improving weather, people have inquired when the project will restart. Currently
there are spring load restrictions in place that restrict the weight on any single axle on
all non-exempt trucks and commercial vehicles to a maximum of five tons on non-concrete
state highways, county highways, town roads and city streets. These went in place on March
14. Historically they have gone in place about a month earlier in February. Mn/DOT uses
actual and forecasted daily air temperatures to determine the placement and removal of
spring load restrictions. Typically the end of spring load restrictions is about eight
weeks after they went into place. We are hoping road restrictions come off around May 1,
but with the possibly freezing temperatures in the forecast that may not be realistic,
especially since it would only be about six weeks from when they went into effect. Restart
of construction will be based on road restrictions being removed and we may have to wait
until May 15 or longer based on MnDOT's calculation.
April 15, 2011
2011-102 PMP Street Maintenance Project
The Contractor anticipates starting work on the project on May 2, but this is dependent on
removal of road restrictions as described above.
-
Maplewood Area (between 1st Avenue and 2nd Avenue includes 1st Avenue and 2nd
Avenue between 95th Street and Maplewood Drive)
Centerpoint Energy anticipates beginning gas service work the week of April 23.
-
83rd Street Area (between Pillsbury Avenue and Nicollet Avenue)
Centerpoint Energy anticipates installing new gas main crossings at Pillsbury Avenue
and Wentworth Avenue during the week of April 23.
December 2010
December 10, 2010
PMP Street Improvement Project
-
Lyndale area (from 99th Street to 94th Street includes 96th Street west of
Lyndale)
Activation of the signal at 95th Street has been tentatively scheduled for Tuesday,
December 14, weather permitting.
For more information, contact:
Shelly Pederson, City Engineer
1700 W. 98th Street
PH: 952-563-4870, FAX: 952-563-4868
E-mail: engineering@ci.bloomington.mn.us